March 9, 2012 Ms. Julie Y. Keys Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708
SUBJECT:
FINAL LICENSE RENEWAL INTERIM STAFF GUIDANCE, LR-ISG-2011-05, ONGOING REVIEW OF OPERATING EXPERIENCE
Dear Ms. Keys:
The purpose of this letter is to inform you of the U.S. Nuclear Regulatory Commissions (NRC or the staff) issuance of the final license renewal interim staff guidance (LR-ISG), LR-ISG-2011-05, Ongoing Review of Operating Experience. This final LR-ISG clarifies the staffs existing position in NUREG-1800, Revision 2, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants, that acceptable license renewal aging management programs should be informed, and enhanced when necessary, based on the ongoing review of both plant-specific and industry operating experience. The final LR-ISG is approved for staff and stakeholder use and will be incorporated into the next license renewal guidance document revisions.
On August 24, 2011, the NRC issued draft LR-ISG-2011-05 for public comment and on November 25, 2011, a revised draft was issued for public comment. The Nuclear Energy Institute provided comments by letters dated October 18, 2011, and December 15, 2011. All comments have been considered and, where appropriate, changes have been made to the LR-ISG. Appendix C to the final LR-ISG contains the staffs responses to the comments.
Enclosed is a copy of the final LR-ISG-2011-05 and the Federal Register notice announcing its issuance. If you have any questions, please contact Mr. Matthew Homiack of my staff by telephone at 301-415-1683 or by e-mail at Matthew.Homiack@nrc.gov.
To inform other stakeholders of the issuance of final LR-ISG-2011-05, courtesy copies of this letter are being sent to subscribers of an NRC electronic mailing list on general license renewal topics.
Sincerely,
/RA/
Melanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation
Enclosures:
As stated cc w/encls: Reactor License Renewal Stakeholder Group Listserv
March 9, 2012 Mr. Michael Gallagher Exelon Nuclear 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
FINAL LICENSE RENEWAL INTERIM STAFF GUIDANCE, LR-ISG-2011-05, ONGOING REVIEW OF OPERATING EXPERIENCE
Dear Mr. Gallagher:
The purpose of this letter is to inform you of the U.S. Nuclear Regulatory Commissions (NRC or the staff) issuance of the final license renewal interim staff guidance (LR-ISG), LR-ISG-2011-05, Ongoing Review of Operating Experience. This final LR-ISG clarifies the staffs existing position in NUREG-1800, Revision 2, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants, that acceptable license renewal aging management programs should be informed, and enhanced when necessary, based on the ongoing review of both plant-specific and industry operating experience. The final LR-ISG is approved for staff and stakeholder use and will be incorporated into the next license renewal guidance document revisions.
On August 24, 2011, the NRC issued draft LR-ISG-2011-05 for public comment and on November 25, 2011, a revised draft was issued for public comment. Exelon Generation Company, LLC, provided comments by letter dated October 18, 2011. All comments have been considered and, where appropriate, changes have been made to the LR-ISG. Appendix C to the final LR-ISG contains the staffs responses to the comments.
Enclosed is a copy of the final LR-ISG-2011-05 and the Federal Register notice announcing its issuance. If you have any questions, please contact Mr. Matthew Homiack of my staff by telephone at 301-415-1683 or by e-mail at Matthew.Homiack@nrc.gov.
To inform other stakeholders of the issuance of final LR-ISG-2011-05, courtesy copies of this letter are being sent to subscribers of an NRC electronic mailing list on general license renewal topics.
Sincerely,
/RA/
Melanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation
Enclosures:
As stated cc w/encls: Reactor License Renewal Stakeholder Group Listserv
ML12044A220 (Package)
ML12044A214 (Letter)
ML12044A215 (Interim Staff Guidance Document)
OFFICE LA:DLR/RPB2 PM:DLR/RARB BC:DLR/RPOB BC:DLR/RARB NAME IKing MHomiack YDiaz BPham DATE 02/24/2012 02/22/2012 02/21/2012 02/24/2012 OFFICE OGC (NLO)
PM:DLR/RARB D:DLR NAME JBiggins MHomiack MGalloway DATE 03/07/2012 03/08/2012 03/09/2012
Letter to Julie Y. Keys, et al. from Melanie A. Galloway dated March 9, 2012
SUBJECT:
FINAL LICENSE RENEWAL INTERIM STAFF GUIDANCE, LR-ISG-2011-05, ONGOING REVIEW OF OPERATING EXPERIENCE DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDra Resource RidsNrrDe Resource RidsNrrDss Resource RidsOgcMailCenter Resource RidsOpaMail Resource RidsOcaMailCenter Resource MHomiack, NRR EGettys, NRR RConte, RI JRivera, RII AStone, RIII NOKeefe, RIV