Supplemental Information Regarding Extending Completion Times for Technical Specification 3.8.1 Dated January 19, 2011
ML11234A177
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 08/19/2011
From: Krich R
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
TAC ME5036, TAC ME5037, TAC ME5038
Download: ML11234A177 (2)


Text

Tennessee Valley Authority 1101 Market Street, LP 3R Chattanooga, Tennessee 37402-2801 R. M. Krich Vice President Nuclear Licensing August 19, 2011 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296

Subject:

Supplemental Information Regarding Extending Completion Times for Technical Specification 3.8.1 (TAC Nos. ME5036, ME5037, and ME5038), dated January 19, 2011

Reference:

TVA Letter to NRC, "Revised Technical Specifications Change TS-468, Request to Extend Completion Time for TS 3.8.1 Required Action B.4 -

Emergency Diesel Generators A, B, C, D, 3A, 3B, 3C, and 3D," dated November 12, 2010 In the referenced License Amendment Request (LAR), the Tennessee Valley Authority (TVA) noted that the requested 14-day completion time will provide operational and maintenance flexibility, primarily through allowing adequate time for planned on-line preventive maintenance and reliability improvement activities on the Emergency Diesel Generators (EDGs). TVA also stated that the proposed changes would allow more time for unanticipated EDG repairs resulting from major unexpected failures.

The use of the 14-day completion time in the proposed Technical Specifications changes was dependent on availability of temporary diesel generators. However, during the NRC review process TVA revised or added various commitments (through responses to Requests for Additional Information) regarding availability of the temporary diesel generators before and during the proposed 14-day completion time.

As a result, use of the 14-day completion time for unanticipated EDG repairs is not consistent with these commitments. Therefore, TVA intends to use the 14-day completion time only for planned maintenance activities.

printed on recycled paper

U.S. Nuclear Regulatory Commission Page 2 August 19, 2011 This letter includes no new regulatory commitments. Please direct any questions concerning this matter to Tom Matthews at (423) 751-2687.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on the 19th day of August 2011.

Respectfully, R. M. Krich cc: