Category:Legal-Pleading
MONTHYEARML19221B7252019-08-0909 August 2019 Applicants' Answer Opposing the Environmental Law & Policy Center'S Petition to Intervene and Hearing Request ML15138A1542015-05-18018 May 2015 FENOC Answer Opposing Motion to Amend Placeholder Contention ML15138A0662015-05-18018 May 2015 NRC Staff Answer to Motion to Amend ML15127A2512015-05-0707 May 2015 Reply by Beyond Nuclear, Blue Ridge Environmental Defense League, Nuclear Information and Resource Service, Seed Coalition and Southern Alliance for Clean Energy to Oppositions by Applicants and NRC Staff to Motions to Admit New Contentions ML15126A4782015-05-0606 May 2015 Reply by Beyond Nuclear, Blue Ridge Environmental Defense League, Nuclear Information and Resource Service, Seed Coalition and Southern Alliance for Clean Energy to Oppositions by Applicants and NRC Staff to Motions to Admit New Contentions ML15124A7652015-05-0404 May 2015 Firstenergy Nuclear Operating Company Response Opposing Motion to Reopen and Placeholder Contention Regarding Continued Storage Rule ML15121A4992015-05-0101 May 2015 NRC Staff Answer to Beyond Nuclear'S Hearing Request and Petition to Intervene and Motion to Reopen the Record in the License Renewal Proceeding for Davis-Besse Nuclear Power Plant ML14304A7202014-10-31031 October 2014 Firstenergy Nuclear Operating Co., Combined Response to Proposed Contention and Petition to Suspend Related to Alleged Need for Issuance of Waste Confidence Safety Findings ML14304A6872014-10-31031 October 2014 NRC Staff Consolidated Answer to Petitions to Suspend Final Reactor Licensing Decisions, Motions to Admit a New Contention, and Motions to Reopen the Record ML14304A6452014-10-31031 October 2014 Inc.'S Motion for Leave to File Amicus Curiae Brief ML14136A4862014-05-16016 May 2014 Fenoc'S Answer Opposing Intervenors'S Motion for Admission of Contention No. 6 ML14136A3272014-05-16016 May 2014 NRC Staff'S Answer to Motion for Admission of Contention No. 6 on Shield Building Concrete Void, Cracking and Broken Rebar Problems ML14087A0252014-03-28028 March 2014 March 2014 Status Update Letter ML14080A2352014-03-21021 March 2014 NRC Staff Answer Opposing Suspension Petition ML14080A5932014-03-21021 March 2014 Firstenergy Nuclear Operating Company Response to Petition to Suspend Licensing Decisions Pending Completion of Rulemaking ML13189A3272013-07-0808 July 2013 NRC Staff Answer to Firstenergy Nuclear Operating Company Motion to Strike ML13165A3512013-06-14014 June 2013 NRC Staff Answer to the Beyond Nuclear, Citizens Environment Alliance of Southwestern Ontario, Don'T Waste Michigan, and Ohio Sierra Club Joint Request for a Hearing and Petition to Intervene ML13165A3022013-06-14014 June 2013 Firstenergy Nuclear Operating Company'S Answer Opposing Petition to Intervene and Request for Hearing Regarding Technical Specification License Amendment Request ML13155A2852013-06-0404 June 2013 Notice of Appearance of Mitzi A. Young on Behalf of the U.S. Nuclear Regulatory Commission in the Matter of Davis-Besse Nuclear Power Station, Unit 1 ML13141A2502013-05-20020 May 2013 Petition to Intervene and for an Adjudicatory Public Hearing of FENOC License Amendment Request ML12306A2732012-11-0101 November 2012 Fenocs Answer Opposing Intervenors' Motion for Reconsideration of Order Striking Intervenors' Answer to Fenocs Motion for Summary Disposition of Contention 4 ML12305A2782012-10-31031 October 2012 NRC Staff'S Answer to Intervenors' Motion for Reconsideration of ASLB Order Granting Fenoc'S Motion to Strike Intervenors' Reply in Opposition to Firstenergy'S Motion for Summary Disposition of Contention 4 (Sama Analysis - Source Terms) ML12258A3112012-09-14014 September 2012 Attachment E - NRC Staff Answer to Motion for Summary Disposition of Contention 4 ML12258A3072012-09-14014 September 2012 Attachment D - NRC Staff Answer to Motion for Summary Disposition of Contention 4 ML12258A3082012-09-14014 September 2012 the Staff'S Response to Firstenergy'S Statement of Materials Facts ML12258A3092012-09-14014 September 2012 Attachment a - NRC Staff Answer to Motion for Summary Disposition of Contention 4 ML12258A3062012-09-14014 September 2012 Attachment B - NRC Staff Answer to Motion for Summary Disposition of Contention 4 ML12258A3122012-09-14014 September 2012 K. Ross Statement of Professional Qualifications ML12258A3142012-09-14014 September 2012 NRC Staff'S Answer to Firstenergy'S Motion for Summary Disposition of Contention 4 (SAMA Analysis Source Terms) ML12258A3132012-09-14014 September 2012 Affidavit of Kyle W. Ross Concerning the Motion for Summary Disposition of Contention 4 ML12254B0862012-09-10010 September 2012 Fenoc'S Answer Opposing Intervenors' Fifth Motion to Amend And/Or Supplement Proposed Contention No. 5 (Shield Building Cracking) ML12254A1382012-09-10010 September 2012 NRC Staff'S Answer to Intervenors' Fifth Motion to Amend And/Or Supplement Proposed Contention No. 5 (Shield Building Cracking) ML12230A3182012-08-17017 August 2012 Fenoc'S Answer Opposing Intervenors' Third and Fourth Motions to Amend And/Or Supplement Proposed Contention No. 5 (Shield Building Cracking) ML12230A2122012-08-17017 August 2012 NRC Staff'S Answer to Intervenors' Third and Fourth Motions to Amend And/Or Supplement Proposed Contention No. 5 (Shield Building Cracking) ML12216A1452012-08-0303 August 2012 Fenoc'S Answer Opposing New Contention Concerning Temporary Storage and Ultimate Disposal of Nuclear Waste at Davis-Besse Nuclear Power Station ML12215A5072012-08-0202 August 2012 NRC Staff'S Answer to Intervenor'S Motion for Leave to File a New Contention Concerning Temporary Storage and Ultimate Disposal of Nuclear Waste at Davis-Besse Nuclear Power Station ML12215A2952012-08-0202 August 2012 NRC Staff'S Unopposed Motion for Extension of Time to File an Answer to Firstenergy'S Motion for Summary Disposition of Contention 4 (SAMA Analysis Source Terms) ML12208A4292012-07-26026 July 2012 Attachment 1, Firstenergy Statement of Material Facts on Which There Is No Genuine Issue to Be Heard (July 26, 2012) ML12208A4302012-07-26026 July 2012 List of Attachments to Firstenergy'S Motion for Summary Disposition of Contention 4 (SAMA Analysis Source Terms) ML12181A3032012-06-29029 June 2012 Fenoc'S Answer Opposing Intervenors' Motion to Amend and Supplement Proposed Contention No. 5 (Shield Building Cracking) ML12181A0132012-06-29029 June 2012 NRC Staff'S Answer to Motion to Amend and Supplement Proposed Contention No. 5 (Shield Building Cracking) ML12177A0282012-06-25025 June 2012 NRC Staff'S Answer to Petition to Suspend Final Decisions in All Pending Reactor Licensing Proceeding Pending Completion of Remanded Waste Confidence Proceedings ML12177A2002012-06-25025 June 2012 Fenoc'S Answer Opposing Petition to Suspend Final Licensing Decisions Pending Completion of Remanded Waste Confidence Proceedings ML12118A5402012-04-27027 April 2012 Notices of Appearance of Paul M. Bessette and Stephen J. Burdick ML12118A5412012-04-27027 April 2012 Joint Answer Opposing Hearing Requests Regarding Sufficiency of Order EA-12-051 Modifying Licenses with Regard to Spent Fuel Pool Instrumentation ML12110A4702012-04-19019 April 2012 Notice of Appearance Withdrawal of Alex Polonsky ML12110A4662012-04-19019 April 2012 Notice of Appearance Withdrawal of Brooke Leach ML12068A0952012-03-0808 March 2012 NRC Staff'S Answer to Intervenor'S Motion to Amend 'Motion for Admission of Contention No. 5.' ML12068A4292012-03-0808 March 2012 Fenoc'S Answer Opposing Intervenors' Motion to Amend Proposed Contention 5 on Shield Building Cracking ML12068A0942012-03-0808 March 2012 Attachment C - NRC Staff Affidavit of Abdul H. Sheikh Concerning Intervenors' Motion to Amend Motion for Admission of Contention No. 5 2019-08-09
[Table view] |
Text
May 6, 2011 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Office of the Secretary In the Matter of: ) Docket No. 50-346 FirstEnergy Nuclear Operating Company )
Davis-Besse Nuclear Power Station, Unit 1 )
(Regarding the Renewal of Facility )
Operating License NPF-003 for a 20-Year Period) )
)
CERTIFICATE OF SERVICE I hereby certify that on May 6, 2011, I served Petitioners Reply, Motion for Modification of Order to Allow Reply and Certification of Consultation on the parties listed below via electronic deposit filing with the Commissions EIE system:
Administrative Judge Rulemakings and Adjudications Staff William J. Froehlich, Chair Washington, DC 20555-0001 Atomic Safety and Licensing Board Panel E-mail: hearingdocket@nrc.gov U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Office of the General Counsel E-mail: wjf1@nrc.gov U.S. Nuclear Regulatory Commission Mail Stop O-15D21 Administrative Judge Washington, DC 20555-0001 Dr. William E. Kastenberg Brian G. Harris Atomic Safety and Licensing Board Panel Megan Wright U.S. Nuclear Regulatory Commission Emily L. Monteith Washington, DC 20555-0001 E-mail: Brian.Harris@nrc.gov; E-mail: wek1@nrc.gov Megan.Wright@nrc.gov; Emily.Monteith@nrc.gov Office of the Secretary U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Kevin Kamps U.S. Nuclear Regulatory Commission Radioactive Waste Watchdog Mail Stop: O-16C1 Beyond Nuclear Washington, DC 20555-0001 6930 Carroll Avenue, Suite 400 E-mail: ocaamail@nrc.gov Takoma Park, MD 20912 Tel. 301.270.2209 ext. 1 Michael Keegan Email: kevin@beyondnuclear.org Dont Waste Michigan Website: www.beyondnuclear.org 811 Harrison Street Monroe, MI 48161 E-mail: mkeeganj@comcast.net Stephen J. Burdick Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, N.W.
Washington, D.C. 20004 Phone: 202-739-5059 Fax: 202-739-3001 E-mail: sburdick@morganlewis.com Respectfully submitted,
/s/ Terry J. Lodge Terry J. Lodge, Esq. (OH Bar #0029271) 316 N. Michigan St., Ste. 520 Toledo, OH 43604-5627 (419) 255-7552 Fax (419) 255-8582 tjlodge50@yahoo.com