Notice of Regulatory Conference with Virginia Electric Power Company (VEPCO) to Discuss One Apparent Violation (AV) of Technical Specification (TS) 5.4.1.A Associated with the Unit 2 H (2H) Emergency Diesel Generator Gasket Failure
ML12093A228
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 04/02/2012
From: Gerald Mccoy
NRC/RGN-II/DRP/RPB5
To: Heacock D
Virginia Electric & Power Co (VEPCO)
Catherine Morrison 404-997-4559
References
Download: ML12093A228 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 2, 2012 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060

SUBJECT:

MEETING ANNOUNCEMENT - REGULATORY CONFERENCE MEETING -

NORTH ANNA POWER STATION, DOCKET NOS. 50-338 AND 50-339

Dear Mr. Heacock:

This letter confirms the email between Mr. F. Mladen of your staff and myself on March 29, 2012, concerning a Regulatory Conference being conducted at your request, which has been scheduled for April 20, 2012, from 1:00 p.m. to 3:00 p.m. Eastern Daylight Time (EDT). The enclosed meeting notice provides additional details.

The purpose of this meeting is to discuss one Apparent Violation (AV) of Technical Specification (TS) 5.4.1.a associated with the Unit 2 H (2H) emergency diesel generator gasket failure. The results of NRCs inspection of this issue are available in NRC inspection report 05000338/2012008 and 05000339/2012008, available from the US NRCs Agencywide Document Access and Management System (ADAMS) (ML12082A045).

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's ADAMS.

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

VEPCO 2 Should you have any questions concerning this meeting, please contact me at (404) 997-4551.

Sincerely,

/RA/

Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos. 50-338, 50-339 License Nos. NPF-4, NPF-7

Enclosure:

As stated

__ML12093A228_____________ X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE GJM1 for GJM1 NAME SNinh GMcCoy DATE 04/02/2012 04/02/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO VEPCO 3 cc w/encl: Donald R. Taylor Mr. Gerald T. Bischof Licensing Supervisor Site Vice President North Anna Power Station North Anna Power Station P. O. Box 402 Virginia Electric & Power Company Mineral, VA 23117-0402 Electronic Mail Distribution Michael M. Cline Fred Mladen Director Director, Station Safety & Licensing Virginia Department of Emergency Services Virginia Electric and Power Company Management Electronic Mail Distribution Electronic Mail Distribution Michael Crist Executive Vice President Plant Manager Old Dominion Electric Cooperative North Anna Power Station Electronic Mail Distribution Virginia Electric & Power Company Electronic Mail Distribution County Administrator Louisa County Lillian M. Cuoco, Esq. P.O. Box 160 Senior Counsel Louisa, VA 23093 Dominion Resources Services, Inc.

Electronic Mail Distribution Tom Huber Director, Nuclear Licensing & Operations Support Innsbrook Technical Center Electronic Mail Distribution Ginger L. Rutherford Virginia Electric and Power Company Electronic Mail Distribution Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, VA 23209 Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission P.O. Box 490 Mineral, VA 23117

VEPCO 4 Letter to David A. Heacock from Gerald J. McCoy dated April 2, 2012

SUBJECT:

MEETING ANNOUNCEMENT - REGULATORY CONFERENCE MEETING -

NORTH ANNA POWER STATION, DOCKET NOS. 50-338 AND 50-339 Distribution w/encl:

C. Evans, RII EICS L. Douglas, RII EICS OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMNorthAnna Resource Region II Administrators Secretary Region II DRP Division Secretary Region II Division Directors and Deputies Region II Counsel Region II State Liaison Officer Region II Public Affairs Officer Region II Resource Management Branch Region II Receptionist Region II Regional Coordinator OEDO Headquarters Operation Officer PMNS

SUBJECT:

REGULATORY CONFERENCE WITH VIRGINIA ELECTRIC POWER COMPANY (VEPCO)

FACILITY: North Anna Power Station DOCKETS: 50-338 and 50-339 DATE & TIME: Friday, April 20, 2012, from 1:00 p.m. to 3:00 p.m. (EDT)

LOCATION: USNRC, Region II, 245 Peachtree Center Ave. NE Suite 1200 Atlanta, GA 30303 PURPOSE: The purpose of the meeting is to discuss one Apparent Violation (AV) of Technical Specification (TS) 5.4.1.a associated with the Unit 2 H (2H) emergency diesel generator gasket failure. The results of NRCs inspection of this issue are available in NRC inspection report 05000338/2012008 and 05000339/2012008, available from the Agencywide Document Access and Management System (ADAMS) (ML12082A045). The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov and contains information regarding conduct of NRC meetings.

CATEGORY: This is a Category 1 meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with NRC after the business portion of the meeting but before the meeting is adjourned.

The NRC provides reasonable accommodation to individuals with disabilities, where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript or other information from the meeting in another format (e.g., braille, large print),

please notify the NRC=s meeting contact listed below. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

NRC OFFICE Region II PARTICIPATING:

OTHER ORGANIZATIONS PARTICIPATING: None Enclosure

2 PARTICIPANTS: NRC V. McCree, Regional Administrator, Region II (RII)

R. Croteau, Director, Division Reactor Projects (DRP), RII W. Jones, Deputy Director, DRP, RII G. McCoy, Chief, Reactor Projects Branch 5, RII J. Munday, Director Reactor Safety, RII G. Kolcum, Senior Resident Inspector, North Anna R. Clagg, Resident Inspector, North Anna C. Evans, Director, Enforcement & Investigation Coordination Staff (EICS)

G. McDonald, Senior Reactor Analyst, DRP, RII LICENSEE (partial list)

G. Bischof, Site Vice President F. Mladen, Director, Nuclear Safety and Licensing MEETING Gerald J. McCoy CONTACT: 404-997-4551 Gerald.McCoy@nrc.gov AUDIO TELE- Interested members of the public can participate in this meeting via a toll-free CONFERENCING audio teleconference. Please contact the NRC meeting contact in advance of the meeting to obtain teleconferencing information.

Enclosure