MONTHYEARML24022A0972024-01-22022 January 2024 Massachusetts Institute of Technology Change of Facility Backup Project Manager ML23354A1442024-01-0505 January 2024 Examination Confirmation Letter No. 50-020/OL-24-01, Massachusetts Institute of Technology IR 05000020/20232032023-11-21021 November 2023 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2023203 ML23242A3382023-11-0606 November 2023 Examination Report Letter No. 50-020/OL-23-01, Massachusetts Institute of Technology ML23242A3392023-11-0606 November 2023 Examination Result Letter No. 50-020/OL-23-01, Massachusetts Institute of Technology IR 05000020/20232012023-10-12012 October 2023 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2023201 IR 05000020/20232022023-09-27027 September 2023 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Security Inspection Report No. 05000020/2023202 ML23194A0412023-07-11011 July 2023 Mit Research Reactor - Duties of Reactor Superintendent ML23103A2632023-05-10010 May 2023 Examination Confirmation Letter No. 50-020/OL-23-01 Massachusetts Institute of Technology ML23094A1102023-03-30030 March 2023 Massachusetts Institute of Technology (Mit), Submittal of Annual Report for 2022, Technical Specification 7.7.1 ML23072A0242023-03-0707 March 2023 Mit, Nuclear Reactor Lab., Proposal for Conversion to Low Enriched Uranium (Leu), Mit Research Reactor IR 05000020/20222012023-02-0707 February 2023 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2022201 ML22189A0492022-07-25025 July 2022 Examination Confirmation Letter No.50-020/OL-22-02, Massachusetts Institute of Technology ML22095A2412022-03-31031 March 2022 Annual Report for the Mit Research Reactor for the Period from January 1, 2021, to December 31, 2021 ML22062B0422022-02-10010 February 2022 Proposal for Conversion to Low Enriched Uranium (Leu), Mit Research Reactor, Docket No. 50-20, 10 CFR 50.64 (c)(2)(ii) of That Paragraph ML21328A2342021-11-29029 November 2021 Examination Confirmation Letter No. 50-020/OL-22-01, Massachusetts Institute of Technology IR 05000020/20212032021-11-0909 November 2021 Massachusetts Institutes of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2021203 IR 05000020/20212012021-09-30030 September 2021 Massachusetts Institute of Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report 05000020/2021201 ML21186A0032021-07-16016 July 2021 Examination Confirmation Letter No. 50-020/OL-21-02, Massachusetts Institute of Technology ML21165A1542021-05-28028 May 2021 Mit - Emergency Plan and Procedures, 10 CFR 50.54(q)(5) ML21140A3622021-05-17017 May 2021 Massachusetts Institute of Technology (Mit) - Supplement to Response to the Request for Additional Information for Battery Upgrade License Amendment Request (EPID: L-2021 -NFA-0000) ML21132A2512021-05-0606 May 2021 Massachusetts Institute of Technology, License No. R-37, Docket No. 50-20, Reportable Occurrence 50-20/2021-: Operation with Less than the Required Staffing on Site; NRC OPS Center Log EN 55212 ML21112A1672021-04-12012 April 2021 Massachusetts Institute of Technology - Physical Security Plan Revision Regarding Biometric Readers ML21105A3602021-04-0707 April 2021 Duties of Reactor Superintendent ML21099A1132021-03-31031 March 2021 Massachusetts Institute of Technology - Annual Report, Docket No. 50-20, License R-37, Technical Specification 7.7.1 ML21091A2082021-03-24024 March 2021 Mit Nuclear Reactor Lab - Response to Request for Additional Information for Battery Upgrade License Amendment Request ML21076A0232021-03-18018 March 2021 Requests for Additional Information - Related to License Amendment Request to Replace Emergency Power System Batteries ML21070A1852021-03-0202 March 2021 Mit Nuclear Reactor Laboratory, License Amendment Request Regarding Emergency Battery Surveillances in Technical Specification 4.6, Docket No. 50-20, License R-37 ML21063A2552021-02-25025 February 2021 Proposal for Conversion to Low Enriched Uranium (Leu), :Mit Research Reactor, Docket No. 50-20, 10 CFR 50.64 (c)(2)(ii) of That Paragraph ML21053A4372021-02-23023 February 2021 Examination Confirmation Letter No. 50-020/OL-21-01, Massachusetts Institute of Technology ML21036A0852021-02-19019 February 2021 Massachusetts Institute of Technology - Acceptance of License Amendment Request to Revise Surveillance Frequency During Extended Reactor Shutdown ML21035A2582021-01-29029 January 2021 Massachusetts Institute of Technology (Mit), Supplement to Technical Specifications Surveillance Frequency Definition Update for Improved Compliance Under 10 CPR 50.36(c)(3) ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20307A4202020-11-0505 November 2020 Granting of Extension Request to Supplement License Amendment to Revise Surveillance Requirement Frequency ML20304A1172020-10-19019 October 2020 Time Extension Request for LAR on Technical Specifications Surveillance Frequency Update for Improved Compliance Under 10 CFR 50.36(c)(3) for the Mit Research Reactor ML20248H5682020-09-22022 September 2020 Mit Research Reactor Routine Inspection Report with Enforcement Discretion (EA-20-109) - August 2020 ML20161A3342020-07-24024 July 2020 Massachusetts Institute of Technology - Issuance of Amendment NO.44 to Renewed Facility Operation License No. R-37 to Amend Technical Specifications Related to Level 1 Position Title Change ML20182A7092020-07-0909 July 2020 Acceptance Review Amendment Request to Revise Surveillance Frequency - Opportunity to Supplement ML20192A0762020-06-30030 June 2020 Mit - Supplemental Information for License Amendment Request for Position Title Change in Technical Specifications for Level 1 Staff ML20070H2672020-06-0404 June 2020 Examination Report No. 50-020/OL-20-01, Massachusetts Institute of Technology ML20119A8272020-05-29029 May 2020 Massachusetts Institute of Technology - Issuance of Amendment No. 43 Extending Time to Implement License Amendment No. 42 to Facility Operating License No. R-37 ML20149K4142020-05-27027 May 2020 NRC LAR Extension Supplemental Letter 2020-05-27 ML20135H1882020-05-15015 May 2020 Massachusetts Institute of Technology - Exemption from Select Requirements of 10 CFR Part 55, Operators' Licenses ML20122A0622020-04-21021 April 2020 Massachusetts Institute of Technology, Regarding the, Amendment No. 42 to Renewed Facility Operating License No. R-37 for the Nuclear Safety System Digital Upgrade (Epdi No. L-2016-LLA-0003) ML20090E2272020-04-16016 April 2020 Massachusetts Institute of Technology - Acceptance of the Application for a License Amendment Level 1 Position Title Change ML20097B6932020-03-31031 March 2020 Amendment No. 42 to Renewed Facility Operating License No. R-37 Regarding the Nuclear Safety System Digital Upgrade (Epdi No. L-2016-LLA-0003) ML20097D2992020-03-27027 March 2020 Massachusetts Institute of Technology (Mit) - Annual Report for the Year 2019 ML20078J4852020-03-12012 March 2020 Massachusetts Institute of Technology (Mit), License Amendment Request for Position Title Change in Technical Specifications for Level 1 Staff ML20055D3322020-02-18018 February 2020 Proposal for Conversion to Low Enriched Uranium (Leu), Mit Research Reactor, Docket No. 50-20, 10 CFR 50.64 (c)(2)(ii) of That Paragraph IR 05000020/20192032020-01-15015 January 2020 Massachusetts Institute of Technology U.S. Nuclear Regulatory Commission Security-Related Inspection Report 05000020/2019203 2024-01-05
[Table view] Category:Licensee 30-Day Written Event Report
MONTHYEARML18036A1872018-01-30030 January 2018 Massachusetts Institute of Technology: Reportable Occurrence 50-20/2018-2: Operation with Fewer than the Required Number of Full Power Nuclear Safety System Level Channel Scrams; NRC OPS Center Log #En 53174 ML18026A6262018-01-23023 January 2018 Reportable Occurrence 50-20/2018-1: Operation with Fewer than the Required Number of <100 Kw Nuclear Safety System Level Channel Set to Alarm; NRC OPS Center Log # EN 52157 ML17026A3732017-01-24024 January 2017 Massachusetts Institute of Technology; License No. R-37; Docket No. 50-20; Reportable Occurrence 50-20/2017-1: Operation with Fewer than the Required Number of Nuclear Safety Channel Period Scrams; NRC OPS Center Log# EN 52497 ML11258A0452011-09-0707 September 2011 Massachusetts Institute of Technology - Reportable Occurrence 50-20/2011-4: Work Involving Reactivity with Possibly Fewer than the Required Number of Nuclear Safety Channel Period Alarms; NRC OPS Center Log #47-229 ML0517504082005-06-16016 June 2005 Reportable Occurrence 50-20/2005-1, Missed Daily Secondary Coolant Sample 2018-01-30
[Table view] |
Text
MIT NUCLEAR REACTOR LABORATORY AN MIT INTERDEPARTMENTAL CENTER Thomas H. Newton, Jr. Mail Stop: NW12-116a Phone: 617 253-4211 Director of Reactor Operations 138 Albany Street Fax: 617 253-7300 Cambridge, MA 02139 Email: tnewton@mit.edu 7 September, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re: Massachusetts Institute of Technology; License No. R-37; Docket No. 50-20; Reportable Occurrence 50-20/2011-4: Work Involving Reactivity with Possibly Fewer than the Required Number of Nuclear Safety Channel Period Alarms; NRC OPS Center Log #47-229
Dear Sir or Madam:
The Massachusetts institute of Technology hereby submits a report of an occurrence at the MIT Research Reactor (MITR) in accordance with paragraph 7.7.2 of the Technical Specifications. An initial report was made by telephone to the U.S.
Nuclear Regulatory Commission Headquarters Operations Center on 1 September 2011.
The format and content of this report are based on Regulatory Guide 1.16, Revision 1.
- 1. Report No. 50-20/2011-4; Ops Center No.47-071 2a. Report Date: 7 September 2011 2b. Date of Occurrence: 12 August 2011
- 3. Facility: MIT Nuclear Reactor Laboratory
- 4. Identification of Occurrence:
An in-core experiment was inserted and work was conducted on a single control blade at the MIT Research Reactor on 12 August 2011, with possibly only one operable nuclear safety channel period alarm. Technical Specification No. 3.2.3-2 requires that there be at least two such operable channels prior to work involving reactivity being performed in core.
- 5. Condition Prior to Occurrence:
The <100 kW startup checklist had been completed in preparation for replacement of a drive for control blade #5. In order to facilitate access to this drive, the in-core 4c~f
Nuclear Regulatory Commission Reportable Occurrence 50-20/2011-4 7 September 2011 Page 2 of 3 sample assembly (ICSA) was removed from the core on Thursday 11 August at 1141. At about 2100 on 11 August, as part of a check of the functionality of the electromagnet for the control blade undergoing maintenance, the Assistant Superintendent observed that all six safety channels were properly connected. (Note: Channel #1-3 are the period safety channels which are each connected to a Keithley picoammeter. Channel 3, an ion chamber, is not considered to be operable at this low range.)
On Friday 12 August, the drive was replaced, the ISCA tube was reinserted in core, and routine blade drop time measurements were made on control blade #5.
- 6. Description of Occurrence:
After completion of the drive work and testing on 12 August, the operator proceeded to perform the full power startup checklists in preparation for operating the reactor at full power. As part of this test, all three period channels were checked and it was observed that although Channel 1 showed a period response on the Keithley amplifier, there was no corresponding period on the safety channel or a resulting scram.
Subsequent investigation showed that the cable normally connecting Channel 1 Keithley to the scram circuit was disconnected from the back of the Channel 1 safety amplifier.
- 7. Description of Apparent Cause of Occurrence The control room had been continuously attended by licensed personnel for the entire time in question. All licensed operators and supervisors have stated that there was no work being done on any of the safety channels between 2100 Thursday 11 August, and -2115 on Friday 12 August, when the disconnection was discovered. Thus, it is surmised that the BNC cable connection was not properly latched in place and eventually vibrated loose some time on 12 August.
- 8. Analysis of Occurrence:
As noted above, although Channel No. 1 Keithley was continuously indicating the reactor period, it was not capable of alarming at its setpoint of 10 seconds as of the time it became disconnected. Safety Channel No. 2 was observed to be operating properly at all times and would have caused an alarm if the period had exceeded the setpoint of 10 seconds. In addition, the D20 reflector was dumped as a normal part of the procedure thereby adding approximately negative 10.2 beta of additional reactivity. Thus, the reactor was far subcritical at all times and none of the activities concerned could have even brought KIff up to 0.9.
In addition to the uncertainty in the time at which Channel No. 1 became disconnected, there is also considerable uncertainty as to whether the maintenance
Nuclear Regulatory Commission Reportable Occurrence 50-20/2011-4 7 September 2011 Page 3 of 3 activities in question fall into the technical specification category of "work involving reactivity performed in core." It was this debate that delayed classification of this event as reportable. Modification of the wording of the technical specification is under consideration.
- 9. Corrective Action:
The immediate corrective action consisted of replacing the connection and retesting the period trip.
The long-range corrective action consists of initiating a log sheet for changing the state of all connections in the back of the control panel, with verification and checking by a second licensed person prior to declaring a channel operational. This log sheet also has a section to ensure information is recorded on the Reactor Bypass Log. The Reactor Bypass Log is reviewed by the Instrumentation Supervisor, Shift Supervisor, and Superintendent. (Action completed, 2 September 2011.)
- 10. Failure Data A related occurrence took place in July 2011. Refer to ROR 50-20-2011-3 dated 28 July 2011.
Sincerely, John P. Foster homas H. Newton, Jr., Ph.D, PE Superintendent Director of Reactor Operations MIT Research Reactor MIT Research Reactor cc: MITRSC USNRC - Senior Project Manager Research and Test Reactors Division of Policy and Rulemaking Office of Nuclear Reactor Regulation USNRC - Senior Reactor Inspector Research and Test Reactors Division of Policy and Rulemaking Office of Nuclear Reactor Regulation