Letter Sequence Request |
---|
|
|
MONTHYEARML11353A3192011-12-13013 December 2011 12/8/11 Meeting Slides - Brown Ferry Nuclear Plant, Units 1, 2, and 3 - Meeting with the Tennessee Valley Authority (TVA) to Discuss Delay in Submittal of Fire Risk Reduction Amendment Request Project stage: Meeting ML12017A1862012-01-13013 January 2012 Revised Submittal Schedule for License Amendment Request to Adopt National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Request ML12053A0192012-02-17017 February 2012 Additional Planned Fire Risk Reduction Modifications Project stage: Request ML12055A0632012-02-24024 February 2012 Notice of Forthcoming Meeting with Tennessee Valley Authority (TVA) Regarding Fire Protection Project stage: Request ML12066A1962012-03-0909 March 2012 National Fire Protection Association (NFPA) -805 License Amendment Request Delay Project stage: Other ML12083A1982012-03-20020 March 2012 Request for Extension of Enforcement Discretion Regarding Transition to National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Request ML12053A1882012-05-18018 May 2012 Plants, Units 1, 2, and 3 - Letter - Confirmatory Order (Effective Immediately) (TAC Nos. ME7841, ME7842, and ME7843) Project stage: Other ML12053A1902012-05-18018 May 2012 Federal Register Notice - Confirmatory Order Modifying License (Effective Immediately) Project stage: Other ML12171A3632012-06-28028 June 2012 Summary of Meeting with Tennessee Valley Authority to Discuss the National Fire Protection Association - 805 Transition for Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Meeting ML12240A0802012-09-10010 September 2012 10/3/2012 Notice of Forthcoming Meeting with Tennessee Valley Authority Regarding Voluntary Fire Protection Risk Initiative Project stage: Request ML12272A0612012-09-28028 September 2012 11/8/12 Notice of Forthcoming Meeting with Tennessee Valley Authority Regarding Voluntary Fire Protection Risk Initiative for Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Request ML12324A3352012-11-0808 November 2012 11/8/12 Meeting Slides Regarding Browns Ferry Nuclear Plant Risk Reduction and NFPA 805 Transition Update Project stage: Meeting ML12324A3322012-11-30030 November 2012 11/8/12 Summary of Meeting with Tennessee Valley Authority to Discuss the NFPA-805 Transition for Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Meeting 2012-02-24
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000259/20240032024-11-0404 November 2024 Integrated Inspection Report 05000259/2024003 and 05000260/2024003 and 05000296/2024003 CNL-24-043, Application for Subsequent Renewed Operating Licenses, Second Safety Supplement2024-11-0101 November 2024 Application for Subsequent Renewed Operating Licenses, Second Safety Supplement ML24305A1692024-10-31031 October 2024 Site Emergency Plan Implementing Procedure Revision 05000259/LER-2024-003, Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators2024-10-29029 October 2024 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators 05000259/LER-2024-001-02, Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure2024-10-28028 October 2024 Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure ML24299A2632024-10-25025 October 2024 Response to Apparent Violation in NRC Inspection Report 05000260/2024090, EA-24-075 ML24289A1232024-10-24024 October 2024 Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24308A0042024-10-16016 October 2024 Ahc 24-1578 Environmental Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Subsequent License Renewal Application Limestone County CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 ML24239A3332024-09-0303 September 2024 Full Audit Plan IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request IR 05000259/20244022024-08-0606 August 2024 Security Baseline Inspection Report 05000259/2024402 and 05000260/2024402 and 05000296/2024402 ML24219A0272024-08-0606 August 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000259/20240022024-08-0202 August 2024 Brown Ferry Nuclear Plant – Integrated Inspection Report05000259/2024002 and 05000260/2024002 and 05000296/2024002 ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24183A4142024-07-10010 July 2024 – License Renewal Regulatory Limited Scope Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-SLE-0000) (Docket Numbers: 50-259, 50-260, and 50-296) 05000296/LER-2024-003, Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints2024-07-0808 July 2024 Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints 05000259/LER-2024-001-01, Inoperability of Unit 3 Diesel Generator Due to Relay Failure2024-07-0303 July 2024 Inoperability of Unit 3 Diesel Generator Due to Relay Failure ML24184A1142024-07-0202 July 2024 Site Emergency Plan Implementing Procedure Revision ML24183A3842024-07-0101 July 2024 Registration of Use of Cask to Store Spent Fuel (MPC-364, -365) ML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) 05000259/LER-2024-002, Reactor Scram Due to Generator Step-Up Transformer Failure2024-06-24024 June 2024 Reactor Scram Due to Generator Step-Up Transformer Failure ML24175A0042024-06-23023 June 2024 Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System ML24176A1132024-06-23023 June 2024 American Society of Mechanical Engineers, Section XI, Fourth 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owner’S Activity Report Cycle 21 Oper ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24155A0042024-06-18018 June 2024 Proposed Alternative to the Requirements of the ASME Code (Revised Alternative Request 0-ISI-47) ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24071A0292024-06-0505 June 2024 Subsequent License Renewal Application Enclosure 3 - Proprietary Determination Letter ML24068A2612024-06-0505 June 2024 SLRA Fluence Methodology Report - Proprietary Determination Letter IR 05000259/20244032024-05-22022 May 2024 – Security Baseline Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 05000260/LER-2024-002, High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation2024-05-20020 May 2024 High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A0702024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000259/20240012024-05-14014 May 2024 Integrated Inspection Report 05000259/2024001, 05000260/2024001, and 05000296/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24123A2012024-05-0202 May 2024 NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000259/2024404, 05000260-2024404, 05000296/2024404) and Request for Information ML24122A6852024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual 2024-09-03
[Table view] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 January 13, 2012 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296
Subject:
Revised Submittal Schedule for License Amendment Request to Adopt National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection For Light Water Reactor Generating Plants, 2001 Edition for Browns Ferry Nuclear Plant Units 1, 2, and 3
Reference:
- 1. Letter from TVA to NRC, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 -
Letter of Intent to Adopt National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition, dated March 4, 2009.
- 2. Letter from TVA to NRC, Supplemental Information Related to the Reply to Notice of Violation; EA-09-307, dated October 29, 2010.
The purpose of this letter is to inform the NRC of the revised Tennessee Valley Authority (TVA) schedule for submitting an application to adopt the NFPA Standard 805 for the Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3. By letter dated March 4, 2009 (Reference 1), TVA informed the NRC of plans to submit a license amendment request to adopt NFPA Standard 805, Performance-Based Standard for Fire Protection For Light Water Reactor Generating Plants, within approximately three years of the reference letter.
At a public meeting between the NRC staff and TVA representatives on December 8, 2011, TVA described the strategy it has pursued of performing modifications to the BFN and its associated procedures in parallel with development of a license amendment request to adopt NFPA Standard 805. The objective of the parallel approach has been to achieve meaningful reduction in fire risk at BFN while pursuing the improved regulatory basis provided by NFPA Standard 805. As discussed at the December 8, 2011, meeting, TVA has completed several key modifications to the facility that have improved risk and substantially reduced the number of time critical operator manual actions required to implement the current safe shutdown fire strategy.
U.S. Nuclear Regulatory Commission Page 2 January 13, 2012 As also discussed at the December 8, 2011, meeting, TVA's development of a high quality NFPA 805 application will require more time than originally anticipated. The peer review of the BFN Fire Probabilistic Risk Assessment, a crucial step in the development of the NFPA 805 application, is planned to start on January 23, 2012. Consequently, TVA is revising its previous submittal schedule commitment. TVA will submit its application no later than March 29, 2013.
TVA committed in the letter dated October 29, 2010 (Reference 2) to complete the root cause corrective actions as scheduled. One of these root cause corrective actions is to submit the application to adopt the NFPA Standard 805 with a due date of March 4, 2012. As such, this revised submittal schedule represents a revision to that commitment and the corrective action due date will be revised to March 29, 2013.
While finalizing the submittal of the NFPA 805 application, TVA will continue its approach of developing and implementing additional fire risk reduction modifications to BFN design and procedures. To keep the NRC apprised of progress on these modifications, TVA will submit a detailed list of additional planned modifications and associated implementation schedules by February 17, 2012.
There is one revised commitment and one new commitment contained in this letter as discussed above and contained in the Enclosure to this letter.
If you have any question on these matters, please contact me at 423-718-9576.
Respect y, J. .hea,,Manager C rp ate Nuclear Licensing
Enclosure:
Regulatory Commitments cc (Enclosure):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant
ENCLOSURE Regulatory Commitments
- 1. TVA will submit a license amendment request for Browns Ferry Nuclear Plant, Units 1, 2, and 3, to adopt NFPA Standard 805 by no later than March 29, 2013.
- 2. TVA will submit a detailed list of additional planned fire protection modifications for Browns Ferry Nuclear Plant, Units 1, 2, and 3, and associated implementation schedules by February 17, 2012.