En tergy Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 July 8, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555-0001
SUBJECT:
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket No. 50-293 License No. DPR-35 Implementation of Pilgrim License Amendment 235, "Issuance of Amendment Related to Revised Technical Specifications for Setpoint and Setpoint Tolerances for Safety Relief Valves and Spring Safety Valves" (TAC NO. ME3453), dated March 28, 2011 LETTER NUMBER:
2.11.042
Dear Sir or Madam,
This letter documents the implementation of the Pilgrim License Amendment 235 related to the revised Technical Specifications for setpoint and setpoint tolerances for safety relief and spring safety valves. This implementation of the License Amendment was completed during Refueling Outage 18 (RFO-1 8) that ended on May 10, 2011.
There are no commitments made in this submittal.
If you have any questions, please call Mr. Joseph Lynch, Pilgrim Licensing Manager at 508-830-8403.
Sincerely, Joseph Lynch Pilgrim Licensing Manager cc:
Mr. Richard Guzman, Project Manager Plant Licensing Branch I-1 Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission One White Flint North, O-8C2 11555 Rockville Pike Rockville, MD 20852 NRC Senior Resident Inspector Pilgrim Nuclear Power Station