UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 December 19, 2011 NOTICE OF SIGNIFICANT LICENSEE MEETING REGULATORY CONFERENCE THIS MEETING IS OPEN TO PUBLIC ATTENDANCE Name of Licensee:
Entergy Nuclear Palisades, LLC - Michigan Name of Facility:
Palisades Nuclear Plant Docket No:
50-255 EA Number:
EA-11-241 Date and Time of Meeting:
Wednesday, January 11, 2012, at 9:00 A.M. (CST)
Location of Meeting:
RIII Office, Main Conference Room 2443 Warrenville Road Suite 210 Lisle, IL 60532 Purpose of Meeting:
The Regulatory Conference with the licensee is to discuss a Preliminary White finding associated with the failure of a safety-related service water pump (P-7C) on August 9, 2011.
The conference will also address whether enforcement action is warranted. The details regarding the issue are contained in Inspection Report 05000255/2011016 (ML113330819).
Meeting Category:
This is a Category 1 Meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned. Interested members of the public can participate in this meeting via a toll-free teleconference. For details please call Diana Betancourt at 630-829-9617 or email her at Diana.Betancourt@nrc.gov by January 9, 2012.
Notice of Significant Licensee Meeting NRC Attendees:
C. Pederson, Acting Regional Administrator, RIII J. Uhle, Acting Deputy Regional Administrator, RIII S. West, Director, Division of Reactor Projects, RIII G. Shear, Deputy Director, Division of Projects, RIII J. Giessner, Chief, Branch 4, Division of Reactor Projects, RIII J. Ellegood, Senior Resident Inspector, Palisades N. Valos, Senior Risk Analyst, Division of Reactor Projects, RIII D. Passehl, Senior Risk Analyst, Division of Reactor Projects, RIII Others as designated Licensee Attendees:
A. Vitale, Site Vice President D. Hamilton, Plant Manager A. Blinde, Engineering Director Others as designated Other Attendees:
None The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript or other information from the meeting in another format (e.g. Braille, large print), please notify the NRC meeting contact no later than 2 business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by January 9, 2012, via telephone to the NRC meeting contact.
Approved by: _________/RA/_________________
John B. Giessner, Chief Branch 4 Division of Reactor Projects Meeting
Contact:
Diana Betancourt 630-829-9617 Diana.Betancourt@nrc.gov DISTRIBUTION See Next Page
Notice of Significant Licensee Meeting Distribution:
OEWEB OEMAIL Mary Ann Ashley, Technical Assistant (Enforcement), NRR Ryan Eul, Enforcement Specialist, OE Aida Rivera-Varona, Technical Assistant, OE Amy Snyder, Region III Coordinator, OEDO Robert Nelson, Deputy Director, Division of Operating Reactor Licensing (DORL), NRR RidsNrrPMPalisades Resource RidsNrrDorlLpl3-1 Resource Steven West, Director, Division of Reactor Projects, RIII Steven Reynolds, Director, Division of Reactor Safety, RIII Gary Shear, Deputy Director, Division of Reactor Projects, RIII Kenneth OBrien, Deputy Director, Division of Reactor Safety, RIII DRP Branch Chief SRI, Palisades DRS Branch Chiefs:
Robert Daley David Hills Richard Skokowski AnnMarie Stone Billy Dickson Hironori Peterson Allan Barker, Regional State Liaison Officer, RIII PMNS Viktoria Mitlyng, RIII Public Affairs Prema Chandrathil Tammy Tomczak, ORA Patricia Buckley, ORA Marjorie Zerth, DRP
Notice of Significant Licensee Meeting NRC Attendees:
C. Pederson, Acting Regional Administrator, RIII J. Uhle, Acting Deputy Regional Administrator, RIII S. West, Director, Division of Reactor Projects, RIII G. Shear, Deputy Director, Division of Projects, RIII J. Giessner, Chief, Branch 4, Division of Reactor Projects, RIII J. Ellegood, Senior Resident Inspector, Palisades N. Valos, Senior Risk Analyst, Division of Reactor Projects, RIII D. Passehl, Senior Risk Analyst, Division of Reactor Projects, RIII Others as designated Licensee Attendees:
A. Vitale, Site Vice President D. Hamilton, Plant Manager A. Blind, Engineering Director Others as designated Other Attendees:
None The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript or other information from the meeting in another format (e.g. Braille, large print), please notify the NRC meeting contact no later than 2 business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by January 9, 2012, via telephone to the NRC meeting contact.
Approved by: ___________/RA/_______________
John B. Giessner, Chief Branch 4 Division of Reactor Projects Meeting
Contact:
Diana Betancourt 630-829-9617 Diana.Betancourt@nrc.gov DISTRIBUTION See Next Page See Previous Concurrence DOCUMENT NAME: G:\\DRPIII\\PALI\\Palisades Meeting Notice White.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII NAME DBetancourt-Roldan:dtp JGiessner SOrth DATE 12/15/11 12/19/11 12/15/11 OFFICIAL RECORD COPY