ATTACHMENT 4 Summary of Regulatory Commitments The following table identifies commitments made by Exelon Generation Company, LLC (EGC) in this document. Any other actions discussed in the submittal represent intended or planned actions. They are described to the NRC for the NRC's information and are not regulatory commitments.
COMMITMENT TYPE COMMITMENT COMMITTED DATE OR "OUTAGE" ONE-TIME ACTION (Yes/No)
PROGRAMMATIC (Yes/No)
Limitations regarding operation with an inoperable LEFM system will be included in the TRM.
Prior to increasing power above 3586.6 MWt No Yes The LEFM system for each unit at Byron and Braidwood Stations will be installed prior to uprate implementation Prior to increasing power above 3586.6 MWt Yes No Plant maintenance and calibration procedures will be revised to address Camerons maintenance and calibration requirements.
Prior to increasing power above 3586.6 MWt No Yes For Byron Station Units 1 and 2; and Braidwood Station Units 1 and 2; final acceptance of the unit-specific uncertainty analyses will occur after the completion of the commissioning process.
Prior to increasing power above 3586.6 MWt Yes No Non-safety related modifications for the power uprate, including switchyard modifications, will be implemented.
Prior to increasing power above 3586.6 MWt Yes No Modifications to support SGTR MTO analysis single failure considerations will be implemented.
Prior to increasing power above 3586.6 MWt Yes No Each stations simulator will be modified for the uprated conditions and the changes will be validated in accordance with plant configuration control processes.
Prior to increasing power above 3586.6 MWt Yes No Maintenance personnel will be qualified on LEFM system.
Prior to work on system No Yes Operator training will be completed on the LEFM modification and uprated power operations.
Prior to increasing power above 3586.6 MWt No Yes