NRC Staff Has Issued Supplement 2 to Safety Evaluation Report for License Renewal Application for Pilgrim
ML11181A257
Person / Time
Site: Pilgrim
Issue date: 06/30/2011
From: Mizuno B
NRC/OGC
To: Abramson P, Cole R, Austin Young
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 20537, 50-293-LR, ASLBP 06-848-02-LR
Download: ML11181A257 (4)


Text

June 30, 2011 Administrative Judge Administrative Judge Ann Marshall Young, Chair Paul B. Abramson Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop T-3F23 Mail Stop T-3F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 Administrative Judge Richard F. Cole Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 In the Matter of Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station)

Docket No. 50-293-LR; ASLBP No. 06-848-02-LR

Dear Administrative Judges:

The purpose of this letter is to inform you that the staff of the Nuclear Regulatory Commission (staff) has issued Supplement 2 to the Safety Evaluation Report (SER) for the license renewal application for Pilgrim Nuclear Power Station (Pilgrim) as filed by Entergy Nuclear Operations, Inc. (the applicant). Supplement 2 to the Pilgrim SER can be found in the Agencywide Document Management System (ADAMS) via Accession No. ML11147A034.

The staff issued an SER regarding the Pilgrim license renewal application in June 2007.

That SER summarized the results of the staffs safety review of the renewal application for compliance with the requirements of Title 10, Part 54 of the Code of Federal Regulations (10 CFR Part 54), Requirements for Renewal of Operating Licenses for Nuclear Power Plants.

The staff issued Supplement 1 to the SER in September 2007, which documented the safety review results of the applicants program to deal with the effects of reactor water environments on the fatigue life of reactor components. In November 2007, the staff issued NUREG-1891, Safety Evaluation Report Related to the License Renewal of Pilgrim Nuclear Power Station, which included both the June 2007 SER and Supplement 1.

This SER, Supplement 2, documents the staffs review of information provided by the applicant since the issuance of NUREG-1891. This information includes annual updates required by 10 CFR 54.21(b) and updated information and commitments in response to recent industry operating experience.

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 All entities identified in the attached Certificate of Service are being provided courtesy copies of this letter via the Electronic Information Exchange.

Sincerely,

/Signed Electronically By/

Beth N. Mizuno Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O15-D21 Washington, DC 20555 Telephone: (301) 415-3122 E-mail: Beth.Mizuno@nrc.gov UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of

)

)

ENTERGY NUCLEAR OPERATIONS, INC.

)

Docket No. 50-293-LR

)

(Pilgrim Nuclear Power Station)

)

)

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing letter regarding the issuance of Safety Evaluation Report, Supplement 2, for the Pilgrim Nuclear Power Station have been served upon the following by the Electronic Information Exchange, this 30th day of June, 2011:

Administrative Judge Richard F. Cole Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: Richard.Cole@nrc.gov Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: Paul.Abramson@nrc.gov Administrative Judge Ann Marshall Young, Chair Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: Ann.Young@nrc.gov Office of Commission Appellate Adjudication Mail Stop: O-16G4 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: OCAAMAIL.Resource@nrc.gov Atomic Safety and Licensing Board Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 (VIA INTERNAL MAIL ONLY)

Office of the Secretary Attn: Rulemakings and Adjudications Staff Mail Stop: O-16G4 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: Hearing.Docket@nrc.gov Sheila Slocum Hollis Duane Morris LLP 505 9th St., NW, Suite 1000 Washington, DC 20004 E-mail: sshollis@duanemorris.com Terence A. Burke, Esq.

Entergy Nuclear 1340 Echelon Parkway Mail Stop: M-ECH-62 Jackson, MS 39213 E-mail: tburke@entergy.com Mary Lampert 148 Washington Street Duxbury, MA 02332 E-mail: mary.lampert@comcast.net David R. Lewis, Esq.

Paul A. Gaukler, Esq.

Pillsbury, Winthrop, Shaw, Pittman, LLP 2300 N Street, NW Washington, DC 20037-1137 E-mail: david.lewis@pillsburylaw.com paul.gaukler@pillsburylaw.com Chief Kevin M. Nord Fire Chief & Director Duxbury Emergency Management Agency 668 Tremont Street Duxbury, MA 02332 E-mail: nord@town.duxbury.ma.us Town Manager Town of Plymouth 11 Lincoln St.

Plymouth, MA 02360 E-mail: marrighi@townhall.plymouth.ma.us Richard R. MacDonald Town Manager 878 Tremont Street Duxbury, MA 02332 E-mail: macdonald@town.duxbury.ma.us Matthew Brock Assistant Attorney General Commonwealth of Massachusetts One Ashburton Place Boston, MA 02108 Martha.Coakley@state.ma.us Matthew.Brock@state.ma.us

/Signed Electronically By/

Beth N. Mizuno Counsel for the NRC Staff