Callaway Plant, Unit 1 (Callaway)
Callaway Plant, Unit 1 (Callaway)
License Renewal Process License Renewal Process License Renewal Process License Renewal Process and and Environmental Scoping Meeting Environmental Scoping Meeting March 14, 2012 March 14, 2012
Purpose of Todays Meeting 3/4Provide overview of license renewal review process review process
- Safety review
- Environmental review 3/4Receive public input on environmental review 2
3/4NRCs Governing Statutes
- Atomic Energy Act
- National Environmental Policy Act (NEPA)
NRC Regulatory Oversight 3/4NRCs Mission
- Protect Public Health and Safety
- Promote Common Defense and Security
- Protect Environment 3
3/4 Current Safety Performance http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html Ongoing Regulatory Oversight p
g 3/4 Emergency Planning 3/4 Security 4
NRC Response to Fukushima 3/4 The NRCs response to Fukushima is as a current operating issue 3/4 Increased inspections at operating facilities 3/4 NRC Near-Term Task Force issued its report July of 2011 3/4 Continued operations and continued licensing activities do not pose an imminent risk to public health and safety 3/4 The staff has prioritized the recommendations and identified additional ones 3/4 The NRC plans to issue initial Orders and Request for Information (50.54(f) letters) this month 3/4 More information:
3/4http://www.nrc.gov/japan/japan-info.html 5
3/4License renewal application received on December 19 2011 Callaway License Renewal Review December 19, 2011 The license expires on October 18, 2024 6
3/4Acceptance/Sufficiency review 3/4R i
t t
f li ti Docketing and Sufficiency of Application 3/4Review contents of application
- Technical information
- Technical Specifications
- Environmental Report 3/4Docket 7
License Renewal Process NRC Renewal NRC Renewal License Renewal License Renewal A
li ti A
li ti Safety Safety Review Review Review by Review by ACRS ACRS H
i H
i Environmental Environmental Review Review NRC Renewal NRC Renewal Decision Decision Application Application submitted to NRC submitted to NRC Hearings*
Hearings*
Consultation Consultation and Comment and Comment
- If a Request for Hearing is Granted 8
3/4 The ongoing regulatory process is adequate to ensure the safety of all currently operating plants License Renewal Safety Principles 3/4 The same plant operating rules apply during the renewal term
- NRC applies additional conditions for aging management 9
Safety Review Focus 3/4 Safety review focus is on the effects of aging on:
Safety-related systems, structures, and components (SSCs)
Nonsafety-related SSCs which, if they failed, could affect safety-related SSC functions y
SSCs relied upon for compliance with regulations for:
Fire protection Environmental qualification Pressurized thermal shock Anticipated transients without scram Station blackout 3/4 Safety review is to determine if aging effects will be effectively managed 10
3/4Technical review by NRC staff
- Review application and supporting documentation Safety Review Process
- On-site audits
- Issue Safety Evaluation Report 3/4On-site inspections by NRC staff 3/4Independent review by the Advisory Committee on Reactor Safeguards 11
Application Received December 19, 2011 Notice of Opportunity for Hearing February 24, 2012 Notice of Intent for Scoping February 24, 2012 E
i t l S i
M ti M
h 14 2012 Safety Review Milestones (tentative) 12 Environmental Scoping Meeting March 14, 2012 Hearing Opportunity Closes April 24, 2012 Scoping Comments Due April 24, 2012 SER with Open Items April 2013 ACRS Subcommittee Meeting May 2013 Final SER Issued September 2013 ACRS Full Committee Meeting October 2013 Commission Decision (without hearing) December 2013
3/4National Environmental Policy Act (NEPA)
- Informs Federal decision making f
Environmental Review (10 CFR Part 51)
- Public disclosure of environmental impacts and other considerations 3/4NRCs Environmental Regulations 10 CFR Part 51 3/4Staff prepares an Environmental Impact Statement 13
Staff Evaluates Impacts to Resources
- Fish and Wildlife
- Water and Air Resources Environmental Impact Statement
- Historical or Cultural Resources
- Taxes, Community Development, Environmental Justice
- Human Health
- Land Use 14
Scoping Process 3/4Generic Environmental Impact Statement Environmental Review (10 CFR Part 51) 3/4Generic Environmental Impact Statement http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr1437/
3/4Site-specific Supplemental Environmental Impact Statement 3/4New and significant information on generic conclusions reached in the GEIS 15
Scoping and Public Involvement 3/4What is unique about your community?
3/4What local environmental issues should 3/4What local environmental issues should the NRC examine?
3/4What reasonable alternatives are appropriate for the area?
16
Role of Public Comments Environmental Review EIS EIS Safety Safety Ad i C
itt Ad i C
itt Public Comments on Public Comments on Environmental Review Environmental Review License License Renewal Renewal Decision Decision EIS EIS Regional Regional Inspections Inspections Evaluation Evaluation Report Report Hearing Hearing*
- If a Request for Hearing is Granted Advisory Committee on Advisory Committee on Reactor Safeguards Reactor Safeguards Independent Review Independent Review License Renewal License Renewal Application Application 17
How to Submit Comments on the Environmental Review 9 Online at http://www.regulations.gov Enter ID :
NRC-2012-0001 9 By fax (reference Callaway license renewal):
at 301-492-3446 Comments will not be edited to remove identifying information Comments must be submitted by April 24th 18
9 By mail (please reference Callaway license renewal):
Ms. Cindy Bladey Chief Rules Announcements and Directives Branch How to Submit Comments on the Environmental Review Chief, Rules, Announcements, and Directives Branch Office of Administration, Mail stop: TWB-05-B01M US Nuclear Regulatory Commission Washington, DC 20555-0001 9 In person at NRC Headquarters Comments must be submitted by April 24th 19
Application Received December 19, 2011 Notice of Opportunity for Hearing February 24, 2012 Notice of Intent for Scoping February 24, 2012 E
i t l S i
M ti M
h 14 2012 Environmental Review Milestones (tentative)
Environmental Scoping Meeting March 14, 2012 Hearing Opportunity Closes April 24, 2012 Scoping Comments Due April 24, 2012 Draft SEIS Issued February 2013 Draft SEIS Public Meeting March 2013 Draft SEIS Comments Due April 2013 Final SEIS Issued September 2013 20
Project Manager Information Carmen Fells (800) 368-5642 ext. 6337 C
F ll @
Carmen.Fells@nrc.gov Brian Harris (800) 368-5642 ext. 2277 Brian.Harris2@nrc.gov 21
Where to view documents Documents located at:
- Callaway County Public Library 710 Court Street Fulton, Missouri 65251 Documents can be viewed on the NRCs Web site:
www.nrc.gov/reactors/operating/licensing/renewal/applications/
callaway.html 22