ML12136A267
| ML12136A267 | |
| Person / Time | |
|---|---|
| Site: | Byron, Braidwood |
| Issue date: | 05/23/2012 |
| From: | Michael Mahoney Plant Licensing Branch III |
| To: | Pacilio M Exelon Nuclear |
| Michael Mahoney | |
| References | |
| TAC ME8296, TAC ME8297, TAC ME8298, TAC ME8299 | |
| Download: ML12136A267 (4) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 23, 2012 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
BYRON STATION, UNIT NOS 1 AND. 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (TAC NOS. ME8296, ME8297, ME8298, AND ME8299)
Dear Mr. Pacilio:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated March 20, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML120830222), Exelon Generation Company, LLC submitted an affidavit dated January 19, 2012, executed by J. A.
Gresham, Manager, Regulatory Compliance, Westinghouse Electric Company LLC (Westinghouse), requesting that information designated as proprietary in the following document be withheld from public disclosure pursuant to paragraph (b)(4) of Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
WCAP-17330-P, Revision 1, "H*: Resolution of NRC Technical Issue Regarding Tubesheet Bore Eccentricity (Model F IModel D5," dated June 2011.
WCAP-17330-P, Revision 1 Erratum The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(a) The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouse's competitors without license from Westinghouse constitutes a competitive advantage over other companies.
(b) It consists of supporting data, including test data, relative to a process (or component, structure, tool, method, etc.), the application of which secures a competitive economic advantage, e.g., by optimization or improved marketability.
(c) Its use by a competitor would reduce the expenditure of resources or improve his competitive position in design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.
(d) It reveals cost or price information, production capabilities, budget levels, or commercial strategies of Westinghouse, its customers or suppliers.
M. Pacilio
- 2 (e) It reveals aspects of past, present, or future Westinghouse or customer funded development plans and programs of potential commercial value to Westinghouse.
(f) It contains patentable ideas, for which patent protection may be desirable.
We have reviewed your submittal in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 1 03(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You should also understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, please contact me at (301 )-415-3867.
Si~1eIY, () '111./-x P/~ ()Y~;J Michael Mahoney, Pr#,ct Manager Plant Licensing Bra?l~ 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-454, STN 50-455, STN 50-456, and STN 50-457 cc: See next page
BYRON STATION, UNIT NOS 1 AND. 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 cc:
J. A. Gresham, Manager - Regulatory Compliance Westinghouse Electric Company Nuclear Services 1000 Westinghouse Drive Cranberry Township, PA 16066 Additional distribution via listserv
M. Pacilio
- 2 (e) It reveals aspects of past, present, or future Westinghouse or customer funded development plans and programs of potential commercial value to Westinghouse.
(f) It contains patentable ideas, for which patent protection may be desirable.
We have reviewed your submittal in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You should also understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information.
In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, please contact me at (301 )-415-3867.
Sincerely, IRAI Michael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-454, STN 50-455, STN 50-456, and STN 50-457 cc: See next page DISTRIBUTION:
PUBLIC LPL3-2 R/F RidsNrrDorlLpl3-2 Resource RidsNrrPMByron Resource RidsNrrLASRohrer Resource RidsAcrsAcnw_MailCTR Resource RidsOgcRp Resource RidsRgn3MailCenter Resource RidsNrrDorlDpr Resource RidsNrrPMBraidwood Resource ADAMS Accession No ML12136A267 OFFICE NAME DATE LPL3-2/PM MMahoney 5/17/12 LPL3-21LA SRohrer 5/15 /12 LPL3-2/BC JZimmerman 5/21/12 LPL3-2/PM MMahoney 5/23/12 OFFICIAL RECORD COpy