I was given all the info for the unit 2 SGISI already too.
From: Rivera-Ortiz, Joel Sent: Thursday, September 15, 2011 10:45 AM To: Fletcher, Cecil
Subject:
From: Fletcher, Cecil Sent: Thursday, September 15, 2011 10:44 AM To: Rivera-Ortz, Joel
Subject:
RE: SG ISI Joel...sorry, I just read my email.
The licensee is about 80% complete with bobbin inspection which is a qualified technique which can be used to discover dents/dings and bulges, and they have not found any indications that there was any damage to the tubes due to the earthquake. As stated before, the expected damage if there was going to be any would be dents/dings or bulges at the AVB and/or TSP locations.
To add, they have completed the bobbin on all of the u-tubes on the periphery tubes and they are on the low row tubes now. They are doing about a 25% sample of RPC also during this inspection period.
As far as the schedule, they are on target to complete Unit I SG A SGISI on Monday. So, it still looks like they will be about 50% done on Unit 2 SGISI on Saturday, Sep 2 4 th.
Cecil From: Rivera-Ortiz, Joel Sent: Thursday, September 15, 2011 7:03 AM To: Fletcher, Cecil
Subject:
SG ISI Could you give me an update (before the 9:15am if practical) on the types of indications found so far on Unit 1?