May 7, 2012 MEMORANDUM TO:
John R. Jolicoeur, Chief Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation FROM:
Joseph A. Golla, Project Manager
/RA/
Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
SUBJECT:
NOTICE OF PUBLIC TELECONFERENCE BETWEEN THE U.S.
NUCLEAR REGULATORY COMMISSION (NRC) STAFF AND THE BOILING WATER REACTOR OWNERS GROUP (BWROG)
ON EMERGENCY CORE COOLING SYSTEM (ECCS) SUCTION STRAINER ISSUES DATE AND TIME:
Thursday, May 24, 2012 1:00 p.m. - 4:00 p.m.
PURPOSE:
This teleconference is a follow-up to the March 28, 2012, public meeting on ECCS suction strainer issues. The purpose of the call is to further discuss the insulation damage pressure issue and the NRC staff comments on the BWROGs bypass test plan and chemical effects strategy outline. The agenda is enclosed with this notice.
CATEGORY 2*:
This is a Category 2 teleconference. The public is invited to participate in this teleconference by discussing regulatory issues with the NRC. Public comments will be solicited toward the end of the call.
NOTE:
Interested members of the public can participate in this teleconference by calling the contact person listed below.
CONTACT:
Joseph Golla, NRR 301-415-1002 Joe.Golla@nrc.gov
- Commissions Policy Statement on Enhancing Public Participation in NRC Meetings, (67 Federal Register 36920), May 2002.
REFERENCE DOCUMENTS:
- 1. BWROG ECCS Suction Strainer BWR Downstream Effects Bypass Test Plan (Agencywide Documents Access and Management System (ADAMS) Accession No. ML11335A262)
- 2. Feedback on BWROG-11060, BWROG [Boiling Water Reactor (BWR) Owners Group] ECCS [emergency core cooling system]
Suction Strainers Bypass Test Plan (ADAMS Accession No. ML12017A158)
- 3. BWROG ECCS Suction Strainer Chemical Effects Resolution Strategy Plan and Flowchart (ADAMS Accession No. ML11335A264)
- 4. Feedback on BWROG-11061, BWROG [Boiling Water Reactor (BWR) Owners Group] [emergency core cooling system] Suction Strainers Chemical Effects Strategy Outline (ADAMS Accession No. ML12013A159)
- 5. Additional informal staff comments on BWROG Chemical Effects Strategy Outline (ML12081A045).
- 6. BWROG draft responses to NRC staff feedback on Bypass Test Plan (12093A135).
- 7. BWROG draft responses to NRC staff feedback on Chemical Effects Strategy Outline (ML12093A141).
- 8. BWROG presentation slides from March 28, 2012, meeting (ML12093A143).
Portions of the above documents will be the subject of the telecom discussions.
Project No. 691
Enclosure:
Agenda
- 3. BWROG ECCS Suction Strainer Chemical Effects Resolution Strategy Plan and Flowchart (ADAMS Accession No. ML11335A264)
- 4. Feedback on BWROG-11061, BWROG [Boiling Water Reactor (BWR) Owners Group] [emergency core cooling system] Suction Strainers Chemical Effects Strategy Outline (ADAMS Accession No. ML12013A159)
- 5. Additional informal staff comments on BWROG Chemical Effects Strategy Outline (ML12081A045).
- 6. BWROG draft responses to NRC staff feedback on Bypass Test Plan (12093A135).
- 7. BWROG draft responses to NRC staff feedback on Chemical Effects Strategy Outline (ML12093A141).
- 8. BWROG presentation slides from March 28, 2012, meeting (ML12093A143).
Portions of the above documents will be the subject of the telecom discussions.
Project No. 691
Enclosure:
Agenda DISTRIBUTION:
See next page ADAMS Accession No.: ML12123A030 NRC-001 OFFICE PLPB/PM PLPB/LA PLPB/BC NAME JGolla DBaxley JJolicoeur DATE 5/7/2012 5/3/2012 5/7/2012 DISTRIBUTION FOR NOTICE OF PUBLIC TELECONFERENCE WITH THE BOILING WATER REACTOR OWNERS GROUP ON EMERGENCY CORE COOLING SUCTION STRAINER ISSUES Date:
PUBLIC PLPB R/F RidsNrrOd RidsNrrDpr RidsNrrDprPlpb RidsNrrLADBaxley RidsOpaMail PMNS RidsOgcMailCenter RidsAcrsAcnwMailCenter RidsNrrDss RidsNrrDssSsib RidsNrrDe RidsNrrDeEsgb SBailey SSmith PKlein EGeiger MYoder JGolla JJolicoeur GMakar
DRAFT AGENDA UNITED STATES NUCLEAR REGULATORY COMMISSION (NRC) TELECOM WITH THE BOILING WATER REACTOR (BWR) OWNERS GROUP (BWROG)
REGARDING BWR EMERGENCY CORE COOLING SYSTEM (ECCS) SUCTION STRAINER ISSUES MAY 24, 2012 Topic Lead Insulation Damage Pressure NRC Spherical Zone of Influence BWROG Use of Tap Water for Bypass Testing BWROG Debris Strainer Coverage (bypass testing)
BWROG Fluid Approach Velocity (bypass testing)
BWROG Chugging Effect on Debris (bypass testing)
NRC/BWROG Discussion of BWROG Preliminary Responses NRC to Staff Feedback on the Chemical Effects Strategy Outline Discussion of NRC Staffs Informal Comments BWROG on Chemical Effects Strategy Outline Addressing Unqualified Coatings BWROG Comments/Questions PUBLIC ENCLOSURE
cc w/encl:
BWROG Chairman BWROG ECCS Suction Strainers Frederick P. Schiffley Committee Chairman Exelon Generation Co., LLC Steve Scammon Cornerstone II at Cantera slscammon@energy-northwest.com 4300 Winfield Road Warrenville, IL 60555 frederick.schiffley@exeloncorp.com BWROG Project Manager Ed Asbury GE-Hitachi Nuclear Energy PO Box 780 M/C F-12 3901 Castle Hayne Road Wilmington, NC 28402 Ed.Asbury@ge.com BWROG Program Manager Craig J. Nichols GE-Hitachi Nuclear Energy PO Box 780 M/C F-12 3901 Castle Hayne Road Wilmington, NC 28402 craig.nichols@ge.com GEH Senior Vice President Jerald G. Head Senior Vice President, Regulatory Affairs GE-Hitachi Nuclear Energy PO Box 780 M/C A-18 Wilmington, NC 28401 jerald.head@ge.com