MONTHYEARIR 05000254/20230042024-02-0505 February 2024
[Table view]Integrated Inspection Report 05000254/2023004 and 05000265/2023004 IR 05000454/20230042024-02-0202 February 2024 Integrated Inspection Report 05000454/2023004 and 05000455/2023004 ML24022A2722024-01-23023 January 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000454/2024011 ML24018A0362024-01-17017 January 2024 Paragon Energy Solutions, Defect with Detroit Diesel/Mtu Fuel Injectors P/N R5229660 Cat Id 0001390618 ML24004A0052024-01-17017 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0042 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 ML23349A1622023-12-17017 December 2023 Issuance of Amendment Nos. 298 and 294 Increase Completion Time in Technical Specification 3.8.1.B.4 (Emergency Circumstances) RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days ML23320A1762023-12-13013 December 2023 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0027 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23277A0032023-12-11011 December 2023 Issuance of Amendments Regarding Adoption of TSTF-370 ML23339A1762023-12-0505 December 2023 Notification of NRC Baseline Inspection and Request for Information (05000265/2024001) ML23318A5102023-12-0101 December 2023 Relief from the Requirements of the ASME Code IR 05000454/20233012023-11-27027 November 2023 NRC Initial License Examination Report 05000454/2023301 and 05000455/2023301 ML23319A3342023-11-20020 November 2023 Regulatory Audit in Support of License Amendment Requests to Adopt TSTF 505, Revision 2 and 10 CFR 50.69 RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation BYRON 2023-0065, Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline2023-11-17017 November 2023 Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline BYRON 2023-0063, Day Inservice Inspection Report for Interval 4, Period 3, (B2R24)2023-11-16016 November 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B2R24) IR 05000454/20230032023-11-13013 November 2023 Integrated Inspection Report 05000454/2023003 and 05000455/2023003 and Exercise of Enforcement Discretion RS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23313A0852023-11-0909 November 2023 Submittal of 2023-301 Byron Initial License Examination Post-Examination Comments IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML23297A2352023-10-26026 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 262023-10-20020 October 2023 Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 RS-23-100, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23278A0272023-10-0505 October 2023 Operator Licensing Examination Approval - Byron Station, October 2023 ML23251A1622023-09-29029 September 2023 Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-091, Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals2023-09-26026 September 2023 Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals ML23206A0382023-09-21021 September 2023 Proposed Alternative to the Requirements of the ASME Code IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 ML23226A0062023-09-19019 September 2023 Review of License Renewal Commitment Number 10 Submittal ML23180A1692023-09-11011 September 2023 Calvert Cliff Units 1 & 2, and R.E. Ginna Plant - Withdrawal of Proposed Alternatives to American Society of Mechanical Engineers (ASME) Requirements (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program ML23242A3282023-09-0101 September 2023 Amendment No. 233 Correction IR 05000454/20235012023-08-31031 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000454/2023501 and 05000455/2023501 IR 05000454/20230052023-08-30030 August 2023 Updated Inspection Plan for Byron Station (Report 05000454/2023005 and 05000455/2023005) RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs 2024-02-05 Category:Periodic Monitoring Report (Radiological/Environmental) MONTHYEARML23132A2032023-05-31031 May 2023
[Table view]Annual Radiological Environmental Operating Report for Cy 2022 SVP-23-022, Correction/Errata for the 2022 Annual Radioactive Effluent Release Report2023-05-12012 May 2023 Correction/Errata for the 2022 Annual Radioactive Effluent Release Report ML23132A2042023-05-12012 May 2023 Annual Radioactive Effluent Release Report BYRON 2022-0026, Annual Radiological Environmental Operating Report2022-05-0505 May 2022 Annual Radiological Environmental Operating Report SVP-21-028, Annual Radiological Environmental Operating Report2021-05-13013 May 2021 Annual Radiological Environmental Operating Report BYRON 2021-0032, 2020 Annual Radiological Environmental Operating Report (AREOR)2021-05-0606 May 2021 2020 Annual Radiological Environmental Operating Report (AREOR) BYRON 2021-0031, 2020 Annual Radioactive Effluent Release Report2021-04-21021 April 2021 2020 Annual Radioactive Effluent Release Report BYRON 2018-0100, Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report2018-10-18018 October 2018 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report SVP-18-035, Annual Radiological Environmental Operating Report2018-05-10010 May 2018 Annual Radiological Environmental Operating Report BYRON 2015-0032, Fowards 2014 Annual Radioactive Effluent Release Report2015-04-16016 April 2015 Fowards 2014 Annual Radioactive Effluent Release Report ML12136A4772012-05-11011 May 2012 Annual Radiological Environmental Operating Report (AREOR) ML1128602742011-10-13013 October 2011 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report for September 9, 2010 Through September 9, 2011 BYRON 2011-0071, Annual Radiological Environmental Operating Report (AREOR)2011-05-13013 May 2011 Annual Radiological Environmental Operating Report (AREOR) SVP-11-029, Radioactive Effluent Release Report for 20102011-04-27027 April 2011 Radioactive Effluent Release Report for 2010 SVP-02-024, Radioactive Effluent Report for January Through December 20012002-04-0505 April 2002 Radioactive Effluent Report for January Through December 2001 2023-05-31 |
Text
Church Road October 13, 2011 10 CFR 72.44 (d)(3)
LTR: BYRON 2011-143 File: 1.10.0101 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Director. Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission Washington, DC 20555-001 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-45~ and STN 50-455 and 72-53
Subject:
Byron Station Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report In accordance with 10 CFR 72.44 (d)(3) this letter provides the annual radioactive effluent release report for Byron Generating Station Independent Spent Fuel Storage Installation (ISFSI) for the period September 9, 2010 through September 9, 2011.
During this period there were no radioactive effluents released from the Byron Nuclear Station Independent Spent Fuel Storage Installation.
Should you have any questions concerning this letter, please contact Mr. David T.
Gudger, Regulatory Assurance Manager, at (815) 406-2800.
Respectfully, YJ. Tulon vice President BYron Generating Station cc: Regional Administrator - NRC Region III Senior NRC Resident Inspector - Byron Generating Station