MONTHYEARIR 05000416/20243012024-01-16016 January 2024 NRC Initial Operator Licensing Examination Approval 05000416/2024301 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23102A1482023-04-12012 April 2023 Notification of NRC Initial Operator Licensing Examination 05000416/2024301 ML22342B2592022-10-14014 October 2022 10 Post Examination Analysis ML22342B2602022-10-14014 October 2022 10 Public Forms ML22075A3442022-03-16016 March 2022 Response to Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21342A2702021-12-0808 December 2021 GG-2022-10 Corp Notification Ltr - Cco, Grand Gulf Nuclear Station - Notification of NRC Initial Operator Licensing Examination 05000416/2022301 ML21349A1562021-10-25025 October 2021 GG-2021-10 Public Forms ML21333A2532021-10-25025 October 2021 GG-2021-10 Post Exam Analysis ML21280A0732021-10-0707 October 2021 NRC Initial Operator Licensing Examination Approval 05000416/2021301 ML21106A1512021-04-16016 April 2021 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations ML21106A2842021-04-14014 April 2021 Generic Fundamentals Examination Results March 2021 ML21041A5352021-02-11011 February 2021 Notification of NRC Initial Operator Licensing Examination 05000416/2021301 ML20072L2192020-03-12012 March 2020 Response to Regulatory Issue Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML20069C2262020-03-0909 March 2020 Notification of NRC Initial Operator Licensing Examination 05000416/2020302 ML20058J8102020-02-10010 February 2020 GG-2020-02 Post Examination Analysis ML20058H6182020-02-10010 February 2020 GG-2020-02 Draft Written Examination ML20058H6142020-02-10010 February 2020 GG-2020-02 Draft Operating Test ML20058H6152020-02-10010 February 2020 GG-2020-02 Draft Outlines ML20058H6172020-02-10010 February 2020 GG-2020-02 Draft Written Examination Comments ML20058H6112020-02-10010 February 2020 GG-2020-02 Draft Operating Test Comments ML20058H6242020-02-10010 February 2020 GG-2020-02 Final Written Examination ML20058H6222020-02-10010 February 2020 GG-2020-02 Final Outlines ML20058H6212020-02-10010 February 2020 GG-2020-02 Final Operating Test ML20058H6262020-02-10010 February 2020 GG-2020-02 Draft Outline Comments ML20058J8112020-02-10010 February 2020 GG-2020-02 Public Forms ML19135A6642019-05-15015 May 2019 Units 2 & 3; River Bend, and Waterford 3 - Response to RIS 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19128A1582019-05-0808 May 2019 Notification of NRC Initial Operator Licensing Examination 05000416/2020301 ML19045A3732019-02-12012 February 2019 March 2019 GFE Cover Letter Riv ML19011A3712019-01-10010 January 2019 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2019 ML18116A2382018-04-26026 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations. ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18061A1652017-12-11011 December 2017 2017-12 Final Outlines ML18061A1722017-12-11011 December 2017 2017-12 Public Forms ML18050A0562017-12-11011 December 2017 2017-12 Post-Exam Analysis ML18050A0542017-12-11011 December 2017 2017-12 Final Written Exams ML18061A1702017-12-11011 December 2017 2017-12 Proposed Written Exam Comments ML18061A1672017-12-11011 December 2017 2017-12 Proposed Operating Tests ML18061A1712017-12-11011 December 2017 2017-12 Proposed Written Exams ML18050A0552017-12-11011 December 2017 2017-12 Final Operating Tests ML18061A1682017-12-11011 December 2017 2017-12 Proposed Outline Comments ML18061A1662017-12-11011 December 2017 2017-12 Proposed Operating Test Comments ML18061A1692017-12-11011 December 2017 2017-12 Proposed Outlines IR 05000416/20173022017-11-30030 November 2017 NRC Initial Operator Licensing Examination Approval 05000416/2017302 ML17135A4262017-05-12012 May 2017 Notification of NRC Initial Operator Licensing Examination 05000416/2017302 GNRO-2017/00031, NRC Form 536 Response to Regulatory Issue Summary 2017-032017-05-0404 May 2017 NRC Form 536 Response to Regulatory Issue Summary 2017-03 ML17013A5482017-01-13013 January 2017 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2017 ML16291A2602016-10-13013 October 2016 Notification of NRC Initial Operator Licensing Examination 05000416/2017301 ML16272A1472016-09-28028 September 2016 Generic Fundamentals Examination Results Sept 2016 GNRO-2016/00042, NRC Form 536 Response to Regulatory Issue Summary 2016-09, Grand Gulf Nuclear Station, Unit 12016-07-29029 July 2016 NRC Form 536 Response to Regulatory Issue Summary 2016-09, Grand Gulf Nuclear Station, Unit 1 2024-01-16
[Table view] Category:Part 55 Examination Related Material
MONTHYEARIR 05000416/20243012024-01-16016 January 2024 NRC Initial Operator Licensing Examination Approval 05000416/2024301 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23102A1482023-04-12012 April 2023 Notification of NRC Initial Operator Licensing Examination 05000416/2024301 ML22342B2602022-10-14014 October 2022 10 Public Forms ML22342B2592022-10-14014 October 2022 10 Post Examination Analysis ML22075A3442022-03-16016 March 2022 Response to Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21342A2702021-12-0808 December 2021 GG-2022-10 Corp Notification Ltr - Cco, Grand Gulf Nuclear Station - Notification of NRC Initial Operator Licensing Examination 05000416/2022301 ML21333A2532021-10-25025 October 2021 GG-2021-10 Post Exam Analysis ML21349A1562021-10-25025 October 2021 GG-2021-10 Public Forms ML21280A0732021-10-0707 October 2021 NRC Initial Operator Licensing Examination Approval 05000416/2021301 ML21106A1512021-04-16016 April 2021 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations ML21041A5352021-02-11011 February 2021 Notification of NRC Initial Operator Licensing Examination 05000416/2021301 ML20072L2192020-03-12012 March 2020 Response to Regulatory Issue Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML20069C2262020-03-0909 March 2020 Notification of NRC Initial Operator Licensing Examination 05000416/2020302 ML20058H6182020-02-10010 February 2020 GG-2020-02 Draft Written Examination ML20058H6242020-02-10010 February 2020 GG-2020-02 Final Written Examination ML20058H6172020-02-10010 February 2020 GG-2020-02 Draft Written Examination Comments ML20058H6142020-02-10010 February 2020 GG-2020-02 Draft Operating Test ML20058H6212020-02-10010 February 2020 GG-2020-02 Final Operating Test ML20058H6262020-02-10010 February 2020 GG-2020-02 Draft Outline Comments ML20058H6152020-02-10010 February 2020 GG-2020-02 Draft Outlines ML20058J8112020-02-10010 February 2020 GG-2020-02 Public Forms ML20058J8102020-02-10010 February 2020 GG-2020-02 Post Examination Analysis ML20058H6222020-02-10010 February 2020 GG-2020-02 Final Outlines ML20058H6112020-02-10010 February 2020 GG-2020-02 Draft Operating Test Comments ML19135A6642019-05-15015 May 2019 Units 2 & 3; River Bend, and Waterford 3 - Response to RIS 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19128A1582019-05-0808 May 2019 Notification of NRC Initial Operator Licensing Examination 05000416/2020301 ML18116A2382018-04-26026 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations. ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18061A1722017-12-11011 December 2017 2017-12 Public Forms ML18061A1672017-12-11011 December 2017 2017-12 Proposed Operating Tests ML18061A1712017-12-11011 December 2017 2017-12 Proposed Written Exams ML18061A1702017-12-11011 December 2017 2017-12 Proposed Written Exam Comments ML18061A1682017-12-11011 December 2017 2017-12 Proposed Outline Comments ML18061A1692017-12-11011 December 2017 2017-12 Proposed Outlines ML18050A0552017-12-11011 December 2017 2017-12 Final Operating Tests ML18050A0562017-12-11011 December 2017 2017-12 Post-Exam Analysis ML18050A0542017-12-11011 December 2017 2017-12 Final Written Exams ML18061A1652017-12-11011 December 2017 2017-12 Final Outlines ML18061A1662017-12-11011 December 2017 2017-12 Proposed Operating Test Comments ML17135A4262017-05-12012 May 2017 Notification of NRC Initial Operator Licensing Examination 05000416/2017302 GNRO-2017/00031, NRC Form 536 Response to Regulatory Issue Summary 2017-032017-05-0404 May 2017 NRC Form 536 Response to Regulatory Issue Summary 2017-03 ML16291A2602016-10-13013 October 2016 Notification of NRC Initial Operator Licensing Examination 05000416/2017301 ML16272A1472016-09-28028 September 2016 Generic Fundamentals Examination Results Sept 2016 GNRO-2016/00042, NRC Form 536 Response to Regulatory Issue Summary 2016-09, Grand Gulf Nuclear Station, Unit 12016-07-29029 July 2016 NRC Form 536 Response to Regulatory Issue Summary 2016-09, Grand Gulf Nuclear Station, Unit 1 ML15351A0282015-12-17017 December 2015 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2016 ML16028A0202015-12-14014 December 2015 2015-12 Draft Op Tests ML16028A0212015-12-14014 December 2015 2015-12 Draft Op Test Comments ML16028A0222015-12-14014 December 2015 2015-12 Final Outlines ML16028A0242015-12-14014 December 2015 2015-12 Public Forms 2024-01-16
[Table view] |
Text
DRAFT OUTLINE COMMENTS Facility: GG First Exam Date: December 5-9, 2011 Written Exam Outline (Date)
Comment Resolution Ensure revision numbers at the page Request we do this at the question level 1
level for SRO/RO written exam. (versus page level)
SRO- re-sample Tier 3 (Radiation Replaced with 2.3.11 2 Control) K/A 2.3.4. SROs have had this K/A on the last two exams.
3 4
5 Administrative JPM Outline (Date)
Comment Resolution SRO - Emergency Procedures/Plan, K/A 1 2.4.41 used on last two exams. Re-sample this K/A RO - Equipment Control, K/A 2.2.13 2 used on last two exams. Re-sample this K/A.
Was the admin previously used on the Yes. Selected randomly from all on previous 3
RO exam from 2010 randomly selected? 2 exams.
4 5 OBDI 202 - IOLE Process
Control Room / In-Plant System JPM Outline (Date)
Comment Resolution Need K/A and Importance Rating Done 1
notated for each JPM.
Any of the Simulator JPMs to be ran in Yes. See proposed schedule.
2 parallel?
288000/Secure Fuel Pool Sweep- this This was intended as a backup JPM. It has appears to be a ninth Simulator JPM been removed from the outline.
which is unnecessary. Also, this JPM is 3
designed to be administered in the Control Room. No JPMs on this test will be administered in the control room.
Startup Shutdown Cooling B - I assume Correct.
4 this is RHR pump B?
5 Simulator Scenario Outline Comments (Date)
Comment Resolution 1 Add Rev number to all D-1s. Revision numbers added Scenario 1, Event 8: Critical Task to Note 1 (at the end of this document) place the Mode Switch in Shutdown when the reactor enters the Exclusion 2
Region on the power to flow map -
Should this critical task occur before entering this region?
Scenario 1, Event 9: Critical Task to Note 1 restore RPV level greater than -191 when reactor pressure decreases to 3
219#. Does this task need to occur before a certain parameter is reached?
Define the failure mode of this task.
Scenario 1, Event 10: This is the third The ACROs actions that result from event 7 major for this scenario and it looks like (loss of AC) are wrapped up in event 8 (RPS 4 only the ACRO gets credit. Does the automatic scram does not occur).
ACRO not have any verifiable actions on the major for loss of AC? OBDI 202 - IOLE Process
Scenario 1, Event 7: Loss of Service This is a partial loss of AC power; however, Transformer 11. Is this a loss of all AC? this loss of AC causes a loss of both RFPTs It appears the guiding procedure is an and a loss of the only remaining Recirc pump, 5 Off Normal which leads me to think this both of which would normally cause an should be counted as an Abnormal and automatic scram. RPS fails to scram in this not a major unless it is a total loss of AC. scenario and a manual scram is inserted by the ACRO.
Scenario 1, Event 10: What EP is A FW rupture inside the drywell will result in 6
entered for this major? an entry into EP-3 (containment)
Scenario 2, Event 5: Does the ACRO The ACRO will be directed to bypass an have verifiable actions for failure of two APRM.
7 APRM channels in order to constitute an Instrument bean?
Scenario 2, Event 6: Critical task for the Note 1 crew to close MSIVs when MSL annunciators alarm. Define by when this 8 task has to be completed. If the crew closes MSIVs 5 minutes after alarms is this ok? Need drop dead limit to define success.
Scenario 2, Event 8: What is the I/C This requires the operator to attempt to event and verifiable actions for the isolate the leak by placing the E51-F063/F064 ACRO/BOP for the RCIC room handswitches in the closed position. Also, this 9
unisolable steam leak? scenario simulates a motor pinion failure in which the isolation does not complete and the operator must identify and report this failure.
Scenario 2, Event 8: Critical Task to Note 1 emergency depressurize. Is there a 10 pressure limit by when this has to be done? Define by what limit this task must be completed.
Scenario 3, Event 4: Appears to be one The other abnormal is event 3.
of two Abnormals listed for this scenario.
What is the other scenario? Event 6 11 utilizes an ONEP but is a Major and could not be counted as an Abnormal as well.
Scenario 4, Event 3: No actions taken to This bus is locked out. Operators may 12 restore the 16BB3 bus? attempt to re-shut the breaker once, but this will not restore bus power in this case.
Scenario 4, Event 4: Control Rod Drift is This leads to a scram. The crew will reduce categorized as a Major event. Does this power using Recirc flow control valves, but 13 event lead to scram? Appears to be an when a second rod begins to drift the ONEP Abnormal. If it is a Major it cant be will require a scram.
counted as an Abnormal.
Scenario 4: What are the Abnormal Outline revised to reflect 1 Abnormal event.
events in this scenario? No 14 component/instrument failure after event 5 (or event 4 if this really is a Major) can be counted as an Abnormal event. OBDI 202 - IOLE Process
Scenario 4, Event 4: If event 4 is a Prior to the scram, the operator is required to 15 Major it cant count as a Reactivity event lower reactor power using Recirc flow control as well. valves.
Scenario 4, Event 6: Critical Task to re- Critical task revised to reflect the crews need energize the 17AC bus with an alternate for this bus. Note 1 does not apply This CT is 16 feeder. When does this have to be per NUREG-1021 App D.
completed? Define success.
Scenario 4, Event 7: This event utilizes Cooling water is not restored to this Diesel 17 an Ops philosophy procedurewill Generator.
cooling water be restored to this DG?
General Outline Comments (7/20/10)
Comment Resolution Suggested improvement - cross Will add specific question KAs used on next reference of written exam KAs to outline submittal with the draft exam on 55.41/43 and op test KAs to 55.45. This 10/14/11.
1 would provide objective evidence for 4.b on Exam Outline Quality Checklist (ES-201-2).
2 Ensure initial schedule is marked Rev. 0 Done.
Suggested improvement - provide Memorandum of Exam Methodology summary of safety analysis and industry attached.
3 OE used in op test development (Required by ES-301 D.1.f.)
Add an A to D-1 Event Type to specify This item was added.
4 facility identified Abnormal Event.
ES-301-5 Transient and Event ES-301-5 Revised to reflect expected event 5 Checklist - Did not include RO bean count based on the proposed exam week counts for Scenario 3. Please revise. schedule.
ES-301 Scenario 4 is identified as ES-301-5 Revised to reflect expected event 6 the Back-up. Back-up scenario will be count based on the proposed exam week identified during validation week. schedule.
7 8
9 Note 1: Critical tasks were standardized (as a result of the 2009 INPO CPO) by GGNS procedure 14-S-02-21, Preparers Guide for Simulator Evaluation Scenarios. Critical tasks have been updated to reflect the specific criteria as defined in 14-S-02-21. OBDI 202 - IOLE Process