MONTHYEARML23320A1122024-01-18018 January 2024 NRC to Fws, Concurrence with Endangered Species Act Determinations for North Anna Power Station, Units 1 and 2, Subsequent License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment ML23355A2722023-12-21021 December 2023 NRR E-mail Capture - Schedule Revision for Emergency Preparedness Staff Augmentation Times License Amendment Request ML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23067A2162023-03-0707 March 2023 NRR E-mail Capture - RAI for North Anna, 1 & 2, Surry 1 & 2, Millstone, 2 & 3, Request for Approval of App. F Fleet Report DOM-NAF-2-P, Qual of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion VIPRE-D Computer Code ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML23039A1712023-02-0808 February 2023 NRR E-mail Capture - Acceptance Review for Technical Support Center (TSC) Relocation (L-2023-LLA-0006) ML23018A0352023-01-17017 January 2023 NRR E-mail Capture - Acceptance Review for Fleet Report Re Appendix F of DOM-NAF-2-P (L-2022-LLT-0003) ML22342B1472022-12-0808 December 2022 NRR E-mail Capture - Acceptance Review for LAR Re NAPS Post LOCA Buffer Change (L-2022-LLA-0162) ML22335A4842022-12-0101 December 2022 NRR E-mail Capture - Acceptance Review for LAR North Anna Power Station - Units 1 and 2 and Surry Power Station - Units 1 and 2 Emergency Plan Staff Augmentation Times (L-2022-LLA-0166) ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22104A0252022-04-14014 April 2022 NRR E-mail Capture - Dominion Presentation Slides for April 21, 2022 Public Meeting on Emergency Preparedness Submittal for the North Anna Power Station and the Surry Power Station ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML22032A0962022-02-0101 February 2022 002 Radiation Safety Baseline Inspection Information Request ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22007A2672022-01-0707 January 2022 NRR E-mail Capture - North Anna, Unit 2, ASME Section XI Inservice Inspection Program Relief Request N2-14-LMT-003 Fourth Interval Third Period Limited Examinations (L-2021-LLR-0088) ML21335A0812021-12-0101 December 2021 NRR E-mail Capture - Acceptance Review for OMN-28 Request Alternative to ISTC-3700, Position Verification Testing (L-2021-LLR-0086) ML21334A1922021-11-30030 November 2021 NRR E-mail Capture - Audit Plan for Reactor Core Thermal-Hydraulics Using the VIPRE-D Appendix E Review ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21326A1502021-11-22022 November 2021 NRR E-mail Capture - Acceptance Review for Relocation of Unit Staff Requirements to the QAPD LAR (L-2021-LLA-0195) ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21312A0082021-11-0404 November 2021 Enclosure 2 - NAPS Draft SER Table A.1-1 Markup ML21312A0112021-11-0404 November 2021 Enclosure 3 - NAPS Draft SER Section 3 Comments ML21312A0012021-11-0404 November 2021 Comments on North Anna Draft SER ML21306A3302021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review for TSTF-569 LAR ML21286A7372021-10-13013 October 2021 Additional Element Included in the Implementation Plan for the Surry Fuel Melt Safety Limit (SL) LAR ML21274A0022021-09-30030 September 2021 NRR E-mail Capture - Acceptance Review for TSTF-577 LAR (L-2021-LLA-0158) ML21312A0022021-09-21021 September 2021 Enclosure 1 - E-mail - NAPS SLR SER Appendix a for Dominion Review ML21312A0072021-09-21021 September 2021 Enclosure 1 - E-mail - Enclosure B - NAPS SER App a - Dominion Comments 9-21-2021 ML21312A0032021-09-21021 September 2021 Enclosure 1 - E-mail - Enclosure a - Dominion Table A4.4-1 Clean Version ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21152A1722021-09-0707 September 2021 NRC to Fws, NRC Issuance of Draft Environmental Impact Statement for North Anna Subsequent License Renewal, Opportunity for Public Comment, and Endangered Species Act Determinations ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21225A5512021-08-13013 August 2021 Discussion Point for Public Meeting Regarding Fire Protection Piping Cyclic Loading - Transmittal E-mail ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21154A0152021-06-0101 June 2021 NRR E-mail Capture - Acceptance Review for Primary Grade Water LAR (L-2021-LLA-0082) ML21140A3682021-05-20020 May 2021 Response to North Anna Hardship (Temporary Staff Guidance Additional Guidance for FOF Inspections During the PHE) ML21140A3712021-05-19019 May 2021 FOF Discussion ML21123A2972021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail ML21091A0022021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21076A4622021-03-17017 March 2021 NRR E-mail Capture - Draft RAI for Versatile Internals and Component Program for Reactors Vipre Code Review (L-2021-LLT-0000) ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 ML21069A3522021-03-10010 March 2021 NRR E-mail Capture - Acceptance Review for Topical Report DOM-NAF-2 VIPRE-D 2024-01-18
[Table view] |
Text
Boyle, Patrick
/qcy I From: Stuchell, Sheldon Sent: Monday, September 19, 2011 5:15 PM To: Khanna, Meena; Karwoski, Kenneth Cc: Manoly, Kamal; Wilson, George; Boyle, Patrick; Martin, Robert; Jolicoeur, John
Subject:
RE: North Anna Acceptance Criteria R2 Comments.docx Attachments: North Anna Acceptance Criteria Consolidated Comments.docx
- Meena, I took a quick swag at the acceptance criteria, and have attached with the new paragraph.
Sheldon From: Khanna, Meena Sent: Friday, September 16, 2011 5:38 PM To: Karwoski, Kenneth; Stuchell, Sheldon Cc: Manoly, Kamal; Wilson, George; Boyle, Patrick; Martin, Robert
Subject:
North Anna Acceptance Criteria R2 Comments.docx Ken and Sheldon, Attached are some comments that we received regarding the proposed acceptance criteria from Gerry McCoy in Region II. Could we pls meet on Monday to discuss and then conduct a call with him? I plan to go ahead and send the proposed acceptance criteria to OGC so that we can obtain input from them in parallel.
Thanks!
Meena
Short-Term Technical Acceptance Criteria For Demonstrating The Acceptability For North Anna Plant Restart Confirm the adequacy of the scope of the licensee's inspections, tests and analyses which demonstrate that no functional damage resulted from the earthquake to systems, subsystems, trains, components and devices (systems, structures, or components [SSCs]) for the current licensing basis (1) that are required to be operable by TSs, (2) SSCs not explicitly required to be operable by TSs, but that perform required support functions to maintain a TS required system operable; and (3) ISSbs that are nrot described in TSs but which warran-t prograrmmatic controls to ensure that sS-C- a-,vailab-iity and reliability are rnaintaine-i. Refer to NRC Inspection Manual - - Comment [G.M1]: This is so general, I have trouble understanding what it means. It seems Part 9900, "Operability Determinations and Functionality Assessments for Resolution of to catch anything which anyone feels is Degraded or NonConforming Conditions Adverse to Quality or Safety" for more detailed important. That doesn't rule much out! Maybe this is where we talk about risk significant, or guidance for determinations of operability and resolution of degraded or nonconforming safety related components (see the next
ý o nd ition rsl,. . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . -----
. ..-- comment)
Comment [GJM2]:
(1) Should we also include SSCs which are not safety related, but are risk significant?
(2) Is there apossible to have SSCs which are safety related but not covered by TSs? If so, Confirm the adequacy of the scope of the licensee's inspections, tests and analyses which are they captured? Without finding a copy of demonstrate that no functional damage resulted from the earthquake to systems, subsystems, the TS, I know there are no LCO's for the RCS piping if it is inoperable, yet it should be covered trains, components and devices (systems, structures, or components [SSCs]) for the current by this review.
licensing basis (1) that are required to be operable by TSs, (2) that perform required support (3) Part 9900 provides guidance on what to do if functions to maintain a TS required system operable; and (3) that are risk significant or safety a non-conforming condition is identified. The licensee's effort is first a search for non-related. Refer to NRC Inspection Manual Part 9900, "Operability Determinations and confomring conditions, and after that, an Functionality Assessments for Resolution of Degraded or NonConforming Conditions Adverse evaluation of what was found. What guidance do we have available, or what guidance can we to Quality or Safety" for more detailed guidance for determinations of operability and resolution use to determine whether the search was of degraded or nonconforming conditions. The licensee must provide a plan for NRC approval, adequate?
detailing the methods used to search for non-conforming conditions, and the resulting evaluation method if non-conforming conditions are found. The plan must include a determination of an adequate search.
Contact:
Carl Schulten, NRR/ITSB