ML11293A239

From kanterella
Jump to navigation Jump to search
Lr - Davis Besse-Request for a Teleconference
ML11293A239
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 08/24/2011
From:
Office of Nuclear Reactor Regulation
To:
Division of License Renewal
References
Download: ML11293A239 (3)


Text

1 Davis-BesseNPEm Resource From:

CuadradoDeJesus, Samuel Sent:

Wednesday, August 24, 2011 1:11 PM To:

custerc@firstenergycorp.com Cc:

dorts@firstenergycorp.com; kmnesser@firstenergycorp.com; Davis-BesseHearingFile Resource

Subject:

RE: Davis Besse-Request for a Teleconference Cliff:

Ill be on training next week. Ill try to check if another PM can lead the call for me. Ill let you know.

Thanks From: custerc@firstenergycorp.com [1]

Sent: Wednesday, August 24, 2011 1:09 PM To: CuadradoDeJesus, Samuel Cc: dorts@firstenergycorp.com; kmnesser@firstenergycorp.com

Subject:

Re: Davis Besse-Request for a Teleconference Sam, We cannot support the call for tomorrow. How about Monday 8/29 @ 1300 hrs?

Cliff Custer FENOC Project Manager License Renewal Work: (724) 682-7139 BPR: (412) 305-4981 From: "CuadradoDeJesus, Samuel" <Samuel.CuadradoDeJesus@nrc.gov>

To: "custerc@firstenergycorp.com" <custerc@firstenergycorp.com>, "dorts@firstenergycorp.com" <dorts@firstenergycorp.com>

Cc: "Klos, John" <John.Klos@nrc.gov>, "Min, Seung" <Seung.Min@nrc.gov>, "Rogers, Billy" <Billy.Rogers@nrc.gov>, Davis-BesseHearingFile Resource

<Davis-BesseHearingFile.Resource@nrc.gov>

Date: 08/24/2011 09:20 AM

Subject:

Davis Besse-Request for a Teleconference Cliff Please let me know when we can have a Teleconference to discuss the topics listed below.

Topics of Discussion

1) August 17, 2011 Response to RAI 3.3.2.2.5-2 Revised AMP B2.9 Collection, Drainage, and Treatment Components Inspection Program. The NRC staff will request an updated B.2.9 scope of program section that repeats the new programs description shown in the letters B.2.9, program description section and a revised acceptance criteria element to include acceptance criteria for elastomeric components now added to the scope.
2) August 17, 2011 Supplemental Response - Abandoned Equipment Need to discuss commitment 26 implementation schedule
3) August 17, 2011 Supplemental Response - steam generator aging management review tube-to-tubesheet weld

2 The applicant stated the tube-to-tubesheet welds (Alloy 600 welds) for its steam generators do not have a license renewal intended function and therefore, are not subject to an aging management review. However, the staff found a need to further confirm that the original design analysis of the applicants once-through steam generators concluded that the interference fit between the tube and the tubesheets was sufficient to ensure the structural and leak-tight integrity of the tube-to-tubesheet joints, without a need for crediting the tube-to-tubesheet welds.

(See attached Draft RAI)

Regards, Samuel Cuadrado de Jesús Project Manager Projects Branch1 Division of License Renewal U.S. Nuclear Regulatory Commission Phone: 301-415-2946 Samuel.CuadradoDeJesus@nrc.gov


The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify us immediately, and delete the original message.

Hearing Identifier:

Davis_BesseLicenseRenewal_Saf_NonPublic Email Number:

1358 Mail Envelope Properties (377CB97DD54F0F4FAAC7E9FD88BCA6D07D50E2F9EC)

Subject:

RE: Davis Besse-Request for a Teleconference Sent Date:

8/24/2011 1:11:10 PM Received Date:

8/24/2011 1:11:12 PM From:

CuadradoDeJesus, Samuel Created By:

Samuel.CuadradoDeJesus@nrc.gov Recipients:

"dorts@firstenergycorp.com" <dorts@firstenergycorp.com>

Tracking Status: None "kmnesser@firstenergycorp.com" <kmnesser@firstenergycorp.com>

Tracking Status: None "Davis-BesseHearingFile Resource" <Davis-BesseHearingFile.Resource@nrc.gov>

Tracking Status: None "custerc@firstenergycorp.com" <custerc@firstenergycorp.com>

Tracking Status: None Post Office:

HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 3406 8/24/2011 1:11:12 PM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received: