ML112690241

From kanterella
Jump to navigation Jump to search
IR 05000003-11-008, on 08/30/11 - 09/01/11, Entergy Nuclear Operations, Inc., Buchanan, New York Site
ML112690241
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 09/26/2011
From: Laurie Kauffman
Decommissioning Branch I
To:
References
FOIA/PA-2016-0148 IR-11-008
Download: ML112690241 (10)


See also: IR 05000003/2011008

Text

Docket No.

License No.

Inspection No.

Licensee:

Facility:

Location:

Inspection Dates:

Inspector:

Approved By:


- -


U.S. NUCLEAR REGULATORY COMMISSION

REGION I

INSPECTION REPORT

05000003

DPR-5

05000003/2011008

Entergy Nuclear Operations, Inc.

Indian Point Energy Center (lPEC) Unit 1

450 Broadway

Buchanan, New York 10511-0249

August 30 - September 1, 2011

Laurie A. Kauffman

Health Physicist

Decommissioning Branch

Division of Nuclear Materials Safety

Judith A. Joustra, Chief

Decommissioning Branch

Division of Nuclear Materials Safety

Document Name: G:\\WordDocs\\Current\\lnsp Report\\RDPR-5.201100S.doc


EXECUTIVE SUMMARY

Indian Point Energy Center Unit 1

NRC Inspection Report No. 05000003/2011008

An announced routine safety inspection was conducted on August 30 - September 1, 2011, at Indian

Point Energy Center (IPEC) Unit 1 (Unit 1) by a Region I inspector. The NRC's program for

overseeing the safe operation of a shut-down nuclear power reactor is described in Inspection

Manual Chapter (IMC) 2561, Decommissioning Power Reactor Inspection Program. The inspection

included a review of the programs associated with Unit 1 while in long-term safe storage (SAFSTOR)

status. There are no ongoing decommissioning activities being conducted at Unit 1. Within the

scope of this inspection, no safety concerns or violations were identified. A brief summary of each

area inspected is described below.

Organization and Management Oversight

The licensee's organization and management oversight was adequate to support Unit 1 activities.

The roles and responsibilities for the Unit 1 activities were consistent with the IPEC Site Management

Manual, Control of Indian Point 1 and the Technical Specifications (TS).

Safety Reviews, Design Changes and Modifications

There were no plant modifications since the previous inspection conducted in June 2010.

Audit and Corrective Action Programs

The licensee maintained an adequate audit program and effectively utilized the established corrective

action program to identify, evaluate, and correct issues and problems. Condition reports were

appropriately prioritized and corrective actions were tracked in accordance with approved

procedures.

Decommissioning Performance and Status Reviews

No dismantlement or decommissioning activities were performed since the previous inspection.

Maintenance and Surveillance

The licensee effectively implemented the preventive maintenance and surveillance program and

associated procedures in accordance with TS and Offsite Dose Calculation Manual (ODCM)

requirements.

Occupational Radiation Exposure

The licensee provided adequate controls to limit exposures of workers to external sources of

radiation. Posting and labeling of radioactive materials and radiation areas were in compliance with

regulatory requirements. Radiological controls and dose estimates associated with Unit 1 activities

were effective to achieve dose goals. Implementation and oversight of the SAFSTOR program was

effective for the safe storage of radioactive material.

Effluent, Environmental Monitoring and Radioactive Waste and Transportation

The licensee effectively implemented and maintained the radioactive effluent controls program, the

groundwater monitoring program related to Unit 1, the radiological monitoring program, and the

radioactive waste management and transportation programs.

11

- -------------------------

REPORT DETAILS

1.0

Background

Unit 1 is a pressurized water reactor that has been permanently shut down since

October 31, 1974, and is being maintained in long-term storage (SAFSTOR). Units 1

and 2 are physically contiguous and share systems and facilities as well as a common

operating organization. The Technical Specifications (TS) for Unit 1 recognize this

commonality as well as the intended use of the Unit 1 facilities to support Indian Point

Unit 2. The systems associated with Unit 1 are divided into three classifications:

a) systems required per the Unit 1 TS that support the SAFSTOR condition of the unit;

b) systems required to support the operating units (e.g. Liquid Waste Processing); and

c) systems that are not required to support the TS, SAFSTOR condition, or the operating

units.

2.0

Organization and Management Oversight

a.

Inspection Scope (Inspection Procedure (IP) 36801)

The inspector reviewed procedure IP-SMM-OC-905, IPEC Site Management Manual,

Control of Indian Point 1, Revision 6 (IPEC-SMM), issued February 4, 2010, regarding

the roles and responsibilities for the operation, maintenance and control of Unit 1. The

inspector discussed organization, management and/or staffing changes as outlined in

TS, Sections 3.1 and 3.2, and in IPEC-SMM, Section 5.0. The inspector also interviewed

the personnel in the Employee Concerns Program (ECP).

b.

Observations and Findings

Procedure IP-SMM-OC-905 defines roles and assigns responsibility for the operation,

maintenance and control of Unit 1. There were no organizational structure changes

made by the licensee since the previous inspection. The inspector verified that

procedure IP-SMM-OC-905 and associated implementing procedures were consistent

with the TS. Implementation of the TS and the IPEC-SMM was adequate. ECP

personnel provided the inspector with details regarding the licensee commitment to

maintain a high level of awareness to safety.

c.

Conclusions

The licensee's organization and management oversight was adequate to support Unit 1

activities. The roles and responsibilities for the Unit 1 activities were consistent with the

IPEC-SMM and the TS. No safety concerns or violations were identified.

3.0

Safety Reviews, Design Changes, and Modifications

a.

Inspection Scope (lP 37801)

Procedure IP-SMM-OC-905, Rev. 6, provides guidance for modifying or working on

Unit 1 structures, systems and components (SSCs) that have been "retired in place" and

1

that remain in place to support the operation of Unit 2. The inspector discussed

Engineering Change (EC) reports to determine if the licensee conducted safety reviews

and engineering design change screening in accordance with the requirements of

10 CFR 50.59.

b.

Observations and Findings

There were no plant modifications since the previous inspection conducted in June 2010.

c.

Conclusions

No safety concerns or violations were identified.

4.0

Audit and Corrective Action Program

a.

Inspection Scope OP 40801)

The inspector reviewed the quality assurance (QA) audit report QA-12/18-2011-IP-1,

OperationsiTechnical Specifications, dated June 6-27,2011 related to Unit 1 SAFSTOR

activities. The inspector also reviewed selected condition reports (CRs) and any

associated corrective actions to evaluate the licensee's ability to assess, identify, resolve,

and prevent issues that could impact safety or the quality of SAFSTOR activities.

b.

Observations and Findings

The purpose of the audit was to evaluate the effectiveness of Operations, compliance

with TS requirements and to evaluate selected elements of the Master Audit Plan for

Operations and TS. The audit contained 10 scope elements including: Test Control;

Inspection, Test and Operating Status; Limiting Conditions for Operations; Conduct of

Operations; Operator Knowledge and Performance; Work Coordination and Control;

Corrective Action; Self Assessment and Benchmarking; Instruction, Drawings and

Procedures; and Leadership and Management. The audit was adequate and identified

strengths and weaknesses related to the Unit 1 activities.

The priority for addressing CRs and implementation of corrective actions were

appropriate based upon safety significance. Corrective actions were implemented to

address identified issues, and were being tracked to closure using the licensee's

corrective action program. The licensee did not identify any adverse trends or safety

concerns.

c.

Conclusions

The licensee maintained an adequate audit program and effectively utilized the

established corrective action program to identify, evaluate, and correct issues and

problems. CRs were appropriately prioritized and corrective actions were tracked in

accordance with approved procedures. No safety concerns or violations were identified.

2

5.0

Decommissioning Performance and Status Reviews

a.

Inspection Scope (IP 71801)

The inspector reviewed the licensee's current decommissioning status with respect to the

Decommissioning Plan for Indian Point Unit 1, approved by the NRC in an Order dated

January 31, 1996.

b.

Observations and Findings

Unit 1 is currently in the SAFSTOR condition. The licensee informed the inspector that

they plan to actively decommission Unit 1 in parallel with the decommissioning of Unit 2

after that unit has been permanently shutdown.

c.

Conclusions

No dismantlement or decommissioning activities were performed since the previous

inspection, conducted in June 2010. No safety concerns or violations were identified.

6.0

Maintenance and Surveillance

a.

Inspection Scope (lP 62801)

The inspector evaluated the maintenance program, required by TS, Section 5.0 and

described in the IPEC SSM, Section 6.0. The inspector reviewed the surveillance

requirements for the Unit 1 radioactive effluent monitoring instrumentation, required by

TS, Section 5.2 and the ODCM. The inspector examined the shift logs and the

maintenance and calibration records for the liquid discharge monitor (R-54) and the stack

vent noble gas monitor (R-60) for the period July 2010 through August 2011. The

inspector conducted a plant tour, including the nuclear service building (NSB), the

chemical systems building (CSB), the fuel handling building (FHB), the containment

building, and containment sphere [Le. vapor containment (VC)]. The inspector also

discussed the biennial SAFSTOR engineering and structural assessment inspection with

the licensee.

b.

Observations and Findings

The inspector verified that the maintenance and surveillance program for selected

systems and components had been conducted in accordance with TS, implementing

procedures, and the ODCM. The inspector determined from a review of maintenance

and calibration records that the preventative maintenance, routine surveillance, and

calibration results were complete and the results were within acceptable limits. The

inspector also determined that the radioactive effluent monitoring instrumentation were

calibrated and that the set points were appropriate.

The biennial SAFSTOR engineering and structural assessment inspection will be

conducted in November 2011. The inspector will review the engineering and structural

assessment report during the next inspection.

3

c.

Conclusions

The licensee effectively implemented the preventive maintenance and surveillance

program and associated procedures in accordance with TS and ODCM requirements.

No safety concerns or violations were identified.

7.0

Occupational Radiation Exposure

a.

Inspection Scope (lP 83750)

The inspector evaluated the licensee's implementation of the occupational radiation

exposure program to determine the licensee's capability to monitor and control radiation

exposure to employees, and to determine the adequacy of the radiation protection

program. The inspector reviewed procedure EN-RO-1 01, Nuclear Management Manual,

Access Control for Radiologically Control/ed Areas, Rev. 6, issued June 23, 2011,

RP-STD-17, Satellite RP Key Issuance and HRA, LHRA, and VHRA Boundary

Verification, Rev. 10, issued May 17, 2010, and EN-RP-108, Radiation Protection

Posting, Rev. 10, issued August 4, 2011. The inspector interviewed responsible

individuals, reviewed radiological survey plans, survey maps of the radiologically

controlled area, and conducted field observations of radiological postings. The inspector

evaluated the radiation work permits (RWP) related to Unit 1, and the dose totals for

2010 and January 2011 through August 2011.

b.

Observations and Findings

The radiologically controlled areas were appropriately posted for radioactive material.

Radiological postings were readily visible, well-maintained, and reflected radiological

conditions. The radiological survey maps and related information maintained at the

Unit 1 access point were current. High radiation areas and technical specification locked

high radiation areas were properly posted and locked as required. The RWPs were

commensurate with the radiological significance of the tasks and included the

appropriate exposure control measures for the safe implementation of the activities. The

RWP dose totals were below the dose goal totals for 2010 and January 2011 through

August 2011.

c.

Conclusions

The licensee provided adequate controls to limit exposures of workers to external

sources of radiation. Posting of radioactive materials and radiation areas were in

compliance with regulatory requirements. Radiological controls and dose estimates

associated with Unit 1 activities were effective to achieve dose goals. Implementation

and oversight of the SAFSTOR program were effective for the safe storage of radioactive

material. No safety concerns or violations were identified.

4

8.0

Effluent and Environmental Monitoring Programs

a.

Inspection Scope (lP 84750)

The inspector evaluated the radioactive effluent control and the site radiological

environmental monitoring programs. The evaluation included a review of the annual

radioactive effluent release report for 2010, the annual radiological environmental

operating report for 2010, and the associated analytical results for each program. The

inspection also included a review of the Unit 1 TS and the ODCM. The inspector

reviewed the associated radioactive liquid release permits, the analytical sample results,

and the projected doses to the public associated with the groundwater in-leakage into the

North Curtain Drain (NCD) and Sphere Foundation Drain (SFD) sumps. The inspector

also reviewed the gaseous effluent results, the projected doses to the public associated

with the stack vent, and the radiological environmental monitoring program, including the

analytical results associated with samples of shoreline sediment, fish, and water from

January 2011 through August 2011.

b.

Observations and Findings

The annual effluent and environmental monitoring reports demonstrated that the

calculated doses were well below regulatory dose criteria of 10 CFR 50, Appendix I. The

radioactive liquid effluent release permits were completed in accordance with the ODCM.

From a review of the analytical data, the inspector verified that the projected doses to the

public from the liquid and gaseous effluent from Unit 1 were below TS limits and were

performed in accordance with the ODCM and the Code of Federal Regulations

(10 CFR 50.36a) for maintaining doses to the public from radioactive effluents as low as

is reasonably achievable. The inspector verified that the licensee collected and analyzed

the stack vent samples, NCD and SFD sump samples, and the liquid discharge monitor

samples within the required frequencies and that the sample collection was conducted in

accordance with applicable procedures.

The inspector compared the analytical water sample results related to the groundwater

monitoring program, specifically the NCD and SFD analytical sample results from

January 2011 through August 2011 to the results from 2010. The levels of tritium ranged

from 13500 picoCuries per Liter (pCi/L) to 3 pCi/L for the NCD and from 642 pCi/L to

480 pCi/L for the SFD. The licensee informed the inspector that the levels of radioactivity

appear to be trending downward. The inspector's review of this data confirmed the

licensee's conclusion.

The inspector reviewed the analytical results for shoreline sediment, fish, and water from

January 2011 through August 2011 for the radiological environmental monitoring

program and noted that the results indicated that no significant radioactivity was

identified in fish and the environment.

c.

Conclusions

The licensee effectively implemented and maintained the radioactive effluent controls

program, the groundwater monitoring program, and the radiological monitoring program.

No safety concerns or violations were identified.

5

-- ---

-

9.0

Radioactive Waste Management and Transportation of Radioactive Materials

a.

Inspection Scope (IP 86750)

The inspector evaluated and discussed the radioactive waste management and

transportation programs to determine whether the licensee properly processed,

packaged, stored, and shipped radioactive materials. The inspector also conducted a

tour of the Unit 1 FHB.

b.

Observations and Findings

The inspector noted that there were no radioactive waste shipments since the previous

inspection conducted in June 2010.

Additionally, the inspector determined from the Unit 1 FHB tour and discussions with

individuals cognizant of the radioactive waste management and radioactive materials

transportation programs that the Class B waste from the cleanup of the spent fuel pool is

still being maintained in the Unit 1 FHB until an appropriate disposal option is available.

c.

Conclusions

The licensee effectively implemented the radioactive waste management and

transportation programs. No safety concerns or violations were identified.

Exit Meeting Summary

On September 1, 2011, the inspector presented the inspection results to Donald Mayer,

Director, Unit 1, and other members of the licensee's staff. The inspector confirmed that

proprietary information was not provided or examined during the inspection.

6

A-1

SUPPLEMENTAL INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

Licensee

C. English, Superintendant, Unit 1

J. Doroski, Health Physics and Chemistry Specialist

W. Henries, Senior Engineer Consultant, Unit 1

F. Inzirillo, Quality Assurance Manager

D. Mayer, Director, Unit 1

J. Michetti, System Engineering Support - RMS

S. Sandike, Senior Chemistry Engineer

W. Scholtens, Radioactive Waste Engineer

D. Smith, Health Physicist, Radiation Protection

G. Dahl, Licensing Engineer

B. Taggart, Employee Concerns Program

R. Tagliamante, Radiation Protection Manager

INSPECTION PROCEDURES USED

36801

Organization, Management, and Cost Controls at Permanently Shutdown

Reactors (PSRs)

37801

40801

62801

71801

83750

84750

86750

Safety Reviews, Design Changes, and Modifications at PSRs

Self Assessment, Auditing, and Corrective Action at PSRs

Maintenance and Surveillance at PSRs

Decommissioning Performance and Status Reviews at PSRs

Occupational Radiation Exposure

Radioactive Waste Treatment, and Effluent and Environmental Monitoring

Solid Radioactive Waste Management and Transportation of Radioactive

Materials

Attachment

A-2

ITEMS OPEN, CLOSED, AND DISCUSSED

Opened, Closed and Discussed - None

ADAMS

CFR

CR

CSB

EC

ECP

FHB

IMC

IP

IPEC

IPEC-SMM

NCD

NRC

NSB

ODCM

PSRs

QA

RMS

RWP

SAFSTOR

SFD

SSCs

TS

Unit 1

Unit2

VC

LIST OF ACRONYMS USED

Agencywide Documents Access and Management Systems

Code of Federal Regulations

condition reports

chemical systems building

Engineering Change

Employee Concerns Program

fuel handling building

Inspection Manual Chapter

Inspection Procedure

Indian Point Energy Center

IPEC Site Management Manual, Control of Indian Point 1

North Curtain Drain

Nuclear Regulatory Commission

nuclear service building

Offsite Dose Calculation Manual

Permanently Shutdown Reactors

quality assurance

radiation monitoring system

radiation work permits

long-term safe storage

Sphere Foundation Drain

structures, systems and components

technical specification

Indian Point Unit 1

Indian Point Unit 2

vapor containment (containment sphere)

Attachment