0 FPL Florida Power & Light Company, 6501 S. Ocean Drive, Jensen Beach, FL 34957 June 16, 2011 L-2011-228 10 CFR 50.4 EPP 3.2.2 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re:
St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Environmental Protection Plan Report 316(b) Related Documentation Pursuant to section 3.2.2 of the St. Lucie Environmental Protection Plan, Florida Power &
Light Company (FPL) is forwarding the enclosed copy of 316(b) related documentation. The Florida Power & Light Company (FPL) - St. Lucie Nuclear Power Plant - Heated Water Plan of Study (HWPOS) is required by the amended St. Lucie Plant Industrial Wastewater Facility (IWWF) Permit - Revision, December 23, 2010, and Condition 17 of Administrative Order (AO) 022TL.
Please contact Ron Hix at (561) 691-7641 if there are any questions on this matter.
Sincerely, Eric S. Katzman Licensing Manager St. Lucie Plant ESK/tlt Enclosure an FPL Group company
St. Lucie Units I and 2 L-2011-228 Enclosure Florida Power & Light Company (FPL)
St. Lucie Nuclear Power Plant Heated Water Plan of Study (HWPOS)
(VPPSLO23)
Bound report & cover letter (28 Pages)
0Florida Power & Light Company, 6501 S. Ocean Drive, Jensen Beach, FL 34957 June 16, 2011 F=PL Marc Harris, P.E.
Supervisor, Power Plant NPDES Permitting Industrial Wastewater Section Florida Department of Environmental Protection 2600 Blair Stone Road, MS 3545 Tallahassee, Florida 32399-2400 RE:
St. Lucie Plant - State IWWF Permit No. FL0002208 Heated Water Plan of Study
Dear Mr. Harris:
Please find four (4) enclosed copies of Florida Power & Light Company (FPL) Heated Water Plan of Study (HWPOS) as required by the amended St. Lucie Plant Industrial Wastewater Facility (IWWF) Permit - Revision, December 23, 2010, and Condition 17 of Administrative Order (AO) 022TL. The Heated Water Plan of Study is required to be submitted to the Florida Department.of Environmental Protection (FDEP) for review and approval by June 21, 2011. Also, as stated in FPL's response (VPPSLO 12, May 10, 2011) to the Department's RFI letter re: FPL's Ambient Monitoring Report, dated April 14, 2011, the HWPOS incorporates an ambient monitoring station for the St. Lucie Plant.
Please signify the status of the FDEP's approval of the St. Lucie Plant Heated Water Plan of Study in your response to this submittal.
Please contact Ron Hix at (561) 691-7641 if you need additional information on this matter.
Sincerely, Rihard L. Anderts Site Vice President St. Lucie Plant VPPSL023
Enclosure:
Heated Water Plan Of Study - Florida Power & Light Company - St. Lucie Nuclear Power Plant (bound) cc: FDEP - SE District - Linda Brien FDEP - PSL Office - Terry Davis FDEP - Tallahassee - Siting Office - Mike Halpin an FPL Group company