UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of Docket # 50-293-LR Entergy Corporation Pilgrim Nuclear Power Station License Renewal Application April 11 2011 Pilgrim Watch Answer to Entergys and NRC Staffs Reply to Pilgrim Watch Post-Hearing Memorandum Filed April 7, 2011 Entergy and NRC Staff make essentially the same comments in their responses to Pilgrim Watchs Post-hearing Memorandum submitted March 28, 2011; for efficiency, Pilgrim Watch will reply to both in this one filing.
Pilgrim Watch trusts that the ASLB is fully capable of deciding of what facts it will take judicial notice. Those facts quite clearly include that there has been a nuclear disaster in Japan. We are more than a little surprised that both Entergy and the NRC Legal Staff seems to think that this simple fact is still speculative and subject to controversy.
Pilgrim Watch is also surprised by NRC Legal Staffs apparent assertion that The Cause of the Accident in Japan is Speculative, that Pilgrim Watchs statement that the basic cause of the disaster was the loss of off-site power is without any evidence to support that conclusion; and Entergys similar comments. The NRC Information Notice 2011-
05, Tohoku Taiheiyo-Oki Earthquake Effects on Japanese Nuclear Power Plants, dated March 18, 2011 is quite clear (underlining added):
This magnitude 9.0 earthquake and the subsequent tsunami caused significant damage to at least four of the six units of the Fukushima Daiichi nuclear power station as the result of sustained loss of both the offsite and on-site power systems. (Emphasis added)
Thank-you for your consideration, Respectfully signed, Mary lampert (Signed Electronically)
Pilgrim Watch, pro se 148 Washington Street Duxbury, MA 02332 Tel. 781-934-0389 Email mary.lampert@comcast.net April 11, 2011
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before The Atomic Safety and Licensing Board In the Matter of Docket # 50-293-LR Entergy Corporation Pilgrim Nuclear Power Station License Renewal Application April 11, 2011 CERTIFICATE OF SERVICE I hereby certify that Pilgrim Watch Answer to Entergys and NRC Staffs Reply to Pilgrim Watch Post-Hearing Memorandum Filed April 7, 2011 and Certificate of Service were served April 11, 2011 in the above captioned proceeding to the following persons by the Electronic Information Exchange and complimentary copies sent via email to the service list Secretary of the Commission Attn: Rulemakings and Adjudications Staff Mail Stop 0-16 C1 United States Nuclear Regulatory Commission Washington, DC 20555-0001 Administrative Judge Ann Marshall Young, Chair Atomic Safety and Licensing Board Mail Stop - T-3 F23 US NRC Washington, DC 20555-0001 Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Mail Stop T-3 F23 US NRC Washington, DC 20555-0001 Administrative Judge Richard F. Cole Atomic Safety and Licensing Board Mail Stop -T-3-F23 US NRC Washington, DC 20555-0001 Office of Commission Appellate Adjudication Mail Stop 0-16 C1 United States Nuclear Regulatory Commission Washington, DC 20555-0001 Atomic Safety and Licensing Board Mail Stop T-3 F23 United States Nuclear Regulatory Commission Washington, DC 20555-0001
U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Mail Stop: 0-16C1 Washington, DC 20555-0001 U.S. Nuclear Regulatory Commission Office of General Counsel Mail Stop: 0-15 D21 Washington DC 20555-0001 Susan L. Uttal, Esq.
Andrea Jones, Esq.
Brian Harris, Esq.
Michael Dreher, Esq.
Brian Newell, Paralegal U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Mail Stop: 011-F1 Washington, DC 20555-0001 Lisa Regner, Project Mgr. Plant Lic.
Branch 1-1, Operator Reactor Licensing Washington, DC 20555-0001 Paul A. Gaukler, Esq.
David R. Lewis, Esq.
Jason B. Parker, Esq.
Pillsbury, Winthrop, Shaw, Pittman, LLP -
2300 N Street, N.W.
Washington, DC 20037-1128 Martha Coakley, Attorney General Matthew Brock, Assistant Attorney General Commonwealth of Massachusetts Office of Attorney General One Ashburton Place Boston, MA 02108 Mark Stankiewicz Town Manager, Town of Plymouth 11 Lincoln Street Plymouth MA 02360 Sheila Slocum Hollis, Esq.
Town of Plymouth MA Duane Morris, LLP 505 9th Street, N.W. 1000 Washington D.C. 20004-2166 Richard R. MacDonald Town Manager, Town of Duxbury 878 Tremont Street Duxbury, MA 02332 Fire Chief & Director DEMA, Town of Duxbury 688 Tremont Street P.O. Box 2824 Duxbury, MA 02331 Terence A. Burke, Esq.
Entergy Nuclear Mail Stop M-ECH-62 Jackson, MS 39213 Katherine Tucker, Esq.
Law Clerk, Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission 11545 Rockville Pike, Mail Stop T3-E2a Rockville, MD 20852 Signed (electronically) by Mary Lampert Pilgrim Watch, pro se 148 Washington St.
Duxbury, MA 023332 Tel: 781-934-0389 Email: mary.lampert@comcast.net April 11, 2011