Request for Additional Information Regarding the 2010 Steam Generator Inspections
ML11320A015
Person / Time
Site: Surry Dominion icon.png
Issue date: 11/30/2011
From: Cotton K
Plant Licensing Branch II
To: Heacock D
Virginia Electric & Power Co (VEPCO)
Cotton K, 415-1438
References
TAC ME6375
Download: ML11320A015 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 30, 2011 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center SOOO Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

SURRY POWER STATION, UNIT NO.1 (SURRY UNIT 1) - REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING THE 2010 STEAM GENERATOR (SG) INSPECTIONS (TAC NO. ME637S)

Dear Mr. Heacock:

By letter dated May 24,2011, Virginia Electric and Power Company (the licensee) submitted SG tube inspection results from the 2010 inspections at Surry Unit 1.

The Nuclear Regulatory Commission staff has reviewed the information the licensee provided and determined that additional information is required in order to complete the evaluation. The requested additional information is enclosed. Please respond within 30 days of the date of this letter.

If you have any questions, please feel free to contact me at 301-41S-1438.

Sincerely, Karen Cotton, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. SO-280

Enclosure:

RAI cc wi encl: Distribution via Listserv

REQUEST FOR ADDITIONAL INFORMATION 2010 STEAM GENERATOR INSPECTIONS SURRY POWER STATION. UNIT NO.1 (SURRY UNIT 1)

DOCKET NO. 50-280 By letter dated May 24,2011 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML11154A101), Virginia Electric and Power Company (the licensee) submitted steam generator (SG) tube inspection results from the 2010 inspections at Surry Unit 1.

In order to complete its review of the documents listed above, the Nuclear Regulatory Commission staff needs the following additional information:

1. You state in your letter that the fall 2010 outage was the last outage in the 3fd, 60 effective full power month inspection period. Please clarify whether you met your technical specification requirement to inspect 100 percent of the tubes by the end of the inspection period (or a prorated sample percentage as discussed in Regulatory Information Summary 2009-04, "Steam Generator Tube Inspection ReqUirements," (ADAMS Accession Number ML083470557) with techniques capable offinding the forms of degradation to which the tubes are potentially susceptible.
2. Please discuss the results of the foreign object search and retrieval inspections that were performed in the three SGs. Also, please clarify whether you did the foreign object search and retrieval inspection before or after the replacement of the SG feedrings.
3. Previous dents whose voltages exceeded two volts were inspected with a rotating probe.

Please discuss what percentage of the dent population was inspected. Please discuss whether any new dents were identified during the 2010 inspections. If new dents were detected, please discuss whether they were inspected with a rotating probe. If not inspected with a rotating probe, discuss the basis for not performing such inspections.

4. In Table 9, there are several indications in SG B that showed a change between a prior inspection and the 2010 inspection. For these locations, no foreign object is listed at these locations. Were these locations visually inspected? Was a loose part or parts removed from these locations? If not, what caused the change in the eddy current signal? What were the magnitudes of the changes in the signal? If these indications continued to grow, would the tubes still have adequate integrity at the time of the next inspection?
5. Were any other secondary side inspections (other than those listed on page 4) performed (e.g., steam drum)? If so, discuss the scope and results of these inspections.

Enclosure

November 30,2011 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

SURRY POWER STATION UNIT NO.1 (SURRY UNIT 1) - REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING THE 2010 STEAM GENERATOR (SG) INSPECTIONS (TAC NO. ME6375)

Dear Mr. Heacock:

By letter dated May 24, 2011, Virginia Electric and Power Company (the licensee) submitted SG tube inspection results from the 2010 inspections at Surry Unit 1.

The Nuclear Regulatory Commission staff has reviewed the information the licensee provided and determined that additional information is required in order to complete the evaluation. The requested additional information is enclosed. Please respond within 30 days of the date of this letter.

If you have any questions, please feel free to contact me at 301-415-1438.

Sincerely, IRA!

Karen Cotton, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-280

Enclosure:

RAI cc wI encl: Distribution via Listserv DISTRIBUTION:

Public LPL2-1 RlF RidsNrrLAMO'Brien Resource RidsOgcRp Resource RidsRgn2MailCenter Resource RidsNrrDorlLpl2-1 Resource RidsAcrsAcnw _MaiICTR Resource RidsNrrPMSurry Resource RidsNrrDeEsgb Resource AJohnson, NRR ADAMS Accession No. ML11320A015

..transmitted b)v memo dated November 7 2 o11 OFFICE NRR/LPL2-1/PM NRRlLPL2-1/LA DElESGB/(A)BC NRR/LPL2-1/BC NRRlLPL2-1/PM NAME KCotton MOBrien VCusumano (EWong for)

GKulesa KCotton DATE 11/30/11 11/28/11 1117111 11/30/11 11130/11 OFFICIAL RECORD COpy