MONTHYEARLIC-24-0012, Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information2024-10-0707 October 2024 Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information LIC-24-0011, Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-00952024-10-0202 October 2024 Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-0095 LIC-24-0007, License Amendment Request (LAR) to Revise License Termination Plan (LTP)2024-06-18018 June 2024 License Amendment Request (LAR) to Revise License Termination Plan (LTP) LIC-24-0008, Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI2024-05-16016 May 2024 Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI LIC-24-0003, Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report2024-04-25025 April 2024 Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-24-0006, (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan2024-04-17017 April 2024 (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan LIC-24-0005, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2024-03-0101 March 2024 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-24-0002, Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report2024-02-27027 February 2024 Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-18-0031, Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update2018-12-17017 December 2018 Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update 2024-06-18
[Table view] |
Text
Omaha PublicPowerDistrict 444 South 16"' Street Mall Omaha, NE 68102-2247 LIC-12-0005 February 6, 2012 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
References:
- 1. Docket No. 50-285
- 2. Materials Reliability Program: Coordinated PWR Reactor Vessel Surveillance Program (CRVSP) Guidelines (MRP-326). EPRI, Palo Alto, CA: 2011. 1022871.
- 3. NUREG-1782, "Safety Evaluation Report Related to the License Renewal of Fort Calhoun Station, Unit 1", dated October 2003
SUBJECT:
Request for Change in Reactor Vessel Surveillance Capsule Removal Schedule Pursuant to 10 CFR 50, Appendix H, Section ll.B.3, the Omaha Public Power District (OPPD) requests NRC authorization to change the schedule for removal of reactor vessel surveillance capsules associated with the Fort Calhoun Station (FCS) Reactor Vessel Integrity (RVI) Program. This request is consistent with industry initiatives for a coordinated U.S. pressurized water reactor (PWR) reactor vessel surveillance program (RVSP) capsule management plan that will fill the high fluence irradiated Charpy da ta gaps in the PWR RVSP capsule database. This database is currently being used by the NRC in the development of embrittlement correlations.
The current FCS surveillance capsule removal schedule and the proposed schedule modifications are attached. The proposed schedule reflects the planned coordinated U.S. PWR reactor vessel surveillance program. The technical basis for the schedule modifications is described in Reference 2, which is enclosed.
The optimized capsule removal schedule is presented to yield data assuring that the vessel meets the requirements of Regulatory Guide 1.99, "Radiation Embrittlement of Reactor Vessel Materials," Revision 02, Position 2.1 analysis. Consistent with Reference 3, OPPD will continue to evaluate applicable surveillance data from other reactor vessels to ensure that the conclusions of Reference 2 remain valid.
The current schedule is consistent with the Generic Aging Lessons Learned (GALL)
Report and Reference 3. The proposed changes remain consistent with these documents as well.
Employment with Equal Opportunity
U. S. Nuclear Regulatory Commission LIC-12-0005 Page 2 If you should have any questions regarding this submittal, please contact Mr. Bill R.
Hansher at (402) 533-6894.
Sincerely, H ermran iDivision Manager-Nuclear Engineering JBH/MLE/mle
Attachment:
Proposed Changes to the Fort Calhoun Station, 10 CFR 50, Appendix G, Surveillance Program
Enclosure:
Materials Reliability Program:CoordinatedPWR Reactor Vessel Surveillance Program (CRVSP) Guidelines (MRP-326). EPRI, Palo Alto, CA: 2011. 1022871.
E. E. Collins, Jr., NRC Regional Administrator, Region IV (w/o Enclosure)
L. E. Wilkins, NRC Project Manager (w/o Enclosure)
J. C. Kirkland, NRC Senior Resident Inspector (w/o Enclosure)
LIC-12-0005 Attachment Page 1 Proposed Changes to the Fort Calhoun Station, 10 CFR 50, Appendix G, Surveillance Program Material Description Six surveillance capsules containing beltline materials fabricated from American Society of Mechanical Engineers (ASME) SA-533 Grade B Class 1 (low Cu group) were inserted in the reactor prior to initial start-up. The capsules contain specimens made from shell plate D4802-2, heat number Al 768-1, and weld flux Linde 1092 heat 305414, which is representative of the beltline region welds.
Three supplemental capsules (W-225S, W-265S and W-275S) containing materials fabricated from weld flux Linde 1092 were inserted at later dates. Capsules W-225S and W-265S contain Linde 1092 weld heat 305414 while W-275S (installed in 1993) contains weld heats 27204/27204 and 12008/13253. Fort Calhoun Station takes credit for data irradiated in Mihama Unit 1, Diablo Canyon Unit 1, and Palisades for the limiting 3-410 welds.
Each of the original capsules contains the following Charpy V-notch specimens: 24 base (12 longitudinal and 12 transverse), 12 weld metal and 12 HAZ.
Current Program Three of the original six surveillance capsules (W-225, W-265 and W-275) have been removed and tested (Table 1). Capsule W-275S was inserted at the end of Cycle 14.
Fort Calhoun Station received approval for a 60-year (i.e., 48 effective full-power year (EFPY)) license renewal in November 2003. The projected 60-year (48 EFPY) peak reactor pressurve vessel (RPV) fluence is 3.5 x 1019 n/cm 2 .
Capsule W-275S is currently scheduled to be removed and tested after reaching a fluence of at least 1.719 x 10 9 n/cm 2 at 33.6 EFPY.
Capsule W-95 is currently scheduled to be removed and tested after 48 EFPY. Using the capsule lead factor and the linear relationship between the peak RPV fluence and the corresponding EFPY values, the capsule fluence at 48 EFPY was calculated to be 3.92 x 101 9 n/cm2 , which assumes a capacity factor of 0.95 starting in 1993.
LIC-12-0005 Attachment Page 2 Table 1: Fort Calhoun Station Current Withdrawal Schedule Capsule Location Lead Removed Removal Fluence Factor EOC (EFPY) (n/cm 2 )
W-225 2250 1.53 3(1977) 2.5 5.1 x 10"'
W-265 2650 1.07 7(1983) 5.9 9.0 x 10l W-275 2750 1.05 14(1993) 13.6 1.38 x 101 9 W-45 450 1.51 Standby ---....
W-85 850 1.17 Standby ---....
W-95 950 1.17 Planned 48.0 3.92 x 1019(a)
W-225S 2250 1.12 Standby ......
W-265S 2650 0.97 Standby ......
W-275S 2750 --- Planned 33.6 1.719 x 1019 (b)
(a) Greater than projected 60-year (48 EFPY) peak RPV fluence.
(b) Contains corresponding RPV weld material.
Requested Program As shown in Table 2 below, Capsule W-45 should be removed and tested after reaching the projected 80-year (67 EFPY) peak RPV fluence of 4.72 x 1019 n/cm 2 . This fluence was extrapolated from the linear relationship between the peak RPV fluence and the corresponding EFPY values. The 67 EFPY value was determined by assuming a 0.95 capacity factor starting after 60 years of operation. Using the capsule lead factor and the linear relationship between the reported peak RPV fluences and their corresponding EFPY values, capsule W-45 should reach the specified fluence at 42.0 EFPY, which will occur in approximately 2022.
Given the intent to obtain a higher fluence than the current withdrawal schedule for capsule W-275S which was inserted at an EFPY of 13.6, the reactor EFPY of the capsule at the requested time of removal is 47.2. Assuming a capacity factor of 0.95 starting in 1993, capsule W-275S should reach 3.0 x 1019 n/cm 2 in approximately 2028.
This supports the goal of the Electric Power Research Institute (EPRI), Materials Reliability Program (MRP) to coordinate the withdrawal schedules of remaining surveillance capsules so that pressurized water reactor (PWR) high fluence surveillance data (i.e., above 3.0 x 1019 n/cm 2 ) is available to develop future RPV embrittlement trend curves.
Capsule W-95 should remain in the reactor on standby.
LIC-12-0005 Attachment Page 3 Table 2: Fort Calhoun Station Requested Withdrawal Schedule for Remaining Capsules Capsule Location Lead Removal Removal Fluence Factor Year (EFPY) (n/cm 2 W-45 450 1.51 2022 42.0 4.72 x 10 9(a)
W-275S 2750 --- 2028 47.2 3.0 x 10' 9 (b,c)
W-85 850 1.17 Standby ---...
W-95 950 1.17 Standby ---...
W-225S 2250 1.12 Standby ---...
W-265S 2650 0.97 Standby ---...
(a) Projected 80-year (67 EFPY) peak RPV fluence.
(b) Contains corresponding RPV weld material.
(c) Not a change required for the CRVSP but added to list at request of OPPD.