MONTHYEARML24291A2602024-10-14014 October 2024 Oregon State University Triga Reactor (Ostr), Submittal of Annual Report for the Period July 1, 2023 Through June 30, 2024 ML24219A4062024-09-0404 September 2024 Oregon State University - Issuance of Amendment No. 27 to Renewed Facility Operating License No. R-106 for the Oregon State Triga Reactor ML24141A0072024-07-0303 July 2024 Examination Report Letter No. 50-243/OL-24-01, Oregon State University ML24141A0082024-07-0303 July 2024 Examination Result Letter No. 50-243/OL-24-01, Oregon State University ML24145A1262024-05-21021 May 2024 Oregon State University Triga Reactor (OSTR) Re Self-Reporting of a Potential Violation of a Technical Specification Involving Minimum Staffing IR 05000243/20242012024-04-0404 April 2024 Oregon State University - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000243/2024201 ML24078A3512024-03-29029 March 2024 Examination Confirmation Letter No. 50-243/OL 24-01, Oregon State University ML24089A1182024-03-22022 March 2024 Oregon State University Triga Reactor (Ostr), Additional Information Regarding License Amendment Request to Remove Square Wave Operation Mode and Targets ML24052A1432024-02-16016 February 2024 Oregon State University Triga Reactor (OSTR) License Amendment Request to Remove Square Wave Operation Mode and Targets IR 05000243/20232012023-08-24024 August 2023 Oregon State University – U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000243/2023201 ML23143A3132023-07-18018 July 2023 Examination Result Letter No 50-243/OL-23-01, Oregon State University ML23047A5482023-03-0808 March 2023 Examination Confirmation Letter No. 50-243/OL-23-01, Oregon State University ML22199A3092022-07-26026 July 2022 Oregon State University - Issuance of Amendment No. 26 to Renewed Facility Operating License No. R-106 for the Oregon State Triga Reactor ML22102A2842022-04-28028 April 2022 Oregon State University - Review and Approval of the Revised Oregon State Triga Reactor Requalification Plan IR 05000243/20222022022-04-23023 April 2022 Oregon State University - Us Nuclear Regulatory Commission Routine Safety Inspection Report No 05000243-2022202 ML22062B3052022-03-10010 March 2022 Examination Confirmation Letter No. 50-243/OL-22-01, Oregon State University ML22019A2982022-01-19019 January 2022 Oregon State University ,Response to RAI Regarding License Amendment Request, Oregon State University Triga Reactor Dated June 17, 2020 ML21299A2502021-10-22022 October 2021 Oregon State University Triga Reactor (Ostr), Docket No. 50-243, License No. R-106 ML21258A0732021-10-22022 October 2021 Oregon State University Request for Additional Information (RAI) Changes ML21250A3432021-09-20020 September 2021 Oregon State University Closure of Confirmatory Action Letter No. NRR-04-001 on the Site-Specific Compensatory Measures Implementation Plan ML21236A3462021-08-24024 August 2021 Oregon State Univ., License Amendment Request to Revise Requalification Plan for Licensed Operators ML21225A0832021-07-29029 July 2021 Oregon State Univ., Modifications to the OSTR Physical Security Plan (PSP) to Close Out Confirmatory Action Letter No. NRR-04-001 IR 05000243/20212012021-06-0303 June 2021 Oregon State Routine Inspection Report 05000243/2021201 ML21141A2892021-05-21021 May 2021 Oregon State University Triga Reactor (OSTR) - Amendment to Letter Dated June 17, 2020, License Amendment Request to Remove Technical Specification Requirements Related to Instrumented Fuel. ML21119A2362021-04-22022 April 2021 Oregon State University Triga Reactor (Ostr), Follow Up Report of Event Notification 55184 ML21092A1372021-04-0909 April 2021 Oregon State University - Regulatory Audit Re License Amendment Request to Remove Technical Specification Requirements ML20318A3802020-12-18018 December 2020 Oregon State University - Temporary Exemption from the Requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.b Related to Biennial Emergency Exercise (Covid 19) ML20350B7262020-12-10010 December 2020 Extension of Timeframe Required to Complete Biennial Emergency Exercise Per Oregon State Triga Reactor Emergency Response Plan, Facility Operating License No. R-106 ML20338A1302020-11-25025 November 2020 Oregon State University, Change in Level 1 Personnel Update ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20318A0352020-11-0303 November 2020 Extension of Timeframe Required to Complete Biennial Emergency Exercise Per Oregon State Triga Reactor Emergency Response Plan, Facility Operating License No. R-106 ML20307A4132020-10-22022 October 2020 Oregon State University Triga Reactor (OSTR) ML20247J5482020-09-0303 September 2020 Examination Confirmation Letter No. 50-243/OL-21-001, Oregon State University IR 05000243/20202012020-04-20020 April 2020 Oregon State University - Nuclear Regulatory Commission Routine Inspection Report No. 05000243/2020201 ML19298A4412019-10-21021 October 2019 Oregon State University - Radiation Center and Triga Reactor Annual Report 07/01/2018 - 06/30/2019 ML19290D8132019-10-14014 October 2019 Oregon State University, 10 CFR 50.54(q) Report of Changes to the Ostr Emergency Response Plan Which Do Not Decrease the Effectiveness of the Plan ML19281C3412019-10-0202 October 2019 Oregon State University Triga Reactor (Ostr) 10 CFR 50.54(q) Report of Changes to the Ostr Emergency Response Plan Which Do Not Decrease the Effectiveness of the Plan ML19199A1632019-07-24024 July 2019 Examination Report No. 50-243/OL-19-01, Oregon State University ML19210B8882019-07-22022 July 2019 Oregon State University - Transmittal of Reply to Notice of Violation ML19011A3502019-06-18018 June 2019 Oregon State University Issuance of Amendment Number 25 to Renewed Operating License No. R-106 for the Oregon State Triga Reactor, Technical Specifications ML19098A1672019-04-0303 April 2019 Oregon State University Triga Reactor (Ostr) - Modification of Ostr Physical Security Plan, Docket No. 50-243, License No. R-106 ML19065A0512019-02-28028 February 2019 Oregon State University - Supplement to Letter Dated of January 24, 2019, License Amendment Request to Remove Requirement for Fuel Temperature Measuring and Safety Channels While Transient Operation Modes Are Precluded IR 05000243/20192012019-02-15015 February 2019 Oregon State University - U.S. Nuclear Regulatory Commission Inspection Report No. 50-243/2019-201 ML19052A0512019-01-24024 January 2019 Oregon State Univ. Tiga Reactor (Ostr) - Replacement of November 5, 2018, License Amendment Request to Remove Requirement for Fuel Temperature Measuring and Safety Channels While Transient Operation Modes Are Precluded Letter of ... ML19009A0912019-01-0404 January 2019 Oregon State University - Proposed New Basis for the Limiting Safety System Setting ML18347A2112018-12-0707 December 2018 Oregon State Univ., 10 CFR 50.54(q) Report of Changes to the Ostr Emergency Response Plan Which Do Not Decrease the Effectiveness of the Plan ML18334A1002018-11-26026 November 2018 Oregon State University - Withdrawal of License Amendment Request from October 30, 2018 and Amendment to License Amendment Request from November 5, 2018 ML18312A0612018-11-0505 November 2018 Oregon State University Triga Reactor (Ostr) - License Amendment Request to Remove Requirement for Fuel Temperature Measuring and Safety Channels While Transient Operation Modes Are Precluded ML18312A0602018-10-30030 October 2018 Oregon State University - License Amendment Request to Receive a 20/20 Instrumented Fuel Element ML18297A0522018-10-19019 October 2018 Oregon State University, Change in Level 1 Personnel Update 2024-09-04
[Table view] |
Text
Radiation Center Oregon State University, 100 Radiation Center, Corvallis, Oregon 97331-5903 T 541-737-2341 I F 541-737-0480 I http://ne.oregonstate.edu/facilities/radiationcenter Oregon State UNIVERSITY May 6, 2011 Mr. Alexander Adams U. S. Nuclear Regulatory Commission Research and Test Reactors Branch A Office of Nuclear Reactor Regulation Mail Stop 012-G13 One White Flint North 11545 Rockville Pike Rockville, MD 20852-2738
Reference:
Oregon State University TRIGA Reactor (OSTR)
Docket No. 50-243, License No. R-106 Report on the Circumstances of the Event of April 6, 2011
Subject:
Self-reporting of a Technical Specification Violation Involving Reactivity Limits Mr. Adams:
We would like to respectfully submit the attached supplementary report to the Commission on the self-reported violation of our Technical Specification Limiting Condition of Operation 3.8.1, Reactivity Limits. The intent of this report is to reiterate the circumstance of the event described in the report of April 6 and to describe the corrective actions taken on our part to prevent reoccurrence.
Should there be questions regarding the information in this report or should you require more information, please do not hesitate to contact me.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on: s"/ /(
Sincerely, Stev n R es Director cc: Craig Bassett, USNRC Andy Klein, OSU Ken Niles, ODOE Todd Keller, OSU Rick Spinrad, OSU Document Control, USNRC Rich Holdren, OSU 40&D
OSU Supplementary Report on Reactivity Limit Violation Page 2 of 4 Violation of L.C.O. 3.8.1, Reactivity Limits Summary of Events The Oregon State University TRIGA° Reactor (OSTR) is a circular grid Mark II TRIGA° reactor.
Maximum licensed steady state 15ower is 1.1 MWth. The reactor may also be pulsed by reactivity insertion of up to $2.30 which corresponds to a peak power of approximately 2500 MWth.
The OSTR contains several experimental facilities. In-core facilities include a hollow aluminum In Core Irradiation Tube (ICIT), a Cadmium Lined In-Core Irradiation Tube (CLICIT), a G-Ring In-Core Irradiation Tube (GRICIT) and a pneumatic rabbit. The ICIT and CLICIT are located in the B-ring (B-1 position). The GRICIT and the rabbit are located in the G-ring. There are no other approved in-core experimental facilities. Ex-core experimental facilities include the rotating rack, the thermal column and four beam ports.
The OSTR staff was designing a new experiment which will utilize reactivity oscillation to measure reactor parameters. A preliminary test absorber was created to examine the reactivity worth vs. axial position of the absorber in the core at low power. During attempts to measure the maximum worth of this preliminary test absorber on Wednesday, April 6, it was determined that its worth was $0.60 at the mid-plane of the core. Technical Specification 3.8.1, Reactivity Limits, states in part that "The absolute value of the reactivity worth of any single unsecured experiment shall be less than $0.50." Measurements were taken in a manner such that the apparatus qualifies as a movable experiment, and moveable experiments are taken to be a subcategory of unsecured experiments.
The preliminary test absorber was fabricated by crushing an existing 1.25 cm segment of solid B4C and placing 29.8 grams of the material in a sealed aluminum TRIGA° tube. The reactivity of the absorber was not formally calculated, but it was believed that the worth of the absorber would be less than $0.20. This was based on the fact that a full length control rod absorber also made of B4C (38.1 cm) is worth about $2.00. Past experience has also shown that 20 grams of Cadmium tubing used for axial flux measurements has a reactivity worth of $0.19 in the B-1 position where the absorber was being tested.
To characterize the worth of the absorber, the reactor was first taken critical with the ICIT installed in the B-1 position. Critical rod heights were measured and core excess was calculated.
The reactor remained critical at 15 watts in automatic mode. The absorber was then manually lowered to the bottom of the ICIT by an operator. The regulating rod was observed to behave as anticipated, automatically withdrawing until some maximum worth position near core center was reached by the absorber, and then automatically inserting as the absorber was lowered to the bottom of the core. The worth of the absorber when resting at the bottom of the core was calculated by comparing regulating rod position with and without the absorber present. The worth was calculated to be less than $0.07.
When power and regulating rod position were stable, the absorber was slowly withdrawn 7.5" to the mid-plane of the core. The regulating rod automatically withdrew to compensate for the addition of negative reactivity as the absorber was moved to the higher worth position at the axial center of the core. The difference between regulating rod position with no absorber present and regulating rod position with the absorber at core center indicated that the worth of
OSU Supplementary Report on Reactivity Limit Violation Page 4 of 4
$0.07 when at the bottom of the core, the worth at core axial center would be much higher. As shown by this event, the worth of a sample near core center can be a factor of 10 higher than sample worth at the core edge.
Geometry and particularly surface area affects reactivity worth. The tip of a control rod effectively has one unshielded absorber surface, and this surface is partially obscured to neutron absorption by the attached fuel follower. The test absorber consisted of small pieces of B4 C which had a much higher surface area to volume ratio than an intact control rod absorber. The available neutron absorbing surface was significantly larger than the same mass of B4C at the tip of a control rod.
Corrective Actions To prevent reoccurrence, all movable experiments in the ICIT, CLICIT and GRICIT shall have their maximum reactivity worth measured as a secured experiment (Tech Spec definition 1.10.a) before they are used as a movable experiment.
Movable experiments external to the core (i.e. rotating rack, thermal column and beam ports) do not need to be measured due to the fact that objects outside the core are unlikely to have a measurable reactivity effect. Reactivity of movable experiments in the pneumatic rabbit facility do not need to be measured due to the fact that they are performed at the edge of the core and sample mass and volume are limited by the size of the rabbit capsule.
This corrective action will be implemented by a change to OSTR Operating Procedure 10, OperatingProceduresfor Reactor Experimental Facilities. All licensed operators will also be trained on the requirement to measure the reactivity worth of any movable experiment as a secured experiment prior to conducting the experiment as a movable experiment. These changes will be implemented no later than May 31, 2011.