MONTHYEARML24267A2552024-09-23023 September 2024 Change in the NRC Project Manager for the West Valley Demonstration Project IR 05000201/20240012024-05-0808 May 2024 West Valley Demonstration Project - Nuclear Regulatory Commission Monitoring Visit Report 05000201/2024001 ML23229A4712023-08-17017 August 2023 Change in the NRC Project Manager for the West Valley Demonstration Project IR 05000201/20230012023-03-28028 March 2023 West Valley Demonstration Project - U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2023001 ML23038A0402023-03-15015 March 2023 New York State Energy Research and Development Authority Results of a Teleconference to Discuss Disposition of Historical Records Related to the Former Nuclear Fuel Services, Inc ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000201/20220032022-12-0606 December 2022 West Valley Demonstration Project - U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2022003 IR 05000201/20220022022-09-28028 September 2022 West Valley Demonstration Project - U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2022002 IR 05000201/20210012022-08-10010 August 2022 West Valley Demonstration Project: U.S. Nuclear Regulatory Commission Monitoring Visit Report Nos. 05000201/2021001 and 05000201/2022001 ML22180A1892022-06-21021 June 2022 Notification of Temporary Change in Radiation Safety Officer Position for New York State Energy Research and Development Authoritys Radiation Protection Program for the Retained Premises of the Western New York Nuclear Service Center ML22145A2972022-05-0202 May 2022 Letter from J. Dean to M. Pagels, Et Al., West Valley Supplemental Environmental Impact Statement Final Scope Dated 5/2/2022 ML21349B3442021-12-17017 December 2021 U.S. Department of Energy West Valley Demonstration Project - Demolition Readiness of the Main Plant Process Building Decommission and Demolition Plan (Docket No. 50-201 (POOM-032) ML21245A2462021-11-0505 November 2021 NYSERDA Retained Premises Radiation Protection Plan Amendment Package ML21202A2122021-07-15015 July 2021 Response to NRC Letter: Request for Additional Information Regarding the License Amendment to Incorporate Updated Retained Premises Radiation Protection Requirements (EPID L-2020-LLA-0029), Dated June 3, 20 ML21118A0762021-06-0303 June 2021 NYSERDA - Request for Additional Information Regarding the License Amendment to Incorporate Updated Retained Premises Radiation Protection Requirements ML21126A0232021-04-27027 April 2021 Us Dept. of Energy, West Valley Demonstration Project, Air Dispersion Modeling Performed in Support of West Valley Demonstration Project (WVDP) Main Plant Process Building (MPPB) Demolition Preparations ML21105A3522021-04-0505 April 2021 Notification of Change in Radiation Safety Officer for the New York State Energy Research and Development Authoritys Radiation Protection Program for the Retained Premises of the Western New York Nuclear Service Center ML21012A3072020-12-15015 December 2020 Responses to NRC Comments on the West Valley Demonstration Project Main Plant Process Building Decommissioning & Demolition Work Plan, Revision 4 ML21012A2992020-12-14014 December 2020 West Valley Supplemental Environmental Impact Statement Schedule and Probabilistic Performance Assessment Technical Discussions IR 05000201/20200022020-11-0202 November 2020 U. S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2020002, West Valley Demonstration Project, West Valley, New York ML20311A2002020-10-28028 October 2020 Response to NRC Letter: Initial Review for NYSERDA Request for License Amendment: Retained Premises Radiation Protection Requirements (LAR-20-001), Dated March 11, 2020 (EPID L-2020-LLA-0023), Dated March 30, 2020 ML20261H5452020-09-24024 September 2020 Change in the NRC Project Manager for the West Valley Demonstration Project ML20268B2372020-09-24024 September 2020 Change in the NRC Project Manager for the West Valley Demonstration Project ML20265A3552020-09-22022 September 2020 Comments on Rev.4 Main Plant Process Building Demolition & Decommissioning Plan ML20115E4972020-04-27027 April 2020 Second Round of Comments on U.S. Department of Energy West Valley Demonstration Projects Final Study Document: Vitrification Facility Air Emissions During Open-Air Demolition, Measured Vs Predicted, WVDP-579, Rev. 0 (Docket No. 05000201 (Po ML20084G6412020-03-30030 March 2020 Letter, A.Snyder to P. Bembia, NYSERDA, Initial Review for NYSERDA Request for License Amendment: Retained Premises Radiation Protection Requirements (LAR-20-001), Dated March 11, 2020 ML20076C3102020-03-11011 March 2020 Resubmittal of Request for License Amendment: Retained Premises Radiation Protection Requirements ML20055E0492020-02-19019 February 2020 Response to Comments on U.S. DOE, Wvdp Air Study IR 05000201/20200012020-02-10010 February 2020 U.S. Nuclear Regulatory Commission Monitoring Visit Report 05000201/2020001, West Valley Demonstration Project, West Valley, New York ML20042D4972020-02-0606 February 2020 Western New York Nuclear Service Center - Request for License Amendment: Retained Premises Radiation Protection Requirements (LAR-20-001) ML19319A2932019-12-0404 December 2019 Comments on U.S. Department of Energy West Valley Demonstration Project Final Study Document: Vitrification Facility Air Emissions During Open-Air Demolition, Measured Vs Predicted, WVDP-579 ML19267A2102019-09-12012 September 2019 U.S. Department of Energy West Valley Demonstration Project Main Plant Process Building Decommissioning & Demolition Plan, WVDP-586, Revision 3 ML20265A3952019-06-19019 June 2019 June 19, 2019 Letter from Brian C. Bower to Amy Snyder, West Valley Main Plant Process Building, Rev. 3 IR 05000201/20190012019-06-18018 June 2019 U.S. Nuclear Regulatory Commission Monitoring Visit Report 05000201/2019001, West Valley Demonstration Project, West Valley, Ny ML19149A2362019-05-30030 May 2019 NRC Response Letter to DOE-WVDP on the Main Process Plant Demolition Work Plan ML19149A5552019-05-28028 May 2019 Vaughan Letter on CSM Corrections Needed - 5-28-19 ML18282A5232018-11-0707 November 2018 NRC Response to Nyserda'S Requests for Clarification of License Responsibility ML18290A5662018-11-0101 November 2018 Response to NYSERDA 10 CFR 50.59 Evaluation IR 05000201/20180022018-10-25025 October 2018 U. S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2018002, West Valley Demonstration Project, West Valley, New York ML18262A2542018-09-12012 September 2018 NYSERDA Letter Dated September 12, 2018 Requesting Clarification License Responsibility ML18236A3882018-08-27027 August 2018 U.S. Department of Energy West Valley Demonstration Project Main Plant Process Building Decommissioning & Demolition Plan, WVDP-586, Revision 1, Dated February 27, 2017 ML18179A3992018-07-26026 July 2018 Response Letter - the U.S. Army Corps of Engineers Buffalo District Design - Level Sediment Sampling and Analysis Plan - Springville Dam and Cattaraugus Creek Sediment Sampling, Dated April 2018 ML18222A2192018-06-19019 June 2018 NRC Solar Letter IR 05000201/20180012018-06-0707 June 2018 U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2018001. West Valley, Demonstration Project, West Valley, New York ML18192C1592018-05-0202 May 2018 May 2, 2018 Letter from NYSERDA Regarding Conforming CSF-1 to Current Site Conditions ML18087A6662018-04-0909 April 2018 Cover Letter TER for Wvnsnsc Off-Site Evaluation IR 05000201/20170012018-02-22022 February 2018 U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2017001, West Valley Demonstration Project, West Valley, New York ML18092A0562018-02-0505 February 2018 U.S. Department of Energy West Valley Demonstration Project (DOE-WVDP) Responses to U.S. Nuclear Regulatory Commission (NRC) Comments on DOE-WVDP Main Plant Process Building (Mppb) Decommissioning & Demolition (D&D) Plan ML17347A1252018-01-16016 January 2018 Letter to Us Army Corps of Engineers - NRC Comments on Springville Dam Sampling and Analysis Plan ML17270A1192017-09-28028 September 2017 NRC Comments on the U.S. DOE West Valley Demonstration Project Main Plant Process Building Decommissioning & Demolition Plan, WVDP-586, Revision 1 (Docket No. 05000201 (POOM-032) 2024-09-23
[Table view] |
Text
tDepartment of Energy West Valley Demonstration Project 10282 Rock Springs Road West Valley, NY 14171-9799 ES June 22, 2011 Distribution
SUBJECT:
West Valley Demonstration Project (WVDP) Permeable Treatment Wall (PTW)
Documentation J
Dear Ladies and Gentlemen:
Enclosed is a package of reference materials on the PTW installed this past year at the WVDP.
The following are included in the package:
" List of reference documents and media articles on the PTW Referenced CD;
" PTW References CD containing 58 photographs covering multiple aspects (trencher testing, zeolite testing) of the PTW project, media coverage during installation, reference documents, and electronic copies of an aerial photograph of the PTW during construction and a cross sectional diagram of the PTW showing monitoring well locations;
" WVDP PTW Installation DVD with a narrated video (approximately two and a half minutes) of PTW installation;
" 11 inch by 17 inch laminated PTW cross sectional diagram and labeled aerial photograph of the PTW during installation; and
- Samples of the zeolite from the Bear River Mine (that was used in the PTW).
All the materials have been reviewed and are available for general use.
If you have any questions, please contact Moira N. Maloney of my staff at 716-942-4255.
Sincerely, C. Bower, Director West Valley Demonstration Project
Enclosures:
List of reference documents and media articles on the CD, PTW References CD, WVDP PTW Installation DVD, 11 inch by 17 inch laminated PTW cross sectional diagram and aerial photograph of the PTW, and samples of zeolite cc: See Page 2 JMD: 106060 - 455.4.2
4 Ladies and Gentlemen June 22, 2011 cc: L. A. Durham, ANL, w/enc.
R. L. Johnson, ANL, w/enc.
M. N. Maloney, DOE-WVDP, AC-DOE, w/o enc.
M. S. Bellis, DOE-WVDP, AC-DOE, w/o enc.
W. Frederick, USACE, w/enc.
C. A. Biedermann, WVES, AC-EA, w/o enc.
J. D. Chamberlain, WVES, AC-COMM, w/o enc.
L. M. Michalczak, WVES, AC-ENG, w/o enc.
JMD: 106060 - 455.4.2 JMD/jmd
Distribution: June 22, 2011 Mr. Paul A. Giardina Chief Radiation Indoor Air Branch U.S. Environmental Protection Agency, Region 2 DEPP-RIAB - 28th Floor 290 Broadway New York, NY 10007-1866 Ms. Jeanette Eng U.S. Environmental Protection Agency, Region 2 Radiation and Indoor Air Branch DEPP-RIAB, 2 8 th Floor 290 Broadway New York, NY 10007-1866 Mr. Patrick W. Concannon, P.G., Engineering Geologist Division of Hazardous Substance Regulation - Region 9 New York State Department of Environmental Conservation 270 Michigan Ave.
Buffalo, NY 14203-2999 Ms. Lynn M. Winterberger, P.E.
Environmental Engineer 2 RCRA Permitting Section Remedial Bureau E Division of Environmental Remediation New York State Department of Environmental Conservation 625 Broadway, 12th Floor Albany, NY 12233-7017 Mr. Timothy Rice Division of Environmental Remediation, Remedial Bureau A NYSDEC 625 Broadway Albany, NY 12233-3505 Mr. Mark Roberts U.S. Nuclear Regulatory Commission Region I - Division of Nuclear Materials Safety 475 Allendale Road King of Prussia, PA 19406-1415 Mr. Chad Glenn Dr. Keith I. McConnell, Deputy Director, U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission MS T-8-F5, TWFN MS T-8-F5, TWFN 11545 Rockville Pike 11545 Rockville Pike Rockville, MD 20852 Rockville, MD 20852 JMD: 106060 - 455.4.2 JMD/jmd
PTW References Folder This folder includes...
PTW Reference CD
- media articles; print and The Buffalo News on-line video
- reference documents; 2010 and 2011 Waste Management Symposium papers and presentations on the PTW, and references used in the 2011 paper (numbered 1-7)
- diagrams; labeled aerial photo taken during PTW installation and cross sectional diagram from the PTW Monitoring Plan showing location of monitoring wells
- photographs; selection of photographs including zeolite testing, trencher testing, and PTW installation PTW Video DVD
- 2 1/2 minute narrated video of PTW installation
- video plays with Windows Media Player later versions, but with older versions it may be necessary to load the codec from the DVD in order to play audio. Also plays with VLC Media Player.
Laminated Diagrams same diagrams as on CD