ML11235A655
| ML11235A655 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 06/21/2011 |
| From: | Ferrer N Office of Nuclear Reactor Regulation |
| To: | Leslie Perkins Office of Nuclear Reactor Regulation |
| References | |
| FOIA/PA-2011-0288 | |
| Download: ML11235A655 (2) | |
Text
Ferrer, Nathaniel From:
Ferrer, Nathaniel 1 W L-Sent:
Tuesday, June 21, 2011 2:42 PM To:
Perkins, Leslie
Subject:
FW: Re: Question on resources on Diablo review
- Leslie, Here's my input for the safety review:
- 1. 1555.5 total hours expended Jan through May
- 2. Hours in May were expended for final processing of the SER as well as for planning related to the delay in schedule Once you add in your input, we can run it by Bo/Dave.
Nate From: Pham, Bo Sent: Monday, June 20, 2011 3:19 PM To: Ferrer, Nathaniel; Perkins, Leslie Cc: Wrona, David; Weil, Jenny
Subject:
FW: Re: Question on resources on Diablo review Nate & Leslie, OCA's been fielding questions regarding how/what resources are being spent on the Diablo review since PG&E's request to delay the schedule (read: why is the staff still expending ANY resources on this review).
Can you provide Jenny Weil of OCA the following information, so that she can convey or clarify to the congressional staffers the situation with our resource expenditures?
- 1. Total number of staff review hours (aggregate) from Jan-May (broken up between Safety &
Environmental); there should be an evident drop in hours.
- 2. For the hours expended in May, particularly for the environmental review, can you provide a summary of where the efforts are being expended (e.g., hydrology, SAMA, etc.)?
Please also work with Jenny directly to make sure it's the right level of information. Thanks.
Bo Pham Chief, Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-8450 From: Weil, Jenny k..
Sent: Monday, June '20, 2011 2:00 PM To: Pham, Bo
Subject:
FW: Re: Question on resources on Diablo review Hi Bo,
Mike said you may be the one to track this information. The request was for the ongoing resources for the Diablo renewal review.
- Thanks, Jenny From: Markley, Michael.
Sent: Monday, June 20, 2011 8:28 AM To: Weil, Jenny; Wang, Alan; Miller, Geoffrey Cc: Pham, Bo
Subject:
RE: Re: Question on resources on Diablo review
- Jenny, Bo Pham in NRR/DLR is the person to ask about license renewal activities and resources.
Mike From: Weil, Jenny Sent: Friday, June 17, 2011 4:56 PM To: Wang, Alan; Miller, Geoffrey; Markley, Michael
Subject:
Re: Question on resources on Diablo review Hope the meeting went well on Wednesday. I saw in the news clips that there were Fukushima-related questions/concerns.
Rep. Capps' staffer asked me if we could provide in writing the resources being spent on the Diablo relicensing review (dollars and/or staff resources). Her office is getting calls from constituents who don't understand why the review wouldn't be suspended immediately since the 3-D studies won't be completed until 2015. Maybe it would be beneficial to have an explanation of any work that is ongoing?
- Thanks, Jenny 2