1 Davis-BesseNPEm Resource From:
CuadradoDeJesus, Samuel Sent:
Tuesday, December 13, 2011 11:46 AM To:
dorts@firstenergycorp.com Cc:
Davis-BesseHearingFile Resource
Subject:
FW: NRC-FENOC Telephone Conference Notes from December 8, 2011 Attachments:
NRC telecon 20111208 RAI 4.7.4-1.pdf thanks From: dorts@firstenergycorp.com [1]
Sent: Friday, December 09, 2011 10:36 AM To: CuadradoDeJesus, Samuel Cc: custerc@firstenergycorp.com
Subject:
NRC-FENOC Telephone Conference Notes from December 8, 2011 Sam..... attached are the telephone conference notes from the call held on December 8, 2011, for your information.
Please contact me with any questions regarding the attached.
Thank you, Steve Dort DBNPS License Renewal
The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify us immediately, and delete the original message.
Hearing Identifier:
Davis_BesseLicenseRenewal_Saf_NonPublic Email Number:
2729 Mail Envelope Properties (377CB97DD54F0F4FAAC7E9FD88BCA6D0806FAAF995)
Subject:
FW: NRC-FENOC Telephone Conference Notes from December 8, 2011 Sent Date:
12/13/2011 11:46:12 AM Received Date:
12/13/2011 11:46:13 AM From:
CuadradoDeJesus, Samuel Created By:
Samuel.CuadradoDeJesus@nrc.gov Recipients:
"Davis-BesseHearingFile Resource" <Davis-BesseHearingFile.Resource@nrc.gov>
Tracking Status: None "dorts@firstenergycorp.com" <dorts@firstenergycorp.com>
Tracking Status: None Post Office:
HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 1093 12/13/2011 11:46:13 AM NRC telecon 20111208 RAI 4.7.4-1.pdf 23370 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
Doc No. 120811 TO:
File DATE: December 8, 2011 FROM:
Larry Hinkle
SUBJECT:
NRC Telecon Regarding Davis-Besse License Renewal NRC Attendees:
Sam Cuadrado de Jesus, Allen Hiser, Christopher Sydnor, On Yee FENOC Attendees: Allen McAllister, Larry Hinkle, Steven Dort This telephone conference call was initiated by Sam Cuadrado de Jesus, NRC Project Manager for Davis-Besse License Renewal. The telecon took place at 11:00 A.M. on December 8, 2011. The purpose of the call was to discuss the FENOC response to NRC request for additional information (RAI) 4.7.4-1 regarding the HPI/makeup nozzle thermal sleeve time-limited aging analysis (TLAA), submitted by FENOC letter dated October 31, 2011 (ML11306A066).
- 1. Relative to commitment 23 of the LRA, the NRC reviewer wanted clarification as to why the commitment to replace the high pressure injection (HPI)/makeup nozzle thermal sleeve was removed.
FENOC responded that since the HPI/makeup nozzle thermal sleeve TLAA was dispositioned using 10 CFR 54.21(c)(1)(iii) where the effects of cracking on the thermal sleeve are managed by the Inservice Inspection (ISI) Program, the commitment to replace the thermal sleeve was no longer deemed applicable. FENOC noted that the VT-1 visual examination of the HPI/makeup nozzle thermal sleeve conducted on a frequency of once every other refueling outage will continue through the period of extended operation. It was further noted that subsequent inspections conducted after replacement of the HPI/makeup nozzle thermal sleeve in the Cycle 13 refueling outage found no indications of cracking.
The NRC staff found the above clarification acceptable and had no further questions or applicant follow-up actions.
- 2. Relative to the ISI Program, the NRC reviewer wanted to know the type and frequency of the inspection for the HPI/makeup nozzle thermal sleeve.
FENOC responded that this information was included in the changes to the License Renewal Application (LRA) associated with the response to RAI 4.7.4-
- 1. Specifically, revised LRA Sections 4.7.4 and A.2.7.4 provide that the ISI Program requires a VT-1 visual examination of the makeup nozzle once every other refueling outage.
The staff found the above clarification acceptable and had no further questions or applicant follow-up actions.
There was no further discussion, and the call was concluded.