2011 Point Beach Nuclear Plant Initial License Examination Administrative Files ES-201-1
ML11112A035
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 04/25/2011
From: Mcneil D
NRC/RGN-III/DRS/OLB
To:
Florida Power & Light Energy Point Beach
References
Download: ML11112A035 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Point Beach Nuclear Power Plant Date of Examination: 04/25/2011 Examinations Developed by: NRC Target Date*

Task Description (Reference)

Chief Examiner=s Initials k

-180

1.

Examination administration date confirmed (C.1.a; C.2.a and b) dm

-120

2.

NRC examiners and facility contact assigned (C.1.d; C.2.e) dm

-120

3.

Facility contact briefed on security and other requirements (C.2.c) dm

-120

4.

Corporate notification letter sent (C.2.d) dm

[-90]

[5. Reference material due (C.1.e; C.3.c; Attachment 2)]

dm

-75

6.

Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d) dm

-70

7.

Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e) dm

-45

8.

Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6), and reference materials due (C.1.e, f, g and h; C.3.d) dm

-30

9.

Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202) dm

-14

10. Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202) dm

-14

11. Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) dm

-14

12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dm

-7

13. Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) dm

-7

14. Final applications reviewed; examination approval and waiver letters sent (C.2.i; Attachment 4; ES-204) dm

-7

15. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) dm

-7

16. Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) dm Target dates are keyed to the examination date identified in the corporate notification letter.

They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.

[ ]

Applies only to examinations prepared by the NRC.