MONTHYEARML11353A3192011-12-13013 December 2011 12/8/11 Meeting Slides - Brown Ferry Nuclear Plant, Units 1, 2, and 3 - Meeting with the Tennessee Valley Authority (TVA) to Discuss Delay in Submittal of Fire Risk Reduction Amendment Request Project stage: Meeting ML12017A1862012-01-13013 January 2012 Revised Submittal Schedule for License Amendment Request to Adopt National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Request ML12053A0192012-02-17017 February 2012 Additional Planned Fire Risk Reduction Modifications Project stage: Request ML12055A0632012-02-24024 February 2012 Notice of Forthcoming Meeting with Tennessee Valley Authority (TVA) Regarding Fire Protection Project stage: Request ML12066A1962012-03-0909 March 2012 National Fire Protection Association (NFPA) -805 License Amendment Request Delay Project stage: Other ML12083A1982012-03-20020 March 2012 Request for Extension of Enforcement Discretion Regarding Transition to National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Request ML12053A1882012-05-18018 May 2012 Plants, Units 1, 2, and 3 - Letter - Confirmatory Order (Effective Immediately) (TAC Nos. ME7841, ME7842, and ME7843) Project stage: Other ML12053A1902012-05-18018 May 2012 Federal Register Notice - Confirmatory Order Modifying License (Effective Immediately) Project stage: Other ML12171A3632012-06-28028 June 2012 Summary of Meeting with Tennessee Valley Authority to Discuss the National Fire Protection Association - 805 Transition for Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Meeting ML12240A0802012-09-10010 September 2012 10/3/2012 Notice of Forthcoming Meeting with Tennessee Valley Authority Regarding Voluntary Fire Protection Risk Initiative Project stage: Request ML12272A0612012-09-28028 September 2012 11/8/12 Notice of Forthcoming Meeting with Tennessee Valley Authority Regarding Voluntary Fire Protection Risk Initiative for Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Request ML12324A3352012-11-0808 November 2012 11/8/12 Meeting Slides Regarding Browns Ferry Nuclear Plant Risk Reduction and NFPA 805 Transition Update Project stage: Meeting ML12324A3322012-11-30030 November 2012 11/8/12 Summary of Meeting with Tennessee Valley Authority to Discuss the NFPA-805 Transition for Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Meeting 2012-02-24
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A4762024-02-0101 February 2024 Final Report of a Part 21 Evaluation Associated with Starter Contactors for the BFN Unit 1 High Pressure Coolant Injection Suppression Pool Inboard Suction Valve ML24023A2802024-01-23023 January 2024 Final Report of a Deviation or Failure to Comply Associated with a Relay in the Reactor Core Isolation Cooling Condensate Pump CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24016A3042024-01-16016 January 2024 Final Report of a Part 21 Evaluation Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 ML24022A1732024-01-0303 January 2024 Receipt and Availability of the Subsequent License Renewal Application ML23319A1992024-01-0303 January 2024 Issuance of Amendment Nos. 333, 356, and 316 Regarding the Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves ML23355A2062023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23348A3942023-12-14014 December 2023 Interim Part 21 Report of a Potential Deviation or Failure to Comply Associated with Starter Contactors for the High Pressure Coolant Injection Suppression Pool Inboard Suction Valve IR 05000259/20230102023-12-11011 December 2023 Commercial Grade Dedication Inspection Report 05000259/2023010 and 05000260/2023010 and 05000296/2023010 ML23335A0722023-12-0101 December 2023 Interim Report of a Deviation or Failure to Comply Associated with a Relay in the Unit 2 Reactor Core Isolation Cooling Condensate Pump ML23334A2492023-11-30030 November 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-070, Submittal of Fifth 10-Year Interval Inservice Testing Program Plan2023-11-29029 November 2023 Submittal of Fifth 10-Year Interval Inservice Testing Program Plan ML23331A2532023-11-27027 November 2023 Summary Report for 10 CFR 50.9 Evaluations, Technical Specifications Bases Changes, Technical Requirement Manual Changes, and NRC Commitment Revisions CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23325A1102023-11-21021 November 2023 Anchor Darling Double Disc Gate Valve Commitment Revision ML23320A2542023-11-16016 November 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump IR 05000259/20230032023-11-13013 November 2023 Integrated Inspection Report 05000259/2023003, 05000260/2023003 and 05000296/2023003 IR 05000259/20230402023-11-0202 November 2023 Supplemental Inspection Supplemental Report 05000259 2023040 and Follow-Up Assessment Letter ML23292A2532023-10-18018 October 2023 BFN 2024-301, Corporate Notification Letter (210-day Ltr) ML23282A0022023-10-0606 October 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump ML23278A0122023-10-0505 October 2023 Updated Final Safety Analysis Report, Amendment 30 ML23271A1702023-09-28028 September 2023 Site Emergency Plan Implementing Procedure Revision ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23257A1232023-09-22022 September 2023 Administrative Changes to Technical Specification Pages Issued for License Amendment Nos. 332, 355, and 315 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23263B1042023-09-20020 September 2023 Special Report 260/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML23205A2132023-09-0808 September 2023 Issuance of Amendment Nos. 332, 355, and 315 Regarding the Revision of Technical Specifications to Adopt TSTF-566-A and TSTF-580-A, Rev. 1 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 ML23233A0432023-08-18018 August 2023 Enforcement Action EA-22-122 Inspection Readiness Notification ML23219A1542023-08-17017 August 2023 Request to Use Later Edition of ASME Code for Operation and Maintenance and Alternative Requests BFN-IST-01 Through 05 for the Fifth 10-Year Interval Inservice Testing Program ML23228A1642023-08-16016 August 2023 Site Emergency Plan Implementing Procedure Revision ML23228A0202023-08-15015 August 2023 (BFN) Unit 1 - Special Report 259/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation IR 05000259/20230022023-08-10010 August 2023 Integrated Inspection Report 05000259/2023002, 05000260/2023002, 05000296/2023002 and 07200052/2023001 ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills ML23171A8862023-07-24024 July 2023 Issuance of Amend. Nos. 331, 354, and 314; 365 and 359 Regarding Adoption of TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML23201A2182023-07-20020 July 2023 Registration of Use of Cask to Store Spent Fuel (MPC-298 and -299) ML23159A2552023-07-20020 July 2023 Proposed Alternative to the Requirements of the ASME Code Regarding Volumetric Inspection of Standby Liquid Control Nozzles ML23199A3072023-07-18018 July 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions IR 05000259/20233012023-07-18018 July 2023 NRC Operator License Examination Report Nos. 05000259/2023301, 05000260/2023301, and 05000296/2023301 2024-02-01
[Table view] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 January 13, 2012 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296
Subject:
Revised Submittal Schedule for License Amendment Request to Adopt National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection For Light Water Reactor Generating Plants, 2001 Edition for Browns Ferry Nuclear Plant Units 1, 2, and 3
Reference:
- 1. Letter from TVA to NRC, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 -
Letter of Intent to Adopt National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition, dated March 4, 2009.
- 2. Letter from TVA to NRC, Supplemental Information Related to the Reply to Notice of Violation; EA-09-307, dated October 29, 2010.
The purpose of this letter is to inform the NRC of the revised Tennessee Valley Authority (TVA) schedule for submitting an application to adopt the NFPA Standard 805 for the Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3. By letter dated March 4, 2009 (Reference 1), TVA informed the NRC of plans to submit a license amendment request to adopt NFPA Standard 805, Performance-Based Standard for Fire Protection For Light Water Reactor Generating Plants, within approximately three years of the reference letter.
At a public meeting between the NRC staff and TVA representatives on December 8, 2011, TVA described the strategy it has pursued of performing modifications to the BFN and its associated procedures in parallel with development of a license amendment request to adopt NFPA Standard 805. The objective of the parallel approach has been to achieve meaningful reduction in fire risk at BFN while pursuing the improved regulatory basis provided by NFPA Standard 805. As discussed at the December 8, 2011, meeting, TVA has completed several key modifications to the facility that have improved risk and substantially reduced the number of time critical operator manual actions required to implement the current safe shutdown fire strategy.
U.S. Nuclear Regulatory Commission Page 2 January 13, 2012 As also discussed at the December 8, 2011, meeting, TVA's development of a high quality NFPA 805 application will require more time than originally anticipated. The peer review of the BFN Fire Probabilistic Risk Assessment, a crucial step in the development of the NFPA 805 application, is planned to start on January 23, 2012. Consequently, TVA is revising its previous submittal schedule commitment. TVA will submit its application no later than March 29, 2013.
TVA committed in the letter dated October 29, 2010 (Reference 2) to complete the root cause corrective actions as scheduled. One of these root cause corrective actions is to submit the application to adopt the NFPA Standard 805 with a due date of March 4, 2012. As such, this revised submittal schedule represents a revision to that commitment and the corrective action due date will be revised to March 29, 2013.
While finalizing the submittal of the NFPA 805 application, TVA will continue its approach of developing and implementing additional fire risk reduction modifications to BFN design and procedures. To keep the NRC apprised of progress on these modifications, TVA will submit a detailed list of additional planned modifications and associated implementation schedules by February 17, 2012.
There is one revised commitment and one new commitment contained in this letter as discussed above and contained in the Enclosure to this letter.
If you have any question on these matters, please contact me at 423-718-9576.
Respect y, J. .hea,,Manager C rp ate Nuclear Licensing
Enclosure:
Regulatory Commitments cc (Enclosure):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant
ENCLOSURE Regulatory Commitments
- 1. TVA will submit a license amendment request for Browns Ferry Nuclear Plant, Units 1, 2, and 3, to adopt NFPA Standard 805 by no later than March 29, 2013.
- 2. TVA will submit a detailed list of additional planned fire protection modifications for Browns Ferry Nuclear Plant, Units 1, 2, and 3, and associated implementation schedules by February 17, 2012.