MONTHYEARML24107A9112024-04-15015 April 2024 NRC to Fws, Follow-up on Request for Concurrence for North Anna SLR ML24107A9122024-04-11011 April 2024 Fws to NRC, Follow-up on Request for Concurrence for North Anna SLR ML24087A0102024-03-26026 March 2024 NRR E-mail Capture - Verbal Relief for North Anna Unit 1 - (ASME Code), Section XI, Subsection IWB-2430 ML24087A0112024-03-23023 March 2024 NRR E-mail Capture - Draft RAIs for Reactor Coolant Pump (RCP) Relief Request (L-2024-LLR-0022) ML24107B1562024-02-20020 February 2024 Cherokee Nation E.Toombs Na Removal Request ML24044A2462024-02-0606 February 2024 001 Radiation Safety Baseline Inspection Information Request ML23320A1122024-01-18018 January 2024 NRC to Fws, Concurrence with Endangered Species Act Determinations for North Anna Power Station, Units 1 and 2, Subsequent License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment ML23355A2722023-12-21021 December 2023 NRR E-mail Capture - Schedule Revision for Emergency Preparedness Staff Augmentation Times License Amendment Request ML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23067A2162023-03-0707 March 2023 NRR E-mail Capture - RAI for North Anna, 1 & 2, Surry 1 & 2, Millstone, 2 & 3, Request for Approval of App. F Fleet Report DOM-NAF-2-P, Qual of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion VIPRE-D Computer Code ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML23039A1712023-02-0808 February 2023 NRR E-mail Capture - Acceptance Review for Technical Support Center (TSC) Relocation (L-2023-LLA-0006) ML23018A0352023-01-17017 January 2023 NRR E-mail Capture - Acceptance Review for Fleet Report Re Appendix F of DOM-NAF-2-P (L-2022-LLT-0003) ML22342B1472022-12-0808 December 2022 NRR E-mail Capture - Acceptance Review for LAR Re NAPS Post LOCA Buffer Change (L-2022-LLA-0162) ML22335A4842022-12-0101 December 2022 NRR E-mail Capture - Acceptance Review for LAR North Anna Power Station - Units 1 and 2 and Surry Power Station - Units 1 and 2 Emergency Plan Staff Augmentation Times (L-2022-LLA-0166) ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22104A0252022-04-14014 April 2022 NRR E-mail Capture - Dominion Presentation Slides for April 21, 2022 Public Meeting on Emergency Preparedness Submittal for the North Anna Power Station and the Surry Power Station ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML22032A0962022-02-0101 February 2022 002 Radiation Safety Baseline Inspection Information Request ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22007A2672022-01-0707 January 2022 NRR E-mail Capture - North Anna, Unit 2, ASME Section XI Inservice Inspection Program Relief Request N2-14-LMT-003 Fourth Interval Third Period Limited Examinations (L-2021-LLR-0088) ML21335A0812021-12-0101 December 2021 NRR E-mail Capture - Acceptance Review for OMN-28 Request Alternative to ISTC-3700, Position Verification Testing (L-2021-LLR-0086) ML21334A1922021-11-30030 November 2021 NRR E-mail Capture - Audit Plan for Reactor Core Thermal-Hydraulics Using the VIPRE-D Appendix E Review ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21326A1502021-11-22022 November 2021 NRR E-mail Capture - Acceptance Review for Relocation of Unit Staff Requirements to the QAPD LAR (L-2021-LLA-0195) ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21312A0082021-11-0404 November 2021 Enclosure 2 - NAPS Draft SER Table A.1-1 Markup ML21312A0012021-11-0404 November 2021 Comments on North Anna Draft SER ML21312A0112021-11-0404 November 2021 Enclosure 3 - NAPS Draft SER Section 3 Comments ML21306A3302021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review for TSTF-569 LAR ML21286A7372021-10-13013 October 2021 Additional Element Included in the Implementation Plan for the Surry Fuel Melt Safety Limit (SL) LAR ML21274A0022021-09-30030 September 2021 NRR E-mail Capture - Acceptance Review for TSTF-577 LAR (L-2021-LLA-0158) ML21312A0072021-09-21021 September 2021 Enclosure 1 - E-mail - Enclosure B - NAPS SER App a - Dominion Comments 9-21-2021 ML21312A0032021-09-21021 September 2021 Enclosure 1 - E-mail - Enclosure a - Dominion Table A4.4-1 Clean Version ML21312A0022021-09-21021 September 2021 Enclosure 1 - E-mail - NAPS SLR SER Appendix a for Dominion Review ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21152A1722021-09-0707 September 2021 NRC to Fws, NRC Issuance of Draft Environmental Impact Statement for North Anna Subsequent License Renewal, Opportunity for Public Comment, and Endangered Species Act Determinations ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21225A5512021-08-13013 August 2021 Discussion Point for Public Meeting Regarding Fire Protection Piping Cyclic Loading - Transmittal E-mail ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21154A0152021-06-0101 June 2021 NRR E-mail Capture - Acceptance Review for Primary Grade Water LAR (L-2021-LLA-0082) ML21140A3682021-05-20020 May 2021 Response to North Anna Hardship (Temporary Staff Guidance Additional Guidance for FOF Inspections During the PHE) 2024-04-15
[Table view] |
Text
Craver, Patti From: Medoff, James A y--
Sent: Wednesday, September 14, 2011 10:38 AM To: Istar, Ata Cc: Cheruvenki, Ganesh; Ng, Ching; Prinaris, Andrew
Subject:
RE: North Anna Question?
Ata:
Ifyou have time, can you up and see me please regarding your email - I am in OWFN 11 H3? I have not read what is assumed for the North Anna seismic basis in their UFSAR. That is how many OBE occurrences and SSE occurrences and loadings are assumed for in their UFSAR design basis and whether the recent seismic event only exceeded their OBE basis or exceeded their SSE basis. Maybe you can explain what our position in RG 1.57 is for seismic evaluations.
- Thanks, Jim ( I am acting BC for DLR's license renewal reactor systems review branch today and tomorrow)
From: Istar, Ata Sent: Wednesday, eptember 14, 2011 10:24 AM To: Sheikh, Abdul; Auluck, Rajender Cc: Medoff, James; Holston, William
Subject:
RE: North Anna Question?
Referring to RG 1.57 "Design Limits and Loading Combinations...."
(1) Under Level B Service Limits: cyclic loadings are to be included to OBE, if OBE <= one-third of SSE.
I believe North Anna's OBE is one-half of SSE!
(2) Under Level C Service Limits: no cyclic loading added to SSE condition!
(3) Under Level D Service Limits: local dynamic loadings are to be added to SSE.
Should we consider "local dynamic loadings" as cyclic (fatigue) loading?
As well as referring to the Miner's Law, which stated that "in some circumstances, cycles of low stress followed by high stress cause more damage than would be predicted." But, I cannot find any regulatory position on this issue.
Ata Istar From: Sheikh, Abdul Sent: Tuesday, September 13, 2011 10:09 AM To: Auluck, Rajender Cc: Istar, Ata; Medoff, James; Holston, William
Subject:
RE: North Anna Question?
I came up with the following issues:
Impact of August 2011 earthquake at North Anna on long term operations:
- 1. According to the North Anna UFSAR Table 5.2-4, faulted conditions (Design Basis Earthquake) are not included in the fatigue analysis of the plant components and structures. In addition, OBE earthquakes 1 ~ (-
0 .
are also not included in the fatigue analysis. Therefore, fatigue analysis of the structures and components has to be revised to include the impact of the earthquake in August 2011 for the long term operation of the plant (40-60 years)
- 2. Fatigue analysis of the containment penetrations has not been performed previously. Therefore, according to the GALL Report, Rev. 2, a new fatigue analysis is required to be performed or the penetrations inspected for degradations during the long term operations (40-60 years)
- 3. Aging management programs for containment inservice examination (ASME Section Xl, Subsection IWE, Subsection IWL, Subsection IWF, and Appendix J tests) may have to be revised based on the post earthquake assessments. This may include more frequent inspections (augmented) and testing, especially if cracking or degradations is observed during the post earthquake walkdowns.
- 4. Aging management programs for structures, water controlled structures, and masonry walls may also have to be revised based on the post earthquake inspections. This may include more frequent inspections and testing, especially if cracking or degradations is observed during the post earthquake walkdowns.
From: Auluck, Rajender Sent: Tuesday, September 13, 2011 7:18 AM To: Sheikh, Abdul
Subject:
FW: North Anna Question?
FYI. We need to send our questions to DORL today.
raj From: Istar, Ata Sent: Monday, September 12, 2011 12:55 PM To: Auluck, Rajender
Subject:
North Anna Question?
Will the predicted cross-sectional properties at the end of the licensing period of SSCs be considered during their analytical evaluations/analyses for the justification for continued operation?
"the predicted cross-sectional properties at the end of the licensing period" means: the cross-sectional properties of SSCs carried forward to the end of the period of extended operation by considering applicable wear-rate levels under normal operating conditions.
Ata ISTAR (301) 415-4049 ata.istarcnrc..ov
<< OLE Object: Picture (Device Independent Bitmap) >> Reduce waste - print when necessaryl 2