MONTHYEARML24025A0392024-01-12012 January 2024 Independent Spent Fuel Storage Installation, Property Insurance Coverage ML23342A1112024-01-0909 January 2024 Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML23117A0452023-04-25025 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2022 ML23113A0052023-03-31031 March 2023 Request for Exemption from 10 CFR 50.82 10 CFR 50.75 for the Maine Yankee Independent Spent Fuel Storage Installation NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report ML23068A0132023-03-0606 March 2023 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22340A4622023-02-24024 February 2023 Closeout Letter to Maine Yankee Atomic Power Company Regarding 2018 and 2021 Updated DFPs for Maine Yankee ISFSI IR 07200030/20234012023-01-26026 January 2023 Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200030/2023401 (Letter Only) ML23026A0802023-01-17017 January 2023 Company - Property Insurance Coverage IR 07200030/20224012022-10-11011 October 2022 Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200030/2022401 ML22216A0682022-07-28028 July 2022 Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22088A0182022-04-0101 April 2022 Independent Spent Fuel Storage Installation, 10 CFR 50.59 Biennial Report ML22088A0212022-04-0101 April 2022 Independent Spent Fuel Storage Installation, 10 CFR 72.48 Biennial Report NG-22-0041, and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report ML22088A0162022-03-14014 March 2022 Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22088A0122022-03-14014 March 2022 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22011A1332022-01-31031 January 2022 Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML22045A0652022-01-20020 January 2022 Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage ML22045A0662022-01-20020 January 2022 Independent Spent Fuel Storage Installation - Property Insurance Coverage ML21362A1592021-12-10010 December 2021 Independent Spent Fuel Storage Installation, Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan IR 05000309/20210012021-10-28028 October 2021 Company - NRC Independent Spent Fuel Storage Installation Inspection Report Nos. 07200030/2021001 and 05000309/2021001 NG-21-0006, 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report2021-03-31031 March 2021 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report ML21077A1672021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML21105A7392021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML21042B5932021-01-27027 January 2021 Independent Spent Fuel Storage Installation, Property Insurance Coverage ML21042B5942021-01-27027 January 2021 Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage ML21012A3992021-01-13013 January 2021 Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML21050A2302021-01-11011 January 2021 Independent Spent Fuel Storage Installation - Formal Announcement of New ISFSI Manager ML21042B8962021-01-11011 January 2021 Independent Spent Fuel Storage Installation, Biennial Update of the Defueled Safety Analysis Report IR 07200030/20204012020-10-21021 October 2020 Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200030/2020401 ML20136A3372020-04-22022 April 2020 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2019 ML20101H9312020-04-0101 April 2020 Independent Spent Fuel Storage Installation - 10 CFR 50.59 Biennial Report ML20097B6692020-03-19019 March 2020 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML20087J6772020-03-11011 March 2020 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML20015A5492020-01-15015 January 2020 Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML19241A4582019-08-29029 August 2019 Letter to T. Matthews Maine Yankee Atomic Power Company - Threshold Determination That NRC Consent Is Not Required in Connection with Acquisition of Emera Maine by Enmaz Corporation ML19182A0402019-07-0505 July 2019 Letter to P. Dostie Maine Yankee Atomic Power Company Exemption Request from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for the ISFSI ML19182A0322019-07-0505 July 2019 Letter to J. Brown Maine Yankee Atomic Power Company Exemption Request from Certain Requirements of 10 CFR 72.214 for the ISFSI ML19113A1032019-04-23023 April 2019 Request for NRC Threshold Determination That NRC Consent Is Not Required in Connection with Acquisition of Emera Maine by Enmax Corporation ML19127A2892019-04-16016 April 2019 Independent Spent Fuel Storage Installation, Submittal of Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2018 ML19112A0242019-04-11011 April 2019 Independent Spent Fuel Storage Installation, Reference Correction - Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML19116A0512019-03-12012 March 2019 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML19038A0572019-01-29029 January 2019 Independent Spent Fuel Storage Installation (ISFSI) - Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML19031B3412019-01-21021 January 2019 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for the Maine Yankee Independent Spent Fuel Storage Installation ML18319A0992018-11-0101 November 2018 Independent Spent Fuel Storage Installation - Quality Assurance Program - Biennial Update ML18206A4702018-07-10010 July 2018 Independent Spent Fuel Storage Installation - Notification of Change in Maine Yankee Board of Directors IR 05000309/20180012018-05-30030 May 2018 NRC Independent Spent Fuel Storage Installation Report Nos. 07200030/2018001 and 05000309/2018001, Maine Yankee Atomic Power Company, Wiscasset, Maine Site ML18151A4752018-05-22022 May 2018 Independent Spent Fuel Storage Installation - Notification of Change Board of Directors ML18143B4702018-05-0707 May 2018 Independent Spent Fuel Storage Installation - Notification of Change in Maine Yankee Board of Directors ML18128A2662018-04-17017 April 2018 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2017 2024-01-09
[Table view] |
Text
April 20, 2011 Ms. Phyllis Merriam 72 Mechanic Street Rockland, ME 04841-3514
SUBJECT:
CLOSED NUCLEAR PLANT IN WISCASSET, MAINE, AND EVENTS IN JAPAN
Dear Ms. Merriam:
The U.S. Nuclear Regulatory Commission (NRC) received your letter dated March 21, 2011, in which you posed several questions directly related to the Maine Yankee Nuclear Power Plant and recent events in Japan. Specifically, you inquired about security measures and pre-staged responses designed to protect Maine residents. You also inquired about containment issues due to the age of the Maine Yankee plant and the meltdowns at the Japanese nuclear plants.
The Maine Yankee nuclear plant ceased to generate power in 1996 and was subsequently decommissioned. After the plant was decommissioned, the only license in effect for the Wiscasset, Maine site is one to store irradiated nuclear fuel and other reactor-related nuclear waste in dry cask storage in an independent spent fuel storage facility. Responses to your questions are enclosed in this letter. I am additionally enclosing a brochure provided by Maine Yankee that provides further detailed information on the operation, decommissioning, and interim storage of the spent nuclear fuel.
The NRC is firmly committed to ensuring the safe storage of nuclear material at facilities like that in Wiscassett. Therefore, as a result of the events in Japan, the NRC has initiated a review of its processes and regulations in order to determine whether changes are necessary to our regulatory structure. The NRC values your feedback regarding spent nuclear fuel storage issues. Therefore, if you have any further questions, do not hesitate to contact Mr. William Allen, of my staff at William.Allen@nrc.gov.
Sincerely,
/RA/
Doug Weaver, Deputy Director Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards Docket Nos.: 50-309, 72-30
Enclosures:
As stated
April 20, 2011 Ms. Phyllis Merriam 72 Mechanic Street Rockland, ME 04841-3514
SUBJECT:
CLOSED NUCLEAR PLANT IN WISCASSET, MAINE, AND EVENTS IN JAPAN
Dear Ms. Merriam:
The U.S. Nuclear Regulatory Commission (NRC) received your letter dated March 21, 2011, in which you posed several questions directly related to the Maine Yankee Nuclear Power Plant and recent events in Japan. Specifically, you inquired about security measures and pre-staged responses designed to protect Maine residents. You also inquired about containment issues due to the age of the Maine Yankee plant and the meltdowns at the Japanese nuclear plants.
The Maine Yankee nuclear plant ceased to generate power in 1996 and was subsequently decommissioned. After the plant was decommissioned, the only license in effect for the Wiscasset, Maine site is one to store irradiated nuclear fuel and other reactor-related nuclear waste in dry cask storage in an independent spent fuel storage facility. Responses to your questions are enclosed in this letter. I am additionally enclosing a brochure provided by Maine Yankee that provides further detailed information on the operation, decommissioning, and interim storage of the spent nuclear fuel.
The NRC is firmly committed to ensuring the safe storage of nuclear material at facilities like that in Wiscassett. Therefore, as a result of the events in Japan, the NRC has initiated a review of its processes and regulations in order to determine whether changes are necessary to our regulatory structure. The NRC values your feedback regarding spent nuclear fuel storage issues. Therefore, if you have any further questions, do not hesitate to contact Mr. William Allen, of my staff at William.Allen@nrc.gov.
Sincerely,
/RA/
Doug Weaver, Deputy Director Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards Docket Nos.: 50-309, 72-30
Enclosures:
As stated Adams ML DISTRIBUTION: (EDATS: OEDO-2011-230/G20110223)
File location: G:\SFST\Maine Yankee\Japan Inquiry\Letter.docx OFC: SFST SFST SFST SFST SFST SFST NAME: WAllen WWheatley MWaters VOrdaz DATE: 4/19/11 4/19/11 4/19/11 4/20/11 OFFICIAL RECORD COPY
LETTER TO MS. PHYLLIS MERRIAM QUESTIONS AND ANSWERS REGARDING CLOSED NUCLEAR PLANT IN WISCASSET, MAINE, AND EVENTS IN JAPAN
- Are there security measures in place to protect Maine residents from natural or man-made disasters?
The Maine Yankee facility is required to have security measures in place to prevent sabotage or theft of the spent fuel from the storage area. The dry cask storage system employed at Maine Yankee is designed to prevent the release of the radioactive material in the fuel during natural disasters.
- Are there any pre-staged responses in place to protect Maine residents?
The Maine Yankee facility is required to have emergency response plans in place.
However, offsite actions are not required as part of the emergency response plan due to the long cooling time of the spent fuel. This is because the accidents that have the potential for the greatest offsite impact are those that involve spent fuel that has recently been moved from the reactor to the spent fuel pool. Since the Maine Yankee fuel has been sufficiently cooled to be removed from the spent fuel pool, the accidents which have the greatest potential for offsite impact are not physically possible; therefore offsite emergency response plans are not required.
- What are the containment issues at such an old plant such as Maine Yankee in view of the meltdowns at Japanese nuclear plants?
The containment issues at Maine Yankee are significantly different from those associated with the Japanese plants. First, the heat generated by the fuel at Maine Yankee is significantly lower than that at the Japanese plants because, as you mentioned in your letter, Maine Yankee has not generated electricity since 1996. Second, as of April 29, 2003, all fuel had been removed from both the reactor and the spent fuel pool and placed into a dry storage system. The dry storage system at Maine Yankee uses steel containers which are stored above ground in a vertical orientation inside concrete. The containers used to store the Maine Yankee fuel were fabricated to high standards of quality. The containers were welded shut after the fuel was placed inside, and the canisters were filled with an inert gas to ensure the fuel rods, which provide an additional layer of containment, retain both their shape and strength during storage. The dry storage system at Maine Yankee was evaluated as a whole to ensure it could withstand a variety of disasters, such as earthquakes, floods, projectiles originating from a tornado, temperature extremes, and lightning strikes.
Enclosure