on Dennig, Robert From:
Dennig, Robert
[ \\f VA Sent:
Tuesday, September 06, 2011 1:38 PM To:
Wilson, George; Clifford, Paul; Wood, Kent; Ulses, Anthony; Mendiola, Anthony Cc:
Bettle, Jerome; Karipineni, Nageswara
Subject:
RE: North Anna We believe that the licensee likely has a list of IST tests scheduled to be performed if a shutdown will exceed 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. These tests would provide an adequate sample of valve functionality, absent any visible-evidence of damage.
We recommend a general visual inspection of the containment consistent with Appendix J and industry guidance, NEI 94-01 and ANSI/ANS 56.8.
From: Wilson, George Sent: Tuesday, September 06, 2011 10:15 AM To: Clifford, Paul; Wood, Kent; Ulses, Anthony; Mendiola, Anthony; Dennig, Robert
Subject:
North Anna Bob please send me something on cnmt, and paul and Kent something on the feul and spent fuel George Wilson USNRC EICB Branch Chief, Division of Engineering Mail Stop 012H2 301-415-1711 38
/