06/21/2011 Summary of the Public Meeting to Discuss the Results of the Columbia Generating Station License Renewal Inspection (Columbia Generating Station)
ML11188A096
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 07/06/2011
From: O'Keefe N
NRC Region 4
To: Reddemann M
Energy Northwest
References
Download: ML11188A096 (8)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 612 EAST LAMAR BLVD, SUITE 400 ARLINGTON, TEXAS 76011-4125 July 6,2011 Mr. Mark Keddemann Chief, Executive Officer Energy Northwest P.O. Box 968 (Mail Drop 1023)

Richland, WA 99352-0968

SUBJECT:

SUMMARY

OF THE PUBLIC MEETING TO DISCUSS THE RESULTS OF THE COLUMBIAl GENERATING STATION LICENSE RENEWAL INSPECTION

Dear Mr. Reddemann,

This refers to the public meeting conducted in an open house format at Richland, Washington, on June 21, 2011, with members of the public. The participants discussed the overall license renewal piOcess and piOvided the results of the license renewal inspection conducted at Columbia Generating Station, as documented in Inspection Report 05000397/2010007

[ADAMS Accession #ML103540496].

The attendance list is enclosed with this summary (Enclosure 1). A copy of the NRC presentation slides related to the license renewal inspection that sCiOlied during this open house meeting is also enclosed (Enclosure 2).

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, and its enclosure, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS).

ADAMS is accessible from the NRC Web site at (the Public Electronic Reading Room).

Should you have any questions concerning this matter, we will be pleased to discuss them with you.

Sincerely, IRA!

Neil O'Keefe, Chief Engineering Branch 2 Division of Reactor Safety Docket: 50-397 License: NPF-21

Enclosures:

1. Meeting Attendance
2. Presentation Distribution via ListServ for Columbia Generating Station

[Type text]

Electronic distribution by Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howeli@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov )

DRP Acting Deputy Director (Jeff.Clark@nrc.gov )

DRS Director (Anton.vegel@nrc.gov)

DRS Acting Deputy Director (Bob.Caldwell@nrc.gov)

Senior Resident Inspector (Ronald.Cohen@nrc.gov)

Resident Inspector (MahdLHayes@nrc.gov)

Branch Chief, DRP/A (Wayne.Walker@nrc.gov)

Senior Project Engineer, DRP/A (David.Proulx@nrc.gov)

Site Administrative Assistant (CrystaI.Myers@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Balwant.Singal@nrc.gov)

Branch Chief, DRSITSB (MichaeI.Hay@nrc.gov)

RITS Coordinator (Marisa. Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RidsNrrDlr Resource R \ REACTORS\COL\2011\CGS 201007 -MS LRI Resu It s- LTR -gap. d oc ADAMS ML ADAMS: [J No [8J Yes I [8J SUNSI Review Complete I Reviewer Initials: NFO I [8J Publicly Available I [8J Non-Sensitive I D Non-publicly Available I c Sensitive DRS/EB2 C:DRS/EB2 C:DRP/PBA C:DRStEB2 GPick NO'Keefe WWalker NO'Keefe IRA! IRA! IRA! IRA!

07/06/11 07/06/11 07/06/11 07/06/11 OFFICIAL RECORD COPY T=Telephone E=E-mall F=Fax

[Type text]

Enclosure 1 Meeting Attendance ist

Columbia Generating Station License Renewal Inspection Results Meeting Attendance Adami, Brian Energy Atkinson, Dale Energy Northwest Brandon, Denise Energy Northwest Brost, Franklin Cary, Annette Tri-City Herald Christianson, Kyle Energy Northwest Christianson, Sandra Energy Northwest Cohen, Ron USNRC, Region 4 Dobken, John Energy Northwest Fijalkowski, Louise Self Forrester, Chuck Energy Northwest Gilmore, Erin Energy Northwest Gregoire, Don Energy Northwest Hancock, Tim Energy Northwest Kosmata, Hank Self McCullen, Kevin Energy Northwest Miller, Arthur Self Mostala, Abbas Energy Northwest Myers, Crystal USNRC, Region 4 O'Connor, Scott Energy Northwest Oakley, Jim Energy Northwest Olson, Rochelle Energy Northwest Paoli, Mike Energy Northwest Pick, Greg USNRC, Region 4 Reddemann, Mark Energy Northwest Ridge, Brent Energy Northwest Sheldon, Tim Executive Board, Energy Northwest Sherman, Bob Bonneville Power Authority Smith, Angela Energy Northwest Swank, David Energy Northwest Torres, Roberto Energy Northwest Vargas, Felix USG (Retired)

Vaughn, Steve Energy Northwest Walker, Wayne USNRC, Region 4 Woosley, Linda Energy Northwest Enclosure 1

Enclosure 2 NRC Presentation

'f!i) License Renewal

'"

U.S.NRC lll\lTED STATES NUCLEAR REGU~TORY Protecting People and the Environment COMMlSSJON

  • Lubricating oil condition* evaluations
  • Evaluation of reactor building crack
  • Consistency of structural inspections

,'.;:;";::>'c,':':e

  • Scopiog &sereeningiliSPeeflon
  • System Reviews
  • Frequency for diesel fuel oil tank cleaning Enclosure 2

'1 JI!~ Inspection Conclusions

  • Sl;opblg of nOn .

appUcation.of the:

wer~ acceptable

  • Reasonable assurance exists that aging effects will be managed and
  • Inspection Report intended functions maintained - 05000397/2010Q()7 [ML103540496]
  • Arthur Cunanan, Project Manager

- (301) 415-3897

  • Daniel Doyle, Project Manager (301) 415-3748 2

Enclosure 2