MONTHYEARML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23338A0402023-12-0404 December 2023 NRR E-mail Capture - Ready for Clean TS Pages and Updated Review Hours for Clinton Power Station, Unit 1, Request for License Amendment to Revise Technical Specifications Section 3.8.3 ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23261A0032023-09-15015 September 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Amendment Request to Revise Timing of Reactor Water Cleanup Isolation Valves ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23219A2142023-08-0404 August 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Request for Partial Site Release ML23194A1102023-07-13013 July 2023 NRR E-mail Capture - Non-acceptance of Clinton Request for Partial Site Release ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23087A0122023-03-28028 March 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Technical Specifications 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air (L-2023-LLA-0034) ML23033A0332023-02-0101 February 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Adopt TSTF-332 (L-2023-LLA-0007) ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22165A1902022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-230 (L-2022-LLA-0076) ML22165A1912022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-269 (L-2022-LLA-0077) ML23089A0182022-05-24024 May 2022 NRR E-mail Capture - Clinton Power Station Acceptance Review Results - Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan ML22116A0422022-04-26026 April 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Secondary Containment Design Basis ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21252A0482021-09-0707 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21252A0042021-08-26026 August 2021 NRR E-mail Capture - NRC Acceptance Review - Braidwood/Byron/Clinton - Adoption of TSTF-273, Safety Function Determination Program Clarifications ML21225A0392021-08-13013 August 2021 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Request to Revise Degraded Voltage Instrumentation Setpoints ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21203A3062021-07-21021 July 2021 NRR E-mail Capture - NRC Acceptance Review - Clinton - Third Inservice Inspection Interval Relief Request I3R-18 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21182A0722021-06-29029 June 2021 SUNSI and Proprietary Review Determination Email Regarding: Tn CoC 1042 (Eos) Amendment 3 Rsi Responses ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1012021-02-26026 February 2021 NRR E-mail Capture - Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21057A1002021-02-17017 February 2021 NRR E-mail Capture - Second Round RAI - Clinton TSTF-505 License Amendment Request ML21041A5442021-02-10010 February 2021 NRR E-mail Capture - NRC Acceptance Review for Clinton Request for License Amendment to Revise Degraded Voltage Relay Allowable Values (L-2021-LLA-0005) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML20350B5602020-12-15015 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-582 and TSTF-583-T (EPIDs L-2020-LLA-0253 and L-2020-LLA-0254) ML20350B5582020-12-14014 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC -Alternative Request for Documentation of Replacement of Pressure Retaining Bolting ML20346A1012020-12-11011 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for an Alternative to Use ASME Code Case N-893 (EPIDs L-2020-LLR-0147 and L-2020-LLR-0148) ML20307A6592020-10-27027 October 2020 NRR E-mail Capture - Request for Additional Information Regarding TSTF-505 and 50.69 Applications ML20266G3032020-09-22022 September 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Request to Use Paragraph IWA-5120 of the 2017 Edition of the ASME B&PV Code, Section XI ML20295A4952020-08-27027 August 2020 NRR E-mail Capture - NRC Preliminary Audit Plan for Clinton TSTF-505 and 50.69 Submittals ML20191A0182020-07-0101 July 2020 NRR E-mail Capture - Exelon Fleet RR for SPI for Appendix J Valves 2023-09-22
[Table view] |
Text
NRR-PMDAPEm Resource From: Wiebe, Joel Sent: Monday, January 30, 2012 2:44 PM To: Mitchel Mathews
Subject:
Request for Partial Site Release for Clinton Power Station: Non-acceptance with Opportunity to Supplement Attachments: image001.jpg By letter dated November 18, 2011(Agencywide Documents Access and Management System (ADAMS)
Accession No. ML11340A077), Exelon Generation Company, LLC (Exelon), submitted a request for partial site release for Clinton Power Station, Unit 1 (CPS).
We have determined that additional information is necessary to commence our review. Inform me of your availability to participate in a teleconference within 5 days of this communication.
The purpose of the teleconference is to ensure the scope of the required information is understood and to determine if the information can be submitted within the required supplement schedule (not greater than 13 working days).
Additional information required:
- 1. 10 CFR Part 50.83(c)(2) requires a determination whether the licensees classification of any release areas as non-impacted is adequately justified. The staff determined that the following items are not adequately justified:
- a. Exelons November 18, 2011, submittal states that the shallow groundwater flow is predominately toward the lake. The land to be released is toward the lake (from the perspective of site structures), but is on the opposite side of the lake. The submittal does not address any potential, deeper groundwater aquifers nor whether those aquifers (if they exist) could impact the land to be sold.
Additionally, the submittal states Station release pathways are monitored and summarized as followsSurface water, drinking, and well water samples were analyzed. No tritium activity has been detected. A review of the CPS 2010 Annual Radiological Environmental Operating Report (AREOR) indicates the following:
Background levels of tritium were detected at concentrations greater than the self-imposed LLD of 200 pCi/L in three of 17 groundwater monitoring locations. The tritium concentrations ranged from 184 +104 pCi/L to 744 +/- 130 pCi/L.
The CPS 2010 AREOR indicates tritium is localized around three groundwater wells. The NRC finds the highest levels of tritium limited to one groundwater well, MW-CL-21S, and that the results are consistently and significantly higher than other wells in the area. Two other wells very near MW-CL-21S show lower levels of tritium. All other monitoring wells in the 2010 AREOR indicated tritium was not detected. The licensee characterizes this tritium as background levels.
Provide justification that demonstrates that the areas to be released are not impacted by any potential deep aquifers, including providing information regarding any relationship between shallow and potentially deep aquifers and the background levels of tritium in the vicinity of the areas to be released.
- b. Exelons November 18, 2011, submittal states that Station release pathways are monitored and summarized as follows Grass samples were analyzed for concentrations of gamma emitting 1
nuclides. Concentrations of Cosmogenic Be-7 and naturally occurring K-40 were consistent with those detected in previous years. No fission or activation products were detected.
Provide the approximate percentage of samples that were taken in the areas proposed to be released. Provide justification that this adequately confirms that the areas can be classified as non-impacted.
- 2. 10 CFR Part 50.83(a) states, in part, Section 50.75 specifies recordkeeping requirements associated with partial release. Exelons submittal does not address 10 CFR Part 50.75 recordkeeping requirements.
Discuss how 10 CFR Part 50.75 recordkeeping requirements will be met.
- 3. Exelons November 18, 2011, submittal states that the transfer of this land does not have any effect on the Early Site Permit study conducted in 2002, on an area that is contained entirely within the CPS exclusion area. 10 CFR Part 52.39(e) states, in part, The holder of an early site permit may not make changes to the early site permit, including the site safety analysis report, without prior Commission approval.
Provide a specific reference to the issued Early Site Permit and the docketed site safety analysis report. Provide a reference to sections of the early site permit, including the site safety analysis report, that are potentially impacted by the proposed partial release and demonstrate why this is not considered a change.
2
Hearing Identifier: NRR_PMDA Email Number: 257 Mail Envelope Properties (Joel.Wiebe@nrc.gov20120130144400)
Subject:
Request for Partial Site Release for Clinton Power Station: Non-acceptance with Opportunity to Supplement Sent Date: 1/30/2012 2:44:09 PM Received Date: 1/30/2012 2:44:00 PM From: Wiebe, Joel Created By: Joel.Wiebe@nrc.gov Recipients:
"Mitchel Mathews" <Mitchel.Mathews@exeloncorp.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 4418 1/30/2012 2:44:00 PM image001.jpg 11907 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Page 1 of 1 file://c:\EMailCapture\NRR_PMDA\257\attch1.jpg 2/7/2012