Attachment 6 OBDI 202 - IOLE Process DRAFT OUTLINE COMMENTS Facility: Waterford First Exam Date:

March 21, 2011 Written Exam Outline (1/14/2011)

Comment Resolution 1

  1. 1 on all #s on Outlines - Replace with test number to be associated with that K/A Fixed 2

3 4

5 Administrative JPM Outline (1/14/2011)

Comment Resolution 1 A5 - K/A 2.1.23 used on last 3 exams -

Replace Replaced 2 A8 - Needs Type Code P - Used 10/09 exam Fixed 3 A2 - used on 10/09 exam 4

5 A1 - really done in simulator?

Yes 6

A9 - really done in simulator?

Yes 7

Control Room / In-Plant System JPM Outline (1/14/2011)

Comment Resolution 1

2 P1 - used on 10/10 exam 3 JPMs previously used are randomly selected?

Yes 4 S2/S6 can be run in parallel with S4?

Yes 5 S7/S8 can be run in parallel?

Yes

OBDI 202 - IOLE Process Simulator Scenario Outline Comments (Date)

Comment Resolution 1

2 Scenario All - List Critical Tasks on D-1 Fixed 3

Scenario 1 - BOP should get reactivity credit for lowering turbine load on event 3

Fixed 4

Scenario 1 - Event 5, Charging Pump A fails to auto start - does ATC manually start this pump to receive component credit?

Yes.

5