Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2 License Renewal
ML111390275
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/19/2011
From: Subin L
NRC/OGC
To: Abramson P, Karlin A, Nicholas Trikouros
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 20336, 50-275-LR, 50-323-LR, ASLBP 10-900-01-LR-BD01
Download: ML111390275 (4)


Text

May 19, 2011 Administrative Judge Administrative Judge Alex S. Karlin, Chair Paul B. Abramson Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 Mail Stop: T-3F23 Washington, DC 20555-001 Washington, DC 20555-0001 Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)

Docket Nos. 50-275-LR and 50-323-LR RE: Projected Schedule for Completion of the Safety and Environmental Evaluations

Dear Administrative Judges:

Pursuant to the Boards Order of August 5, 2010 (Scheduling Initial Scheduling Conference),

this letter informs the Board of the NRC Staffs current milestone schedule for the Diablo Canyon Units 1 and 2 license renewal safety evaluation and environmental review. Please note that since the April 2011 update there is no change to the projected schedule for the Diablo Canyon Units 1 and 2 license renewal safety evaluation and environmental review.

Sincerely, Signed (electronically) by

_______________________________

Lloyd B. Subin Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1988 E-mail: Lloyd.Subin@nrc.gov Date of signature: May 19, 2011

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

PACIFIC GAS AND ELECTRIC COMPANY ) Docket Nos. 50-275-LR/ 50-323-LR

)

(Diablo Canyon Nuclear Power Plant, ) ASLBP No. 10-900-01-LR-BD01 Units 1 and 2) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Letter regarding Projected Schedule for Completion of the Safety and Environmental Evaluations, dated May 19, 2011 have been served upon the following by the Electronic Information Exchange, this 19th day of May, 2011:

Administrative Judge Office of Commission Appellate Alex S. Karlin, Chair Adjudication Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop - T-3 F23 Mail Stop - O-16G4 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov E-mail: ask2@nrc.gov Administrative Judge Office of the Secretary Nicholas G. Trikouros Attn: Rulemakings and Adjudications Staff Atomic Safety and Licensing Board Panel Mail Stop: O-16G4 Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: HEARINGDOCKET@nrc.gov E-mail: ngt@nrc.gov Administrative Judge David A. Repka, Esq.

Paul B. Abramson Tyson Smith, Esq.

Atomic Safety and Licensing Board Panel Carlos Sisco Mail Stop - T-3 F23 Winston & Strawn LLP U.S. Nuclear Regulatory Commission 101 California Street Washington, DC 20555-0001 San Francisco, CA 94111-5802 E-mail: pba@nrc.gov E-mail: drepka@winston.com trsmith@winston.com CSisco@winston.com

Jill ZamEk, Esq. Diane Curran, Esq.

San Luis Obispo Mothers for Peace Harmon, Curran, Spielberg, and Eisenberg 1123 Flora Road 1726 M Street NW Arroyo Grande, CA 93420 Suite 600 E-mail: jzk@charter.net Washington, DC 20036 E-mail: dcurran@harmoncurran.com Signed (electronically) by

_______________________________

Lloyd B. Subin Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1988 E-mail: Lloyd.Subin@nrc.gov Date of signature: May 19, 2011

3