MONTHYEARIR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) ML23248A2242023-09-0707 September 2023 Regulatory Audit in Support of Review of License Amendment Request for a Risk-Informed Approach for Addressing the Effects of Debris on ECCS Strainer Performance ML23223A2242023-08-29029 August 2023 Individual Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Exigent Circumstances) ML23237B4332023-08-25025 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) ML23229A0122023-08-17017 August 2023 Issuance of Amendment No. 224 to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 (Emergency Circumstances) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23227A2212023-08-15015 August 2023 Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23219A1792023-08-0707 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant, Unit 2 IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 ML23216A1872023-08-0404 August 2023 Submittal of Relief Request RR-A25 for Extended License Period ML23206A1272023-07-26026 July 2023 NOED for Fermi Power Plant, Unit Two Technical Specification 3.7.2, Emergency Equipment Cooling Water Emergency Equipment Service Water System and Ultimate Heat Sink ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23122A2332023-06-26026 June 2023 Issuance of Amendment No. 223 Regarding Revision of Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements IR 05000341/20220102023-06-21021 June 2023 Reissue Fermi Power Plant, Unit 2, Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23158A1332023-06-0808 June 2023 Notice of Enforcement Discretion (NOED) for Fermi Power Plant, Unit Two (EPID L-2023-LLD-0000) Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/ Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink ML23130A1032023-05-17017 May 2023 Regulatory Audit Summary Regarding License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency IR 05000341/20234022023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23118A3612023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23114A1172023-05-0101 May 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23115A4152023-04-25025 April 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Fermi Power Plant, Unit 2 ML23124A2032023-04-10010 April 2023 DTE Electric Company Submittal of Fermi 3 Periodic Reports ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter IR 05000341/20230112023-04-0606 April 2023 Triennial Fire Protection Inspection Report 05000341/2023011 IR 05000341/20234012023-03-17017 March 2023 Security Baseline Inspection Report 05000341/2023401 ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22325A2992023-02-24024 February 2023 Audit Plan in Support of Review of License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency ML23039A1552023-02-14014 February 2023 Integrated Inspection Report 05000341/2022004 IR 05000341/20224032023-02-13013 February 2023 Security Baseline Inspection Report 05000341/2022403 ML23200A2162023-01-20020 January 2023 Outline Submittal Letter 2024-02-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 ML23276A0052023-10-0202 October 2023 NRR E-mail Capture - (External_Sender) Fermi EDG Crankcase Trip LAR RAI Response ML23250A2732023-09-0707 September 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request to Revise TS 3.8.1, AC Sources - Operating, Surveillance Requirement 3.8.1.12 ML23241B0162023-08-24024 August 2023 Exigent License Amendment Request for Additional Information RAI-12 (EPID L-2023-LLA-0112) (Email) ML23235A1822023-08-23023 August 2023 Exigent LAR Request for Additional Information ML23115A1452023-04-25025 April 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Changes to TS 3.8.1, AC Sources - Operating ML22362A0712022-12-28028 December 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report Numbers 05000341/2023010 ML22130A5162022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21214A1492021-08-0202 August 2021 License Amendment Request: Request for Additional Information ML21126A0532021-05-0404 May 2021 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Revised Relief Request RR A-39 ML21099A1012021-04-0909 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000341/2021013 ML21078A4832021-03-19019 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000341/2021011 ML20303A2872020-10-29029 October 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000341/2021012 ML20239A9682020-08-12012 August 2020 NRR E-mail Capture - Fermi 2 LAR: RAI for Revision to Technical Specifications to Change the Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML20133K0502020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20079J0972020-03-19019 March 2020 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report Number 05000341/2020011 ML18206B0632018-07-25025 July 2018 NRR E-mail Capture - Draft Request for Additional Information Regarding Fermi LAR to Adopt TSTF -542 ML18129A3992018-05-0909 May 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi LAR to Adopt TSTF - 542 ML18065A3962018-03-0606 March 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi LAR to Adopt TSTF-542 ML18029A1262018-01-29029 January 2018 NRR E-mail Capture - Fermi 2 LAR to Revise TS to Eliminate MSLRM Reactor Trip and PCIS Group 1 Isolation Functions ML18022A9452018-01-22022 January 2018 NRR E-mail Capture - Fermi RAI for LAR Regarding TS to Eliminate Steam Line Radiation ML18022A1092018-01-19019 January 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi RR-A37 ML17346A8012017-12-12012 December 2017 NRR E-mail Capture - Final Fermi RAI for LAR Regarding Uhc (TS 3.7.2) ML17157B6702017-06-0505 June 2017 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000341/2017012 ML17087A4572017-03-28028 March 2017 NRR E-mail Capture - RAI for Fermi 2 - LAR Regarding the Availability of HPCI and Rici at Low Pressure Conditions ML16357A1152016-12-22022 December 2016 Notification of NRC Baseline Inspection and Request for Information (Jvb) ML16188A1922016-07-0707 July 2016 Request for Additional Information on Severe Accident Mitigation Alternatives for Review of License Renewal Application Environmental Review ML16125A1742016-05-0303 May 2016 Request for Additional Information - Alternative Request PRR-007, Revision 1 ML16090A1032016-03-29029 March 2016 Ltr. 03/29/16 Fermi Power Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000341/2016002 (Maj) ML16011A0442016-01-14014 January 2016 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 38 ML15237A0442015-09-0101 September 2015 Request for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application-Set 37 ML15231A1612015-08-17017 August 2015 Ltr. 08/17/15 Fermi Power Plant - Notification of NRC Inspection and Request for Information (Txb) ML15149A3642015-05-28028 May 2015 Information Request to Support NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15134A0722015-05-21021 May 2015 Request for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application-Set 35 ML15139A4612015-05-20020 May 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application-Set 33 ML15132A4272015-05-18018 May 2015 March 27, 2015 Summary of Telephone Conference Call Held Between the U.S. NRC and DTE Electric Company Concerning Requests for Additional Information Pertaining to the Severe Accident Mitigation Alternatives Review of the Fermi, Unit 2 ML15126A0042015-05-15015 May 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application-Set 34 ML15114A3692015-05-0606 May 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report ML15099A0162015-04-22022 April 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application Set 32 ML15092A9452015-04-0909 April 2015 Request for Additional Information for the Environmental Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives ML15085A5132015-04-0202 April 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 31 ML15077A1082015-03-26026 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 27 ML15082A0462015-03-26026 March 2015 Requests for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 29, ML15078A3372015-03-26026 March 2015 Request for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 28 ML15072A0812015-03-19019 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 25 ML15051A4202015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 23 ML15062A3362015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 26 ML15051A3172015-03-11011 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 24 ML15027A3552015-02-11011 February 2015 Summary of Telephone Conference Call Between NRC and DTE Electric Company Concerning RAIs Pertaining to the Fermi, Unit 2 LRA SAMA Review ML15026A3072015-02-0303 February 2015 Requests for Additional Information for the Environmental Review of the Fermi 2 License Renewal Application-Severe Accident Mitigation Alternatives 2023-09-07
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 February 13, 2012 Mr. Jack M. Davis Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
FERMI POWER PLANT, UNIT 2, NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Davis:
On May 7, 2012, the U. S. Nuclear Regulatory Commission (NRC) will begin inspection of refueling and other outage activities (NRC Inspection Procedure 71111.20) prior to the next refueling outage scheduled for the Fermi Power Plant. This inspection will utilize NRC Operating Experience Smart Sample: (OpESS) FY 2007-03, Revision 2, Crane and Heavy Lift Inspection, Supplemental Guidance for IP-71111.20, issued September 12, 2008. This inspection will focus on the impact of load handling activities on the reactor core and its cooling and plant support systems. Specifically, this inspection will review applicable design and licensing bases, engineering design and analysis, procedures, and surveillances associated with the reactor vessel head removal and installation during refueling outages including: (1) reactor shield plugs, drywell head, reactor pressure vessel head, steam separator, steam dryer lifting devices; (2) reactor vessel head safe load paths; and (3) reactor building crane preventative maintenance, inspections and testing. The on-site portion of the inspection will take place on May 7 - 11, 2012 and May 21 - 25, 2012.
Experience has shown that inspection of these activities is resource intensive both for the NRC inspector and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for documents needed for the inspection. This information should be available in Region III by April 30, 2012, (preparatory week). It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Mr. J. Pendergast, of your organization. If there are any questions about this inspection or the material requested, please contact the inspector, Mr. J. Bozga, at (630) 829-9613.
J. Davis This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
David E. Hills, Chief Engineering Branch 1 Division of Reactor Safety Docket No. 50-341 License No. NPF-43
Enclosure:
Crane and Heavy Lift Inspection Document Request (Information for Preparation Week and Information Available On-site During Inspection) cc w/encl: Distribution via ListServ'
CRANE AND HEAVY LIFT INSPECTION DOCUMENT REQUEST Inspection Dates: May 7 - 11 and May 21 - 25, 2012 Inspection Procedures: Inspection Procedure (IP) 71111.20, Refueling and Other Outage Activities Lead Inspector: John V. Bozga (630) 829-9613 John.bozga@nrc.gov I. Information Requested for In-Office Preparation Week The following information (paper copy if practicable, unless otherwise indicated) is requested to be available in Region III on April 30, 2012. If you have any questions regarding this information, please call the lead inspector as soon as possible.
A copy of the following documents related to heavy load control during removal or installation of the reactor vessel head:
(1) Fermi submittals as a result of NRC December 22, 1980, unnumbered Generic Letter (GL) (now NRC numbered as GL 80-113) and GL 81-07, Control of Heavy Loads regarding NUREG 0612, Control of Heavy Loads at Nuclear Power Plants, six-month response (Phase I) and nine-month response (Phase II). Final Supplement to Safety Evaluation Report related to NUREG 0612, Phase I and Phase II, if applicable.
(2) Fermi Corrective Action Program Reports related to NRC Regulatory Issue Summary 2005-25, Clarification of NRC Guidelines for Control of Heavy Loads, NRC Regulatory Issue Summary 2005-25, Supplement 1 Clarification of NRC Guidelines for Control of Heavy Loads, Enforcement Guidance Memorandum 2007-006, Enforcement Discretion for Heavy Load Handling Activities, and Nuclear Energy Institute 08-05, Industry Initiative on Control of Heavy Loads.
(3) Design calculations for lifting lugs on reactor pressure vessel head, drywell head, steam dryer, and steam separator and design calculations for lifting devices associated with lifting the reactor shield plugs, drywell head, reactor pressure vessel head, steam dryer and steam separator.
(4) Documents that establish the total lift weight for the existing reactor pressure vessel head, reactor shield plugs, drywell head, steam dryer and steam separator.
(5) Site procedures associated with control of heavy loads-safe load paths, which includes removal of the reactor vessel head during refueling operations, installation of the reactor vessel head during refueling operations, and any contingency actions taken to mitigate the consequences of a postulated reactor pressure vessel head drop.
1 Enclosure
CRANE AND HEAVY LIFT INSPECTION DOCUMENT REQUEST (6) Reactor building crane vendor recommendations regarding preventative maintenance, and inspection, and testing prior to use.
(7) Site procedures associated with reactor building crane preventative maintenance, inspection, and testing prior to lifting the reactor vessel head.
(8) Documentation for reactor building crane preventative maintenance, inspection, and testing performed during last refueling outage prior to lifting the reactor vessel head.
(9) Site procedures used for implementation of industry standards related to training and qualification of reactor building crane operators (10) The most recent site control of heavy loads program audit and/or self-assessment.
(11) Corrective action documents generated as a result of most recent site control of heavy loads program audit and/or self-assessment.
(12) A copy of the Fermi Updated Final Safety Analysis Report.
II. Information Requested to be provided throughout the inspection (1) Copies of any corrective action documents generated as a result of the inspectors questions or queries during this inspection.
(2) Copies of the list of questions submitted by the lead inspector and the status/resolution of the information requested (provide daily during the inspection to lead inspector).
If you have questions regarding the information requested, please contact the lead inspector.
2 Enclosure
J. Davis This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
David E. Hills, Chief Engineering Branch 1 Division of Reactor Safety Docket No. 50-341 License No. NPF-43
Enclosure:
Crane and Heavy Lift Inspection Document Request (Information for Preparation Week and Information Available On-Site During Inspection) cc w/encl: Distribution via ListServ' DISTRIBUTION:
Breeda Reilly RidsNrrDorlLpl3-1 Resource RidsNrrPMFermi2 Resource RidsNrrDirsIrib Resource Cynthia Pederson Jennifer Uhle Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak DOCUMENT NAME: Ltr 021312 FERMI Request for Information JVB.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME JBozga:ls DHills DATE 02/09/12 02/13/12 OFFICIAL RECORD COPY