MONTHYEARML1128004752011-10-0707 October 2011 Acceptance Review Email, Relief Request RR-ENG-3-06 from ASME Code Requirements for Leak Testing Boundaries of Class 1 Pressure-Retaining Components, Third 10-Year Inservice Inspection Interval (TAC ME7053-ME7054) Project stage: Acceptance Review ML1204402942012-02-13013 February 2012 Email, Request for Additional Information, Relief Request RR-ENG-3-06, Requirements for Leak Testing Boundaries of Class 1 Pressure-Retaining Components, Third 10-Year Inservice Inspection Interval (TAC ME7053-ME7054) Project stage: RAI NOC-AE-12002822, Response to Request for Additional Information for Relief Request RR-ENG-3-06 for Leak Testing of Class 1 Pressure-Retaining Components2012-04-10010 April 2012 Response to Request for Additional Information for Relief Request RR-ENG-3-06 for Leak Testing of Class 1 Pressure-Retaining Components Project stage: Response to RAI NOC-AE-12002828, Response to Request for Additional Information for Relief Request RR-ENG-3-06 for Leak Testing of Class 1 Pressure-Retaining Components2012-04-10010 April 2012 Response to Request for Additional Information for Relief Request RR-ENG-3-06 for Leak Testing of Class 1 Pressure-Retaining Components Project stage: Response to RAI ML12108A0072012-04-10010 April 2012 Response to Request for Additional Information for Relief Request RR-ENG-3-06 for Leak Testing of Class 1 Pressure-Retaining Components Project stage: Response to RAI ML12135A1782012-04-10010 April 2012 Response to Request for Additional Information for Relief Request RR-ENG-3-06 for Leak Testing of Class 1 Pressure-Retaining Components Project stage: Response to RAI NOC-AE-12002842, Errata Sheet with the Corrected Correspondence Serial Number2012-05-0202 May 2012 Errata Sheet with the Corrected Correspondence Serial Number Project stage: Other ML12135A1772012-05-0202 May 2012 Errata Sheet with the Corrected Correspondence Serial Number Project stage: Other ML12235A3472012-08-28028 August 2012 Relief Request RR-ENG-3-06 from ASME Code Requirements for Leak Testing Boundaries of Class 1 Pressure-Retaining Components, Third 10-Year Inservice Inspection Interval (TAC ME7053-ME7054) Project stage: Approval 2012-04-10
[Table View] |
Text
From:
Singal, Balwant Sent:
Monday, February 13, 2012 10:37 AM To:
'Harrison, Albon' Cc:
'Walker, Philip'
Subject:
Request for Additional Information (RAI) - Relief Request RR-EBG-3-06 (TACs ME7053 and ME7054)
By letter dated August 31, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML11250A169), STP Nuclear Operating Company (STPNOC, the licensee) requested relief from American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI Table IWB-2500-1 for leak testing boundaries of Class 1 pressure retaining components. To complete its review, the U.S. Nuclear Regulatory Commission staff needs the following additional information.
- 1. Please provide a more detailed description of the system leakage test that will be performed for each component group (test pressure and temperature, hold time, etc). In particular, for Component Groups 3, 4, and 5, your application states that the examination will be performed at a reduced test pressure. Please provide the pressure(s) that will be used for the test.
- 2. Has there been plant or industry operating experience of degradation of the subject segments by mechanisms such as stress corrosion cracking or fatigue?
Draft RAIs were transmitted on January 31, 2012. Mr. Phil Walker of STPNOC informed on February 13, 2012 that a clarification is not needed. Please treat this e-mail as formal request.
You are requested to provide your response within 30 days from the date of this e-mail.