MONTHYEARML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24018A0142024-01-17017 January 2024 Engine Systems, Inc., Report No. 10CFR21-0137, Rev. 1, 56913-EN 56913 ML24011A3182024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), October 2023 ML24011A3172024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), September 2023 ML24011A3202024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), December 2023 ML24011A3162024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), August 2023 ML24011A3192024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), November 2023 IR 05000327/20234422024-01-11011 January 2024 95001 Supplemental Inspection Report 05000327/2023442 and 05000328/2023442 and Follow-Up Assessment Letter ML24010A2132024-01-10010 January 2024 CFR 21.21 Final Report Regarding Siemens Medium Voltage Circuit Breakers ML24018A0952024-01-0404 January 2024 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0137, Rev. 0 ML24004A0332024-01-0303 January 2024 Interim Report of a Deviation or Failure to Comply Crompton Instruments Type 077 Ammeter ML24004A0402024-01-0303 January 2024 Response to NRCs November 8, 2023, Request for Additional Information - Related to Independent Spent Fuel Storage Installation CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) ML23346A1222023-12-12012 December 2023 Annual Non-Radiological Environmental Operating Report - 2023 IR 05000327/20234202023-11-28028 November 2023 Security Baseline Inspection Report 05000327/2023420 and 05000328/2023420 CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23324A4362023-11-0909 November 2023 Exam Corporate Notification Letter Aka 210-day Letter ML23307A0822023-11-0808 November 2023 Request for Additional Information August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation IR 05000327/20230032023-11-0303 November 2023 Integrated Inspection Report 05000327/2023003 and 05000328/2023003 ML23306A1592023-11-0202 November 2023 Enforcement Action EA-22-129 Inspection Readiness Notification ML23292A0792023-10-19019 October 2023 Tennessee Valley Authority - Emergency Plan Implementing Procedure Revision, Includes EPIP-5, Revision 58, General Emergency IR 05000327/20230112023-10-16016 October 2023 Triennial Fire Protection Inspection Report 05000327/2023011 and 05000328/2023011 ML23285A0882023-10-12012 October 2023 Submittal of Sequoyah Nuclear Plant, Units 1 and 2, Submittal of Updated Final Safety Analysis Report Amendment 31 ML23284A4252023-10-11011 October 2023 10 CFR 50.59 and 10 CFR 72.48 Changes, Tests, and Experiments Summary Report; Commitment Summary Report; and Update to the Fire Protection Report ML23283A2792023-10-10010 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Requirements Manual ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0462023-10-0404 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Specification Bases ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23271A1662023-09-28028 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision IR 05000327/20234032023-09-14014 September 2023 Cyber Security Inspection Report 05000327/2023403 and 05000328/2023403 (Cover Letter) ML23257A0062023-09-14014 September 2023 Enforcement Action EA-22-129 Inspection Postponement Request ML23254A2192023-09-11011 September 2023 Emergency Plan Implementing Procedure Revisions ML23254A0652023-09-0707 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000327/20230052023-08-29029 August 2023 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2023005 and 05000328/2023005 ML23233A0122023-08-17017 August 2023 Unit 1 Cycle 25 Refueling Outage - 90-Day Inservice Inspection Summary Report - Supplement ML23233A0142023-08-15015 August 2023 Discharge Monitoring Report (Dmr), July 2023 ML23215A1212023-08-0303 August 2023 301 Exam Administrative Items (2B) Normal Release ML23215A1572023-08-0303 August 2023 Enforcement Action EA-22-129 Inspection Readiness Notification CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-01-04
[Table view] Category:Code Relief or Alternative
MONTHYEARML23048A3042023-03-0808 March 2023 Tennessee Valley Authority - Request for Relief from Requirements of ASME Boiler and Pressure Vessel Code Regarding Weld Examination Coverage (EPID L-2022-LLR-0045,-0046,-0047) ML22304A1862022-12-0101 December 2022 Revised Authorization of Alternative Request RV-02 for Pressure Isolation Valve Seat Leakage ML22272A5682022-10-12012 October 2022 Authorization of Alternatives to Certain Inservice Testing Requirements in the American Society of Mechanical Engineers Operating and Maintenance Code ML22203A1122022-07-25025 July 2022 Summary of Verbal Authorization of Alternative Request RP-12 for the 1B-B Centrifugal Charging Pump CNL-22-081, Supplement to Sequoyah Nuclear Plant, Unit 1, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RP-122022-07-21021 July 2022 Supplement to Sequoyah Nuclear Plant, Unit 1, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RP-12 ML21266A3832021-10-0101 October 2021 Authorization of Alternative Request RP-10 for the 1B-B Motor Driven Auxiliary Feedwater Pump ML19227A1102019-08-26026 August 2019 Alternative Request for the Turbine Driven Auxiliary Feedwater Pumps 10-Year Interval Inservice Testing Program CNL-19-068, Response to Request for Additional Information Regarding the Sequoyah Nuclear Plant (SQN) Units 1 and 2 and Watts Bar Nuclear Plant (WBN) Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for2019-07-22022 July 2019 Response to Request for Additional Information Regarding the Sequoyah Nuclear Plant (SQN) Units 1 and 2 and Watts Bar Nuclear Plant (WBN) Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for .. ML17059B7912017-03-0202 March 2017 Sequoyah Nuclear Plant, Units 1 and 2 - Relief from the Requirements of the American Society of Mechanical Engineer OM Code (CAC Nos. MF9305 and MF9306) ML16225A6332016-09-0202 September 2016 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Sequoyah Nuclear Plant, Units 1 and 2; Watts Bar Nuclear Plant, Unit 1 and 2 - Relief Request for Use of Alternate Calibration Block Reflector Requirements 16-PDI-5 (TAC Nos. MF7754-MF7760) ML16123A1312016-05-12012 May 2016 Relief Requests RP-01, RP-02, RP-06, RP-08, and RV-01 Related to the Inservice Testing Program, Fourth 10-Year Interval (CAC Nos. MF7099 and MF7100) ML15329A1862015-12-0404 December 2015 Request for Relief PR-07 for Alternative Inservice Pump Testing at Reference Values ML1109506822011-04-0101 April 2011 American Society of Mechanical Engineers Request for Relief RP-01, Revision 1 ML0924402962009-08-28028 August 2009 American Society of Mechanical Engineers Inservice Inspection Program Relief Request 1-ISI-34 ML0708003612007-06-11011 June 2007 Request for Relief G-RR-1 Regarding Preemptive Weld Overlays on Pressurizer Nozzles ML0617907332006-07-27027 July 2006 Request for Relief from the Requirements of ASME Code ML0601000802006-02-0303 February 2006 Relief Request Response, Authorization to Extend ISI Interval for Reactor Vessel Weld Exams ML0601301942006-01-0909 January 2006 Inservice Test Pressure (Ispt) Program Update and Associated Relief Requests for Third Ten-Year Interval ML0517304872005-08-0202 August 2005 Relief, Inservice Inspection Program Relief Request PDI-4 ML0519502612005-07-0808 July 2005 American Society of Mechanical Engineers Section XI Inservice Inspection Program Relief Request to Extend the Second 10-year ISI Interval for Unit 1 Reactor Vessel Weld Examination - Request No. 1-ISI-27 ML0508104642005-04-0808 April 2005 Second 10-year Interval Inservice Inspection Program Plan Request for Relief No. ISPT-09 ML0502504152005-02-15015 February 2005 Relief, Use of ASME and Pressure Vessel (PV) Code for VT-2 ML0421504382004-10-0606 October 2004 Relief, Relief Request Re. Maximum Allowable Flaw Width When Planar Flaw Evaluation Rules May Be Applied ML0423305572004-08-17017 August 2004 8/17/04, Sequoyah, Units 1 & 2, Relief Request, Two Welds on SQN Unit 1 & 2 Seal Water Injection Filter head-to-shell Welds ML0421904402004-08-0606 August 2004 American Society of Mechanical Engineers (ASME) Section XI Inservice Pressure Test Program Relief Request (ISPT-09) ML0420201942004-07-19019 July 2004 Relief Request, Inservice Inspection of Class 1 & Class 3 Welds ML0332303472003-11-0606 November 2003 Response to NRC Request for Additional Information (RAI) Regarding ASME Section XI Inservice Inspection (ISI) Program Relief Requests 1-ISI-23, 1/2-ISI-24, and 1/2-ISI-25 ML0329302632003-10-15015 October 2003 American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, Appendix Viii, Supplement 10 - Qualification Requirements for Dissimilar Metal Piping Welds, Request for Relief PDI-3 ML0329009382003-10-0808 October 2003 Unit 1 - Change to a Commitment Associated with Request for Relief from American Society of Mechanical Engineers (ASME) Code for Replacement of ASME Code Class 3 Piping ML0317505932003-06-14014 June 2003 Request for Relief from American Society of Mechanical Engineers (ASME) Code for Replacement of ASME Code Class 3 Piping ML0314700772003-05-13013 May 2003 American Society of Mechanical Engineers (ASME) Section XI Inservice Inspection (ISI) Program - Relief Requests ML0313203202003-05-0909 May 2003 Request for Relief from American Society of Mechanical Engineers, Section XI Code Requirements for Tests Following Repair, Modification, or Replacement ML0310605452003-04-15015 April 2003 Request for Relief from American Society of Mechanical Engineers (Asme), Section XI Code Requirements - Tests Following Repair, Modification, or Replacement (IWE-5221) ML0219702792002-07-16016 July 2002 Relief Request RR-09 and RR-10 Associated with Inservice Testing Requirements for Vibration Monitoring of the Turbine Driven Auxiliary Feedwater Pumps 2023-03-08
[Table view] |
Text
Tennessee Valley Authority 1101 Market Street, LP 3R Chattanooga, Tennessee 37402-2801 R. M. Krich Vice President Nuclear Licensing April 1,2011 10 CFR 50.4 10 CFR 50.55a ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328
Subject:
American Society of Mechanical Engineers Request for Relief RP-01, Revision I
Reference:
Letter from NRC to TVA, "Sequoyah Nuclear Plant, Units 1 and 2 -
Request for Relief from the Requirements of the ASME Code (TAC Nos. MC9537, MC9538, MC9539, MC9540, MC9541, MC9542, MC9543, MC9544, MC9545, MC9546, MC9547, MC9548, MC9549, MC9550, MC9551, MC9552, MC9553, and MC9554)," dated July 27, 2006 In accordance with 10 CFR 50.55a, "Codes and Standards," the Tennessee Valley Authority (TVA) requests NRC approval of Request for Relief RP-01, Revision 1. The original version of RP-01 was authorized by the NRC in the safety evaluation issued July 27, 2006 (Reference).
The Code of Record for the current third 10-year interval is the 2001 Edition through 2003 Addenda of the American Society of Mechanical Engineers, "Code for Operation and Maintenance of Nuclear Power Plants" (OM Code).
The revision to RP-01 requests authorization to include relief from the "preservice" testing requirements of ISTB-521 0(a) in addition to relief from the "inservice" testing requirements as authorized in the original version of RP-01. The "Basis for Relief' is unchanged from the original relief request because the basis is applicable to both preservice and inservice testing.
printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 April 1, 2011 In addition to the "preservice" requirements, the revision to RP-01 corrects the OM Code reference from Section ISTB-5121(b) to Section ISTB-5221 (b). ISTB-5121 (b) is in the OM Code section for "Centrifugal Pumps (Excluding Vertical Line Shaft Pumps)," whereas the correct reference should be ISTB-5221(b) which is for "Vertical Line Shaft Pumps." The essential raw cooling water (ERCW) screen wash pumps, for which TVA is requesting this revised relief, are vertical line shaft pumps. The sections are essentially the same with only minor changes associated with the pump type.
Identification of this correction has been entered in TVA's Corrective Action Program.
The request for relief is provided in the enclosure. TVA requests approval of the proposed alternative by April 30, 2012.
There are no regulatory commitments associated with this submittal. If you have any questions about this change, please contact Rod M. Cook at (423) 751-2834.
Respectfully, R. M. Krich
Enclosure:
Request for Relief RP-01, Revision 1 cc (Enclosure):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Sequoyah Nuclear Plant
ENCLOSURE TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR PLANT, UNITS I AND 2 AMERICAN SOCIETY OF MECHANICAL ENGINEERS CODE RELIEF REQUEST REQUEST FOR RELIEF RP-0t, REVISION I
Tennessee Valley Authority Sequoyah Nuclear Plant, Units I and 2 American Society of Mechanical Engineers Code Relief Request Request for Relief RP-01, Revision I Affected Components Essential Raw Cooling Water (ERCW) Screen Wash Pumps (0-PMP-067-0470-A, O-PMP-067-0477-B, 0-PMP-067-0482-B, O-PMP-067-0487-A)
Test Requirement The American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM)
Code of Record for the Third Inservice Inspection Interval is 2001 Edition with Addenda through 2003. The third interval began on June 1, 2006, and will end on May 31, 2015.
ISTB-5210(a), "Preservice Testing" (Vertical Line Shaft Centrifugal Pumps) states that "In systems where resistance can be varied, flow rate and differential pressure shall be measured at a minimum of five points. If practicable, these points shall be from pump minimum flow to at least pump design flow. A pump curve shall be established based upon the measured points.
At least one point shall be designated as the reference point(s). Data taken at the reference point will be used to compare the results of inservice tests. A pump curve need not be established for pumps in systems where the resistance cannot be varied."
ISTB-5221 (b), "Group A Test Procedure" (Inservice Testing, Vertical Line Shaft Centrifugal Pumps), states that "The resistance of the system shall be varied until the flow rate equals the reference point. The differential pressure shall then be determined and compared to its reference value. Alternatively, the flow rate shall be varied until the differential pressure equals the reference point and the flow rate determined and compared to the reference flow rate value."
ISTB-5223(b), "Comprehensive Test Procedure" (Inservice Testing, Vertical Line Shaft Centrifugal Pumps) states that "The resistance of the system shall be varied until the flow rate equals the reference point. The differential pressure shall then be determined and compared to its reference point. Alternatively, the flow rate shall be varied until the differential pressure equals the reference point and the flow rate determined and compared to the reference flow rate value."
Test Requirement from Which Relief is Requested Relief is being requested from measuring the pump flow rate during the preservice and inservice testing of the screen wash pumps and from measuring differential pressure at five points during preservice testing and establishment of a pump curve.
E-1
Basis for Relief No in-line instrumentation exists to measure flow and the physical configuration of the pump and piping does not allow the use of portable flow measuring equipment such as ultrasonic flow meters. Piping from the discharge of the screen wash pumps is open-ended to the spray nozzles at the traveling screen and is relatively short with multiple elbows, reducers, and valves in different planes. The physical configuration of this piping system is such that no portion of the piping meets the requirements for adequate installation of a permanent flow measuring device, or the utilization of a portable flow measuring device capable of providing accurate flow rate measurements. Therefore, measured flow readings from an installed device may not be repeatable or representative of actual pump flow. Significant system modifications, such as piping rerouting and support redesign, would be required to obtain a configuration that would provide reliable flow readings.
Flow is not the critical parameter for these pumps. The nature of their operation is to ensure that sufficient pressure is maintained at the spray nozzles during flushing operations of the traveling water screens to ensure that sufficient force is exerted on the debris accumulated on the screen to remove it. This can be verified by verifying the effectiveness of the flushing operation.
Maintenance history was reviewed for nozzle plugging and it was determined that nozzle plugging is infrequent. The nozzles are inspected by Operations personnel during spray operation with corrective maintenance initiated as required.
Alternative Test The preservice, Group A, and comprehensive tests will be performed by setting the system resistance to the same point for each test with the throttle valves full open. Flow will not be measured. The remaining variable that could affect system resistance is the spray nozzles.
The condition of the spray nozzles will be inspected during each test performance with corrective actions initiated as necessary, thus providing assurance that the spray nozzle condition will not affect flow rate. With system resistance maintained constant for each test, pump degradation would be identified through changes in differential pressure. Differential pressure is calculated using inlet (based on lake level or suction pressure) and discharge pressure. The pump will be trended for degradation based on differential pressure at this point.
Vibration readings will also be taken at this reference point. The pumps will be tested in this manner for the preservice, the quarterly Group A, and the biennial comprehensive test.
Instrument accuracy and acceptance criteria for pump differential pressure and vibration will meet the requirements of Table ISTB-3500-1, "Required Instrument Accuracy," and Table ISTB-5200-1, "Vertical Line Shaft and Centrifugal Pumps Test Acceptance Criteria," respectively, for the appropriate test type.
Preservice test data for differential pressure and vibration data will be evaluated to verify if it represents acceptable pump operation and will be used as reference values for subsequent quarterly Group A and biennial comprehensive tests.
E-2
For a new ERCW screen wash pump, the bowl assembly will be tested at the vendor's facility prior to shipment to Sequoyah Nuclear Plant (SQN). This test data is adjusted to account for the pump column (in order to represent the fully assembled pump configuration). A vendor pump curve will then be developed and provided to SQN prior to pump installation.
The preservice pump test for a new ERCW screen wash pump will be performed by setting the throttle valves full open (the same as the Group A and comprehensive tests) and measuring pump differential pressure and vibration. Flow will not be measured. In addition, the condition of the screen spray nozzles will be inspected to verify that the spray covers the screen spray area and the spray force is sufficient to remove any debris present.
The measured differential pressure will be plotted on the vendor pump curve to determine the theoretical flow rate. The differential pressure and theoretical flow rate will then be evaluated against the requirements established in the ERCW screen wash pump design specification, design criteria, and system description. If the pump hydraulic data meets the design requirements with some margin to provide for future degradation and the vibration data analysis is acceptable, the pump will be considered to be operating acceptably. Visual examination of the screen wash spray nozzle performance provides additional positive verification that the pump is operating acceptably and is capable of performing its safety-related function.
Conclusion Based upon the above discussion, the alternative test provides an acceptable level of quality and safety. Authorization to implement the proposed alternative is requested in accordance with 10 CFR 50.55a(a)(3)(i).
Revision 0 of this relief request was authorized by letter from L. Raghavan, Acting Branch Chief, Plant Licensing Branch (NRC) to Karl W. Singer (TVA), dated July 27, 2006. The safety evaluation transmitted by that letter authorized the use of relief requests, including RP-01, for the third 10-year inservice inspection interval.
Precedent NRC approval has been previously granted for a similar relief request at Watts Bar Nuclear Plant in NRC letter to Mr. R. M. Krich (Vice President, Nuclear Licensing), "Watts Bar Nuclear Plant, Unit 1, Safety Evaluation of Relief Request PV-02, Revision 1, for the Second 10-Year Interval on the Inservice Testing Program (TAC No. ME4204)," ADAMS Accession No. ML102360191, dated August 30, 2010.
E-3