Master Inspection Plan - Fiscal Year 2012
ML11294A217
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/14/2011
From: Christine Lipa
Division of Nuclear Materials Safety II
To: Plona J
Detroit Edison
References
Download: ML11294A217 (3)


Text

October 14, 2011 Mr. Joseph Plona Site Vice President Nuclear Generation The Detroit Edison Company 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

FERMI UNIT 1 MASTER INSPECTION PLAN FISCAL YEAR 2012

Dear Mr. Plona:

In accordance with U.S. NRC Inspection Manual Chapter 2561, Decommissioning Power Reactor Inspection Program, the NRC Region III staff and management have developed a Master Inspection Plan (MIP) for Fermi Unit 1. The plan is based on your current performance and schedule of significant decommissioning activities planned for the site for the period of October 2011 through December 2012. The plan outlines how we intend to focus our regional inspection resources to address significant ongoing decommissioning activities.

Because this MIP is based, in part, on your proposed schedule of significant decommissioning activities for fiscal year (FY) 2012; the plan and focus of the NRC inspection activities may change to reflect a change in your planned decommissioning activities or your performance. In order to ensure that this MIP remains current, we request that you keep the Materials Control, ISFSI and Decommissioning Branch (MCID) staff informed of any significant changes in your proposed schedule of decommissioning activities. You will be informed of any significant changes to the Fermi Unit 1 inspection schedule.

We currently project the region will conduct approximately three inspections at Fermi Unit 1 through December 2012 to evaluate the routine decommissioning activities. The following is a list of the inspection procedures we expect to use during our inspections. The specific procedures used during each inspection will depend on the specific decommissioning activities being conducted. Additional inspection procedures may be used or inspections conducted if decommissioning activities warrant.

Inspection Procedure Title IP 36801 Organization, Management and Cost Controls IP 37801 Safety Reviews, Design Changes, and Modifications IP 40801 Self-Assessment, Auditing, and Corrective Action IP 71801 Decommissioning Performance and Status Review IP 83750 Occupational Radiation Exposure

J. Plona IP 83890 Closeout Inspection and Survey IP 84750 Radioactive Waste Treatment, and Effluent and Environmental Monitoring IP 86750 Solid Radioactive Waste Management and Transportation of Radioactive Materials In accordance with Title 10 Code of Federal Regulations 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.

We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact Peter Lee of my staff at (630) 829-9870.

Sincerely,

/RA/

Christine A. Lipa, Chief Materials Control, ISFSI and Decommissioning Branch Division of Nuclear Materials Safety Docket No. 05000016 License No. DPR-9 cc: Distribution via ListServ

J. Plona IP 83890 Closeout Inspection and Survey IP 84750 Radioactive Waste Treatment, and Effluent and Environmental Monitoring IP 86750 Solid Radioactive Waste Management and Transportation of Radioactive Materials In accordance with Title 10 Code of Federal Regulations 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.

We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact Peter Lee of my staff at (630) 829-9870.

Sincerely,

/RA/

Christine A. Lipa, Chief Materials Control, ISFSI and Decommissioning Branch Division of Nuclear Materials Safety Docket No. 05000016 License No. DPR-9 cc: Distribution via ListServ

  • See previous concurrence DOCUMENT NAME: G:\DNMSIII\Work in progress\MIP- Fermi U1 FY12.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl N" = No copy OFFICE RIII DNMS RIII DNMS C RIII RIII NAME PJLee:jm PJL CALipa CAL DATE 10/13/11 10/14/11 OFFICIAL RECORD COPY