E-mail from B. Pham, NRR, to S. Sakai, NRR Et Al, on Salem & Hc Environmental Review
ML11263A019
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 09/02/2010
From: Bo Pham
Division of License Renewal
To: Sakai S
Division of License Renewal
References
FOIA/PA-2011-0113
Download: ML11263A019 (2)


Text

7) ~

12-'

Perkins, Leslie From: Pham, Bo Sent: Thursday, September 02, 2010 6:00 PM To: Sakai, Stacie Cc: Perkins, Leslie; Brady, Bennett

Subject:

FW: Salem & HC environmental review Stacie, please submit the following EDO note:

0 The schedule for issuing the Draft Supplemental Environmental Impact Statement (SEIS) for the Salem, Units 1 and 2 and Hope Creek license renewal environmental review has been delayed due to staff requiring additional time to complete its review. The DSEIS is expected to be published by the end of October 2010. The staff issued a formal schedule change letter on September 2, 2010.

Bo Pham Chief, Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-8450 From: Sakai, Stacie Sent: Thursday, September 02, 2010 5:54 PM To: Pham, Bo

Subject:

RE: Salem & HC environmental review We have done EDO notes for schedule extensions for PINGP and IP. We may want to consider doing one for this. If so, here's the issued EDO notes:

The schedule for issuing the Final Supplemental Environmental Impact Statement (SEIS) for Indian Point Units 2 and 3 license renewal has been delayed. The staff fiad intended to issue the Final SEIS on August 31, 2010, but now intends to issue the Final SEIS on or before November 19, 2010, to allow time to consider the large number of public comments the staff has received from members of the public. The staff issued a formal schedule change letter on August 31, 2010.

The schedule for issuing the Final Supplemental Environmental Impact Statement (SEIS) for the Prairie Island Generating Nuclear Plant, Units 1 and 2 has been delayed one month. The delay is due to staff identifying additional information needed from the applicant to complete their review. The FSEIS is expected to be published by the end of October 2010.

The staff issued a formal schedule change letter on September 1, 2010.

From: Pham, Bo Sent: Thursday, September 02, 2010 5:47 PM To: Perkins, Leslie; Eccleston, Charles; Brady, Bennett Cc: Sakai, Stacie

Subject:

Salem & HC environmental review

All, 1

I just signed a letter out to Salem & HC to extend their environmental review schedule as indicated below. All the major milestones, including DSEIS issuance, DSEIS meeting, and FSEIS issuance will be impacted. I've also just spoke to Nancy Ranek to inform her of the change.

From here on, I'd like to have Charles focus on finishing and issuing the FSEIS for Duane Arnold. Leslie will take over putting & issuing the DSEIS for Salem & HC until Charles is free from DAEC. Leslie, please make sure the schedule for the interface meeting handouts and public webpage are updated with this info. Thanks.

Milestones Schedule Draft Supplemental Environmental Impact Statement (SEIS) - Issued 10/22/2010 EPA FRN Published - Availability / Comment on Draft SEIS 10/29/2010 Public Meeting - Draft SEIS 11/17/2010 End of Draft SEIS Comment Period 12/17/2010 Final SEIS - Issued 03/25/2011 EPA FRN Published - Availability of Final SEIS 04/01/2011 Decision Director NRR - Approval 06/14/2011 Commission Decision (if hearing is granted) 02/03/2012 Bo Pham Chief, Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-8450 2