UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 July 11, 2011 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

NORTH ANNA POWER STATION, NOTIFICATION OF EMERGENCY PREPAREDNESS INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Heacock:

During the period of August 22-26, 2011, the NRC will conduct baseline emergency preparedness inspection activities at the North Anna Power Station. The inspection will evaluate activities in the Emergency Preparedness cornerstone using NRC Inspection Procedures (IP) 71114.02, 71114.03, 71114.04, and 71114.05. The inspection will also review the emergency preparedness performance indicators using IP 71151.

To minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. It is important that all of these documents are up to date and complete, thereby minimizing the number of additional documents requested during the preparation and/or the onsite portions of the inspection. The inspector has requested that the subject informational material be made available to the NRC staff upon arrival on August 22, 2011.

We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Jay Leberstein of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Mark Speck at (404) 997-4759.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document

VEPCO 2

Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/ reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Brian R. Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket Nos.: 50-338, 50-339 License Nos.: NPF-4, NPF-4

Enclosure:

Inspection Document Request List cc w/encl.: (See page 3)

ML111930674 X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII: DRS RII: DRS SIGNATURE RA RA NAME MSPECK BBONSER DATE 07/11/2011 07/11/2011 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

VEPCO 3

cc w/encl:

Daniel G. Stoddard Senior Vice President Nuclear Operations Virginia Electric and Power Company Electronic Mail Distribution Fred Mladen Director, Station Safety & Licensing Virginia Electric and Power Company Electronic Mail Distribution N. L. Lane Site Vice President North Anna Power Station Virginia Electric & Power Company Electronic Mail Distribution Chris L. Funderburk Director, Nuclear Licensing & Operations Support Virginia Electric and Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq.

Senior Counsel Dominion Resources Services, Inc.

Electronic Mail Distribution Executive Vice President Old Dominion Electric Cooperative Electronic Mail Distribution Ginger L. Melton Virginia Electric and Power Company Electronic Mail Distribution Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission P.O. Box 490 Mineral, VA 23117 Michael M. Cline Director Virginia Department of Emergency Services Management Electronic Mail Distribution County Administrator Louisa County P.O. Box 160 Louisa, VA 23093 Michael Crist Plant Manager North Anna Power Station Virginia Electric & Power Company Electronic Mail Distribution

Enclosure Document Request List Inspection Dates:

August 22-26, 2011 Inspection Procedures:

IP 71114.02 Alert and Notification System Testing IP 71114.03 Emergency Response Organization Staffing and Augmentation System IP 71114.04 Emergency Action Level and Emergency Plan Changes IP 71114.05 Correction of Emergency Preparedness Weakness IP 71151 Performance Indicator Verification Note: This is a list of the documents to be delivered to the NRC Region II Office (Attention:

Mark Speck, 245 Peachtree Center Avenue, NE, Suite 1200, Atlanta, GA 30303-1257) or provided to the inspector upon arrival onsite for the inspection. The current version of these documents is expected unless specified otherwise. Electronic media is preferred, if readily available (the preferred file format is Word or searchable pdf files on CDROM or thumb drive). Please organize the information as it is arranged below (e.g. a folder labeled Miscellaneous). It is not the intent that large or burdensome data be scanned for this purpose.

This data will be inspected using original documentation. If there are questions regarding the documents requested, please do not hesitate to contact the inspector.

EP2 Alert and Notification System (ANS) Testing Department of Homeland Security (DHS) approved Alert Notification System (ANS) report.

Alert Notification System Testing Procedure.

ANS equipment technical manual.

ANS equipment testing results (raw data) for two year inspection period.

ANS equipment maintenance records for two year inspection period.

Changes to the ANS system, testing procedures and the maintenance program including any supporting DHS approval letters.

Corrective action program entries related to the Alert and Notification System for the two year inspection period.

Copies of brochures/information provided to the public.

EP3 Emergency Response Organization (ERO) Staffing and Augmentation System Current ERO roster.

NUREG 0654 Table B1 site equivalent.

ERO training program procedure.

EP staff training program and qualification records.

ERO augmentation.

ERF activation, including backup, equipment initiation procedure.

ERO augmentation testing results.

Corrective action program entries related to the ERO staffing and augmentation for the two year inspection period.

2 Enclosure EP4 Emergency Action Level (EAL) and Emergency Plan Changes Governing document for 10 CFR 50.54(q) evaluation process.

10 CFR 50.54(q) evaluator training program and qualification records.

Changed procedure 10 CFR 50.54(q) evaluation.

Changed procedure current and immediately previous revisions.

Corrective action program entries related to Emergency Action Level and Emergency Plan changes for the two year inspection period.

EP5 Correction of Emergency Preparedness (EP) Weakness Governing document for the assessment process.

All EP program assessments, not including INPO performed assessments, for the two year inspection period.

10 CFR 50.54(t) audits and subsequent state/local correspondence for the two year inspection period.

Drill and exercise critiques for the two year inspection period.

Corrective action program entries that are an identifier and one line description, for the two year inspection period with the risk significant related entries separated.

EP01/EP02/EP03 Performance Indicators (PI) Verification Governing document for the performance indicator process.

Drill and Exercise Performance (DEP), Emergency Response Organization (ERO), and Alert and Notification System (ANS) PI data submitted for the two year inspection period.

DEP documentation and evaluations for the two year inspection period.

Current ERO roster.

Corrective action program entries related to performance indicators, that is DEP, ERO training and participation, and ANS for the two year inspection period.

Miscellaneous Procedures Current Emergency Plan.

Safety Evaluation Report approved Emergency Plan.

Current Emergency Action Levels.

Safety Evaluation Report approved Emergency Action Levels.

Current Emergency Plan implementing procedures.

Corrective Action Program procedure.

Lead Inspector Contact Information:

Mark E. Speck (404) 997-4759 Mark.Speck@nrc.gov Mailing Address US Nuclear Regulatory Commission, Region II ATTN: Mark Speck 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257