Letter Sequence Request |
---|
|
|
MONTHYEARML1109005662011-03-30030 March 2011 N1-14-CMP-001 Use of Weld Overlays as an Alternative Repair Technique for Steam Generator Hot Leg Nozzles Project stage: Request ML11153A1342011-06-0909 June 2011 Request for Additional Information Regarding Use of Weld Overlays as an Alternative Repair Technique for Steam Generator Hot Leg Nozzles Project stage: RAI ML11187A3232011-06-29029 June 2011 N1-14-CMP-001, Use of Weld Overlays as an Alternative Repair Technique for Steam Generator Hot Leg Nozzles Response to Request for Additional Information Project stage: Response to RAI ML1131802962011-11-10010 November 2011 N1-14-CMP-001 Use of Weld Overlays as an Alternative Repair Technique for Steam Generator Hot Leg Nozzles Response to Request for Additional Information Project stage: Response to RAI ML11348A2192012-01-27027 January 2012 Relief Request N1-14-CMP-001, Regarding the Use of Weld Overlays as an Alternative Repair Technique Project stage: Acceptance Review ML12058A4152012-02-23023 February 2012 Relief Request N1-I4-CMP-001, Justification of Length of Proposed Weld Overlay for Steam Generator Hot Leg Nozzles Project stage: Request ML12067A1332012-03-13013 March 2012 Relief Request (RR) N1-I4-CMP-001, Revised Safety Evaluation Regarding the Use of Weld Overlays as an Alternative Repair Technique Project stage: Approval 2011-06-09
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) 05000339/LER-2024-001, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant 05000338/LER-2024-001, Automatic Reactor Trip Due to Prni High Negative Rate2024-07-25025 July 2024 Automatic Reactor Trip Due to Prni High Negative Rate ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24165A1462024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 IR 05000338/20240102024-05-24024 May 2024 NRC Fire Protection Team Inspection (FPTI) Report 05000338/2024010 and 05000339/2024010 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24110A1502024-04-18018 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24110A1392024-04-18018 April 2024 Annual Environmental Operating Report ML24110A1462024-04-18018 April 2024 Independent Spent Fuel Storage Installation (Sfsi) - Annual Radiological Environmental Operating Report ML24087A0572024-04-16016 April 2024 Correction to Issuance of Amendment Nos. 296 and 279 ML24088A2692024-03-27027 March 2024 Core Operating Limits Report Cycle 31 Pattern Sos Revision 0 ML24086A4292024-03-25025 March 2024 Response to Request for Additional Information Associated with Alternative Request N1-I5-NDE-007 Request to Deter Additional Required Reactor Coolant Pump Casing Inspection ML24082A2742024-03-22022 March 2024 Request for Approval of Alternative Request N1-I5-NDE-007 to Deter Additional Required Reactor Coolant Pump Casing Inspection ML24086A4682024-03-21021 March 2024 Summary of Facility Changes, Tests and Experiments ML24005A0042024-03-18018 March 2024 Issuance of Amendment Nos. 296 and 279, Regarding Revised Emergency Plan for Relocation of the Technical Support Center ML24074A3012024-03-14014 March 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000338-2024403 and 05000339-2024403) IR 05000338/20244012024-03-0808 March 2024 Security Baseline Inspection Report 05000338/2024401, 05000339/2024401 and 07200016/2024401 IR 05000338/20230062024-02-28028 February 2024 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2023006 and 05000339/2023006 2024-09-23
[Table view] |
Text
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 February 23, 2012 U.S. Nuclear Regulatory Commission Serial No.12-093 Attention: Document Control Desk NLOS/ETS One White Flint North Docket No. 50-338 11555 Rockville Pike License No. NPF-4 Rockville, MD 20852-2738 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
NORTH ANNA POWER STATION UNIT 1 RELIEF REQUEST N1-14-CMP-001 JUSTIFICATION OF LENGTH OF PROPOSED WELD OVERLAY FOR STEAM GENERATOR HOT LEG NOZZLES In a March 30, 2011 letter (Serial No.11-120), as supplemented on June 29, 2011 (Serial No.11-366) and November 10, 2011 (Serial No.11-625), Dominion requested NRC approval for proposed alternatives to certain (ASME Code) Section XI-2004 Edition requirements associated with Steam Generator (SG) hot leg nozzle repairs. The proposed alternative will permit the application of a full structural weld overlay (FSWOL) on the Steam Generator hot leg nozzles for North Anna Unit 1. The weld overlays are required to mitigate the potential for primary water stress corrosion cracking (PWSCC) susceptibility of the dissimilar metal welds (DMW). In a January 27, 2012 letter, the NRC approved Relief Request N1-/4-CMP-001. However, the accompanying safety evaluation identifies, as ~
staff understanding, that the weld overlay length would be 0.75 -vRt applied axially on bot~
sides of the susceptible weld. !
I i
In a phone call on February 15, 2012 with the NRC staff to discuss the sizing requirements I for the FSWOLs delineated in the staff's SER, Dominion informed the NRC that it was physically impossible to meet one of the requirements delineated in the staff's safety evaluation report (SER. Specifically, the 0.75v'Rt length for the weld overlay cannot be used on the pipe end due to structural interferences from the SG lower support assembly]
Extension of the overlay further towards the SG is not feasible due to the excessiv~
amount of nozzle machining that would be necessary. I I
The proposed FSWOL has been designed to meet the relevant Code requirements (speoifically NB-3200) for transfer of the load for a postulated flaw back into the bas~
material. The associated analysis considered design basis loads with the required safety factors applied. Therefore, the proposed FSWOL
- meets quality and safety standards)I However, the SER discussed imposing a 0.75y'Ht length. This is mentioned in Cod~
Case N-740-2 as a length that usually satisfies load redistribution. However, if a location'~
actual loading is small, load redistribution can be achieved with much shorter lengths. Ir this case, this is achieved at a distance less than 0.75\/Rt. To ensure future lSI of th¢ DIVIWs will meet Code Case N-770-1 requirements, the weld overlay length on each sid~
of the DMW will need to be somewhat greater than the length required to satisfy NB-320p requirements. Specifically, the overlay will extend on each side of the susceptible materi,/
I
Serial No. 12-0~3 Docket No. 50-3~8 Justification for L~~~~ ~v~;~
Page 2 013 by a minimum of 3.89" on the nozzle side and 4.98" minimum on the stainless steel sile before it ties back into the adjoining base metal.
In summary, the proposed weld overlay le.ngth~ selected are less t~an the I~~gl h calculated by 0.75*lRt due to the constraints Imposed by the physical condltlo~s associated with the DMW. However, the weld overlay length is bounded by analysis al d technically acceptable. The attachment provides sketches and a photo that shows t e WOL dimensions and the physical obstructions, respectively.
Dominion requests the NRC's approval of the proposed sizing of the FSWOL on the Stea Generator hot leg nozzles.
As noted in the original relief request the applicable stress reports will be provided to tIe NRC prior to entry into Mode 4 following the completion of the weld overlays.
If you have any questions regarding this submittal, please contact Mr. Thomas Shaub t (804) 273-2763.
Very truly yours,
~-L.
Leslie N. Hartz u.... ,-',
~~
Vice President - Nuclear Support Senn6es Attachment Sketches and Photo of WOL Dimensions and Obstructions Commitments made in this letter: None
Serial No.12-093 Docket No. 50-338 Justification for Length of WOL Weld Overlay Page 3 of 3 cc: U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave" NE Suite 1200 Atlanta, Georgia 30303-1257 Mr. J. E. Reasor, Jr.
Old Dominion Electric Cooperative Innsbrook Corporate Center 4201 Dominion Blvd.
Suite 300 Glen Allen, Virginia 23060 NRC Senior Resident Inspector North Anna Power Station Dr. V. Sreenivas NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 08 G-9A Rockville, Maryland 20852 Ms. K. R. Cotton NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 08 G-9A Rockville, Maryland 20852 Mr. M. M. Grace Authorized Nuclear Insurance Inspector North Anna Power Station
Serial No.12-093 Docket No. 50-338 Attachment Sketches and Photo of WOL Dimensions and Obstructions Virginia Electric and Power Company (Dominion)
North Anna Power Station Unit 1
Serial No.12-093 Docket No. 50-338 Justification for Length of WOL Attachment Page 1 of 2 Estimate of O.7S"RT weld length location on SG Nozzle Minimum and Maximum Weld Dimensions
Serial No.12-093 Docket No. 50-338 Justification for Length of WOL Attachment Page 2 of 2 These structural members would interfere with tooling for machining, welding, & sanding operations if overlay was extended past the safe end for the - 8" axial length for O.75\/Rt.