Entergy Pre-Filed Evidentiary Hearing Exhibit ENT000403 - Excerpt from NL-09-079, Letter from Fred Dacimo, Entergy, to NRC Document Control Desk, Eply to Request for Additional Information Regarding Offsite Power, Refueling Cavity, and Unit
ML12130A511
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 06/12/2009
From: Dacimo F
Entergy Nuclear Northeast
To:
Office of Nuclear Reactor Regulation
SECY RAS
Shared Package
ML12130A510 List:
References
RAS 22426, 50-247-LR, 50-286-LR, ASLBP 07-858-03-LR-BD01
Download: ML12130A511 (4)


Text

ENT000403 Submitted: May 9, 2012 Enteray Nuclear Northeast Indian Point Energy Center SEntergy 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel (914) 788-2055 Fred Dacimo Vice President License Renewal NL-09-079 June 12, 2009 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Reply to Request for Additional Information Regarding Offsite Power, Refueling Cavity, and Unit 2 Auxiliary Feedwater Pump Room Fire Event Indian Point Nuclear Generating Unit Nos. 2 & 3 Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64

REFERENCES:

1. NRC Letter dated May 20, 2009, "Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application - Offsite Power, Refueling Cavity, and Unit 2 Auxiliary Feedwater Pump Room Fire Event

Dear Sir or Madam:

Entergy Nuclear Operations, Inc is providing, in Attachment I, the additional information requested in the referenced letter pertaining to NRC review of the License Renewal Application for Indian Point 2 and Indian Point 3. The additional information provided in this transmittal addresses staff questions regarding Offsite Power, Refueling Cavity, and Unit 2 Auxiliary Feedwater Pump Room Fire Event. Attachment 2 consists of Revision 9 to the list of regulatory commitments.

If you have any questions, or require additional information, please contact Mr. Robert Walpole at 914-734-6710.

I declare under penalty of perjury that the foregoing is true and correct. Executed on Sincerely, kiz~

NL-09-079 Page 2 of 2 FRD/dmt

Attachment:

1. Reply to Request for Additional Information Regarding Offsite Power, Refueling Cavity, and Unit 2 Auxiliary Feedwater Pump Room Fire Event
2. List of Regulatory Commitments, Revision 9 cc: Mr. Samuel J. Collins, Regional Administrator, NRC Region I Mr. Sherwin E. Turk, NRC Office of General Counsel, Special Counsel Ms. Kimberly Green, NRC Safety Project Manager Mr. Kenneth Chang, NRC Branch Chief, Engineering Review Branch I Mr. John Boska, NRR Senior Project Manager Mr. Paul Eddy, New York State Department of Public Service NRC Resident Inspector's Office Mr. Francis J. Murray, President and CEO, NYSERDA

ATTACHMENT 1 TO NL-09-079 Reply to Request for Additional Information Regarding Offsite Power, Refueling Cavity, and Unit 2 Auxiliary Feedwater Pump Room Fire Event ENTERGY NUCLEAR OPERATIONS, INC.

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 & 3 DOCKET NOS. 50-247 AND 50-286

Attachment I NL-09-079 Page 22 of 51 Table 3.4.2-5-3-1P2 Circulating Water System (CIRC)

Intended Aging Effect Aging Management NUREG0 Table I Copntt Type Component y eFunction nMteildevrnmn Requiring Management Programs Vol. 2NoeItem 1801Item Pressure Change of Periodic Surveillance -- -- 408 Expansion int boundary Elastomer Air -outdoor (ext) material and Preventive G properties Maintenance P eNe VILI.E-1 3.4.1-11 408 Piping boundary Carbon steel Soil (ext) Loss of material Buried Piping And Tanks (S-01) C aInspection Pressure NeiNe VIII.H-8 3.4.1-28 408 Piping boundary Carbon steel Air outdoor (ext) Loss ofme External Surfaces S A Noe VIII.G-36 3.4.1-8 408 Piping Pressure Carbon steel Raw water (int) NOe Periodic Surveillance (S-12) E boundary Loss of material and Preventive Maintenance Pressure Nee eA VJII.H-8 3.4.1-28 408 Pump casing boundary Carbon steel Air-outdoor (ext) Loss of material Axternaq N41e VIII.G-36 3.4.1-8 498 Pump casing Pressure Carbon steel Raw water (int) Nene Periodic Surveillance (S-12 E boundary Loss of material and Preventive Maintenance Pressure Periodic Surveillance VIII.G-36 3.4.1-8 408 Pump casing boundary Carbon steel Raw water (ext) Loss of material and Preventive (S-12) E Maintenance