UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 15, 2012 Mr. T. A. Lynch Vice President Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant Farley Nuclear Plant P.O. Drawer 470 BIN B500 Ashford, AL 36312
SUBJECT:
JOSEPH M. FARLEY NUCLEAR PLANT - EMERGENCY PREPAREDNESS INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Lynch:
From May 7-11, 2012, the NRC will perform baseline Emergency Preparedness inspections at the Joseph M. Farley Nuclear Plant, (NRC Inspection Procedures: 71114.01 - Exercise Evaluation and the Emergency Preparedness Sections of 71151, Performance Indicator Verification).
Experience has shown that this inspection is resource-intensive both for the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Bill Oldfield of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Mark E. Speck at (404) 997-4759 (Mark.Speck@nrc.gov) or the Plant Support Branch 1 Chief, Brian Bonser at (404) 997-4653.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document
SNC 2
Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Brian R. Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 50-348, 50-364 License No. NPF-2, NPF-8
Enclosure:
As stated cc w/encl.: (See page 3)
ML12081A267 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII: DRS/PSB1 RII: DRS/PSB1 SIGNATURE RA/BB For MS RA/BB NAME M. SPECK B. BONSER DATE 03/14/2012 03/14/2012 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO
SNC 3
cc w/encl:
S. Kuczynski Chairman, President and CEO Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution J. L. Pemberton SVP & General Counsel-Ops & SNC Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution D. G. Bost Chief Nuclear Officer Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Dennis R. Madison Vice President Edwin I. Hatch Nuclear Plant Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Paula Marino Vice President Engineering Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution T. E. Tynan Site Vice President Vogtle Electric Generating Plant Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution M. J. Ajluni Nuclear Licensing Director Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Mark Williams Commissioner Georgia Department of Natural Resources Electronic Mail Distribution B. D. McKinney, Jr.
Regulatory Response Manager Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution D. W. Daughhetee Licensing Engineer Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution T. D. Honeycutt Regulatory Response Supervisor Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution L. Mike Stinson Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution N. J. Stringfellow Licensing Manager Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution L. P. Hill Licensing Supervisor Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution L. L. Crumpton Administrative Assistant, Sr.
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution William D. Oldfield Principal Licensing Engineer Joseph M. Farley Nuclear Plant Electronic Mail Distribution Todd L. Youngblood Plant Manager Joseph M. Farley Nuclear Plant Electronic Mail Distribution John G. Horn Site Support Manager Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution (cc w/encl contd - See page 4)
SNC 4
cc w/encl. (continued from pg 3)
Senior Resident Inspector U.S. Nuclear Regulatory Commission Joseph M. Farley Nuclear Plant P. O. Box 620 Ashford, AL 36312 Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Mark Culver Chairman Houston County Commission P. O. Box 6406 Dothan, AL 36302 James L. McNees, CHP Director Office of Radiation Control Alabama Dept. of Public Health P. O. Box 303017 Montgomery, AL 36130-3017 Donald E. Williamson State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 30317 Montgomery, AL 36130-3017 Judson H. Turner Director Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution
Enclosure Document Request List Inspection Dates:
May 7-11, 2012 Inspection Procedures:
IP 71114.01 Exercise Evaluation IP 71151 Performance Indicator Verification Note: This is a list of the documents to be delivered to the NRC Region II Office (Attention:
Mark Speck, 245 Peachtree Center Avenue, NE, Suite 1200, Atlanta, GA 30303-1257) and/or provided to the Team Lead Inspector upon arrival for the inspections. The current version of these documents is expected unless specified otherwise. Electronic media is preferred, if readily available (the preferred file format is Word or searchable.pdf files on CDROM or thumb drive). Please organize the information as it is arranged below (e.g. a folder labeled Miscellaneous). It is not the intent that large or burdensome data be scanned for this purpose.
This data will be inspected using original documentation. If there are questions regarding the documents requested, please do not hesitate to contact the lead inspector.
EP1 Exercise Evaluation Drill and exercise related procedures Core damage assessment procedure Dose assessment procedure Special/emergency exposure procedure Potassium Iodide distribution procedure Assembly/accountability procedure Emergency Facility Activation procedures Previous two exercise packages: scenario timeline drill reports or assessment, and respective Final FEMA/ DHS exercise reports All drill reports within inspection period Current exercise package: scenario timeline, expected Drill and Exercise Performance opportunities, exercise objectives, radiological assumptions, and scope of play and participation Corrective action program entries related to the exercises and drills for the two year inspection period EP01/EP02/EP03 Performance Indicators (PI) Verification Governing document for the performance indicator process Drill and Exercise Performance (DEP), Emergency Response Organization (ERO), and Alert and Notification System (ANS) PI data submitted for the two year inspection period DEP documentation and evaluations for the two year inspection period Current ERO roster Corrective action program entries related to performance indicators (i.e DEP, ERO training and participation, and ANS) for the two year inspection period Miscellaneous Procedures Current Emergency Plan and Emergency Action Levels Safety Evaluation Report approved Emergency Plan and Emergency Action Levels Current Emergency Plan implementing procedures Corrective Action Program procedures