April 26, 2011 MEMORANDUM TO: Sandra Wastler, Chief Materials, Waste and International Security Branch Division of Security Policy Office of Nuclear Security and Incident Response FROM:
Eric J. Benner, Chief /RA/
Rules, Inspection and Operations Branch Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards
SUBJECT:
TECHNICAL ASSISTANCE REQUEST - REVIEW OF PROPOSED AMENDMENT TO THE COMANCHE PEAK NUCLEAR POWER PLANT PHYSICAL SECURITY PLAN (TAC NO. L24532)
The Division of Spent Fuel Storage and Transportation (SFST), Office of Nuclear Material Safety and Safeguards (NMSS), requests technical assistance from the Division of Security Policy (DSP), Nuclear Security and Incident Response (NSIR), for the completion of the following project:
PROJECT: Review Luminant Power Generation Companys (Luminant) response to Order (EA-10-0051) and the Comanche Peak Nuclear Power Plant Independent Spent Fuel Storage Installation (ISFSI) Physical Security Plan and verify implementation of the additional security measures.
DOCKET NOS: 50-445 and 50-446, 72-74 TAC NO: L24532 REQUESTED ACTION: NMSS/SFST requests that NSIR/DSP review Luminants response to the ISFSI Security Order and the Comanche Peak Nuclear Power Plant ISFSI Physical Security Plan. Prepare a memorandum documenting the results of NSIRs review.
Please provide the information requested below and return a completed copy to the SFST Project Manager designated below.
Name of NSIR/DSP assigned Reviewer: _________________________________
NSIR/DSP Project Completion Date: _________________________________
NSIR/DSP Branch Chief Signature: _________________________________
Contact:
Raynard Wharton (301) 492-3316 The above TAC No. should be referenced in future correspondence related to this request and in the Human Resources Management System for recording staff time expended on this effort.
Please provide the information requested below and return a completed copy to the SFST Project Manager designated below.
Name of NSIR/DSP assigned Reviewer: _________________________________
NSIR/DSP Project Completion Date: _________________________________
NSIR/DSP Branch Chief Signature: _________________________________
Contact:
Raynard Wharton (301) 492-3316 The above TAC No. should be referenced in future correspondence related to this request and in the Human Resources Management System for recording staff time expended on this effort.
Distribution: (w/o attachment)
SFST r/f BWhite ADAMS: ML111160488 G:\\SFST\\Security - ICMS & Orders\\TARs\\Comanche Peak TAR.doc OFC SFST SFST SFST NAME RWharton WWheatley EBenner DATE 04/ 26 /11 04/ 26 /11 04/ 26 /11 OFFICIAL RECORD COPY