ML113140273
Letter Sequence Other | |
---|---|
TAC:ME7323, (Approved, Closed) | |
Initiation
Administration | |
MONTHYEARML1131402732011-11-10010 November 2011
[Table View]Find the Licensee'S Application for Exemption and Amendment Re. Optimized Zirlo Fuel Cladding Design Acceptable for Review Project stage: Other ML12088A1042012-03-19019 March 2012 Response to Information Request Pursuant to 10 CFR 50-.54 (F) Related to the Estimated Effect on Peak Cladding Temperature Resulting from Thermal Conductivity Degradation in the Westinghouse-Furnished. Project stage: Request ML12178A5342012-06-26026 June 2012 Draft RAI on Proposed Optimized Zirlo Amendment Project stage: Draft RAI AEP-NRC-2012-56, Response to Request for Additional Information Regarding the License Amendment Request for Use of Optimized Zirlo Fuel Rod Cladding2012-07-25025 July 2012 Response to Request for Additional Information Regarding the License Amendment Request for Use of Optimized Zirlo Fuel Rod Cladding Project stage: Response to RAI ML12124A2512012-08-16016 August 2012 Environmental Assessment for Optimized Zirlo Fuel Amendment and Exemption Project stage: Other ML12124A2352012-08-16016 August 2012 Environmental Assessment and Finding of No Significant Impact Related to a Proposed Exemption to Title 10 of the Code of Federal Regulations, Section 50.45 and Appendix K, and a Proposed Amendment Involving... Project stage: Other NRC-2012-0199, D. C. Cook: Environmental Assessment for Optimized Zirlo Fuel Amendment and Exemption2012-08-16016 August 2012 D. C. Cook: Environmental Assessment for Optimized Zirlo Fuel Amendment and Exemption Project stage: Other ML12142A2872012-08-23023 August 2012 Exemption from the Requirements of 10 CFR Section 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Clad Fuel Rods Project stage: Approval ML12142A2992012-08-23023 August 2012 Exemption from 10 CFR 50.46 and App. K of 10 CFR 50 to Permit Use of Optimized Zirlo Project stage: Approval ML12138A3982012-08-23023 August 2012 Issuance of Amendment No. 302 Regarding Optimized Zirlo Clad Fuel Rods Project stage: Approval 2012-06-26 |
ML113140273 | |
Person / Time | |
---|---|
Site: | Cook |
Issue date: | 11/10/2011 |
From: | Tam P Plant Licensing Branch III |
To: | Etheridge H Indiana Michigan Power Co |
Tam P | |
References | |
TAC ME7323 | |
Download: ML113140273 (1) | |
Similar Documents at Cook | |
---|---|
Category:E-Mail
MONTHYEARML23361A1022023-12-21021 December 2023
[Table view]Security Rule Exemption Request - ISFSI Docket No. Reference ML23321A1222023-11-17017 November 2023 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML23052A1502023-02-21021 February 2023 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Neutron Flux Instrumentation ML22307A2532022-11-0303 November 2022 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Verbal Authorization of Relief Request ISIR-5-06 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML22122A0902022-04-29029 April 2022 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-554, Revision 1 ML22250A6712022-02-16016 February 2022 Outline Submittal Notification Email DC-Cook 2022 ML21341A6252021-12-0707 December 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-577, Revision 1 ML21307A3352021-11-0303 November 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Final RAI - License Amendment Request Regarding Containment Water Level Instrumentation ML21236A0262021-08-23023 August 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Regarding Changes to Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection System Requirements ML21140A3052021-05-20020 May 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21113A2812021-04-23023 April 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Containment Water Level Instrumentation ML21089A0222021-03-24024 March 2021 DC Cook Power Operated Valves (POV) Preliminary Request for Information ML21082A0262021-03-22022 March 2021 Acceptance of Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21049A2682021-02-16016 February 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Final RAI - License Amendment Request for One-Time Extension Containment Type a ILRT ML21026A3472021-01-26026 January 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval ML21008A4742021-01-0808 January 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Request for One-Time Extension Containment Type a ILRT ML20366A1012020-12-31031 December 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Request for One-Time Deferral of Steam Generator Inspection ML20316A0152020-11-0606 November 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval ML20318A0202020-10-16016 October 2020 NRR E-mail Capture - Regarding Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20318A0192020-10-15015 October 2020 NRR E-mail Capture - (External_Sender) Supplemental Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20289A7122020-10-15015 October 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Verbal Authorization of Relief Request ISIR-5-04 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML20290A4252020-10-15015 October 2020 Verbal Authorization of Relief Request ISIR-5-04 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML20318A0182020-10-0909 October 2020 NRR E-mail Capture - (External_Sender) Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20289A1192020-10-0909 October 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request for Alternative to N-729-4 for RPV Head Visual Examination ML20181A4122020-06-29029 June 2020 NRR E-mail Capture - Final RAI - D.C. Cook 1 - One-Time Extension, Containment Type a ILRT Frequency ML20149K6272020-05-28028 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment and Exemptions Regarding UFSAR 10 CFR 50.71(e)(4) Update Schedule (Epids: L-2020-LLA-0100, L-2020-LLE-0052, L-2020-LLE-0053) ML20149K4332020-05-26026 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-567, Revision 1 ML20141L8112020-05-20020 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request Regarding Impracticality for Inservice Inspection for Certain Welds ML20141L6062020-05-20020 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-541, Revision 2 ML20136A5162020-05-15015 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-412, Revision 3 ML20133J9662020-05-11011 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Acceptance of License Amendment Regarding Changes to Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection System Requirements ML20232B4562020-04-27027 April 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Fragility Questions ML20232B4432020-03-25025 March 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Plant Response Model Questions ML19345F9382019-12-0909 December 2019 D.C. Cook 50.54(f) SPRA Submittal - Completeness Review Done and Path Forward ML19333B8042019-11-29029 November 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-569 (L-2019-LLA-0248) ML19309F9212019-11-0505 November 2019 Request for Eportal Access for Audit Review of the DC Cook SPRA Supporting Documents ML19270E7372019-09-26026 September 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-421, Reactor Coolant Pump Flywheel Inspection Program ML19207A4642019-07-26026 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Delete Diesel Generator Load Test Resistor Banks ML19204A0962019-07-23023 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Request for Additional Information Related to Unit 2 Leak Before Break Analysis and Deletion of Containment Humidity Monitors for Unit Nos. 1 and 2 ML19211C3032019-07-0303 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 & 2 - Request for Additional Information Related to LAR to Address NSAL-15-1 ML19175A3032019-06-24024 June 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance Review for LAR to Revise Battery Monitoring and Maintenance TS ML19092A4802019-04-0202 April 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-563 ML19092A4792019-04-0202 April 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Address Issues Identified in Westinghouse Document NSAL-15-1 ML19084A0002019-03-20020 March 2019 NRR E-mail Capture - Resubmitted: Draft Request for Additional Information DC Cook Unit 1 - Leak-Before-Break LAR ML19072A1432019-03-12012 March 2019 NRR E-mail Capture - Resubmitted: Draft Request for Additional Information DC Cook Unit 1 - Leak-Before-Break LAR ML19011A1382019-01-11011 January 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Revise Environmental Technical Specifications (L-2018-LLA-0570) ML19011A3512019-01-11011 January 2019 NRR E-mail Capture - Request for Additional Information DC Cook Unit 1 Leak Before Break Amendment ML19009A5402019-01-0909 January 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Revise Battery Monitoring and Maintenance TS ML18313A0802018-11-0808 November 2018 NRR E-mail Capture - D.C. Cook Units 1 and 2 - RAI for RPV Threads in Flange Alternative ML18275A0532018-10-0101 October 2018 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Revise Battery Monitoring and Maintenance TS 2023-02-21 |
Text
Accession No. ML113140273 From: Tam, Peter Sent: Thursday, November 10, 2011 10:21 AM To: 'hletheridge@aep.com'; mkscarpello@aep.com; 'jrwaters@aep.com' Cc: Wu, Shih-Liang; Feintuch, Karl
Subject:
D.C. Cook Unit 2 - Application for exemption and amendment re.
Optimized ZIRLO acceptable for review (TAC ME7323 Helen:
The NRC staff found your 9/29/2011 application for exemption and amendment (Accession No. ML11286A198) regarding use of Optimized ZIRLO fuel cladding design acceptable for review per the guidance of NRR Office Instruction LIC-109.
Peter S. Tam, Senior Project Manager (for D.C. Cook and Monticello)
Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Tel. 301-415-1451