MONTHYEARL-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums IR 05000335/20250102024-10-21021 October 2024 Notification of St. Lucie Plant Units 1 & 2 Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000335/2025010 and 05000389/2025010 ML24227A9702024-10-18018 October 2024 Letter to Kenneth Mack Dir, License and Reg Compliance, NextEra Energy, Inc Response to Request Re Engagement Re Sub License Renewal Environmental Review - St Lucie Nuclear Plant 1 and 2 L-2024-085, Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results2024-10-15015 October 2024 Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-165, Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made2024-10-14014 October 2024 Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) ML24255A3092024-09-30030 September 2024 SLRA - Revised SE Letter L-2024-155, Subsequent License Renewal Application, Third Annual Update2024-09-27027 September 2024 Subsequent License Renewal Application, Third Annual Update L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes 05000335/LER-2024-001, Unplanned Reactor Scram2024-09-25025 September 2024 Unplanned Reactor Scram IR 05000335/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000335/2024011 and 05000389/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-138, License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles2024-09-11011 September 2024 License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles L-2024-148, Submittal of Offsite Dose Calculation Manual (Odcm), Revision 552024-09-0909 September 2024 Submittal of Offsite Dose Calculation Manual (Odcm), Revision 55 IR 05000335/20240052024-08-22022 August 2024 Updated Inspection Plan for St. Lucie, Units 1 & 2 - Report 05000335/2024005 and 05000389/2024005 L-2024-140, Cycle 28 Core Operating Limits Report2024-08-14014 August 2024 Cycle 28 Core Operating Limits Report L-2024-133, Snubber Program Plan Submittal2024-08-14014 August 2024 Snubber Program Plan Submittal L-2024-132, 2024 Population Update Analysis2024-08-13013 August 2024 2024 Population Update Analysis IR 05000335/20240022024-08-13013 August 2024 Integrated Inspection Report 05000335-2024002 and 05000389-2024002 L-2024-129, Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval2024-08-0707 August 2024 Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review 05000389/LER-2024-003, Unplanned Reactor Scram2024-08-0505 August 2024 Unplanned Reactor Scram L-2024-121, Subsequent License Renewal Commitment 30 Revision2024-07-30030 July 2024 Subsequent License Renewal Commitment 30 Revision L-2024-123, Submittal of In-Service Inspection Program Owners Activity Report (OAR-1)2024-07-29029 July 2024 Submittal of In-Service Inspection Program Owners Activity Report (OAR-1) L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan 05000389/LER-2024-002-01, Safety Injection Tank Vent Through Wall Leakage2024-07-11011 July 2024 Safety Injection Tank Vent Through Wall Leakage L-2024-110, Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake2024-07-10010 July 2024 Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-109, Schedule for Subsequent License Renewal Environmental Review2024-07-0303 July 2024 Schedule for Subsequent License Renewal Environmental Review ML24172A1562024-06-27027 June 2024 Relief Request - PSL2-I5-RR-01 Proposed Alternative to Amse Code XI Code Examination Requirements - System Leakage Test of Reactor Pressure Vessel Bottom Head and Class 1 and 2 Piping in Covered Trenches L-2024-104, Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 102024-06-26026 June 2024 Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 L-2024-097, Technical Specification Special Report2024-06-20020 June 2024 Technical Specification Special Report L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-090, Revised Steam Generator Tube Inspection Reports2024-06-0404 June 2024 Revised Steam Generator Tube Inspection Reports IR 05000335/20244012024-06-0303 June 2024 Security Baseline Inspection Report 05000335/2024401 and 05000389/2024401 ML24135A0642024-05-17017 May 2024 Correction Letter - Amendment Nos. 253 and 208 Regarding Conversion to Improved Standard Technical Specifications L-2024-075, Notification of Improved Standard Technical Specifications (ITS) Implementation2024-05-13013 May 2024 Notification of Improved Standard Technical Specifications (ITS) Implementation IR 05000335/20240012024-05-10010 May 2024 Integrated Inspection Report 05000335/2024001 and 05000389/2024001 ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-053, License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis2024-04-30030 April 2024 License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis L-2024-070, Cycle 32 Core Operating Limits Report2024-04-29029 April 2024 Cycle 32 Core Operating Limits Report L-2024-071, Cycle 27 Core Operating Limits Report2024-04-29029 April 2024 Cycle 27 Core Operating Limits Report ML24108A0632024-04-18018 April 2024 – Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection L-2024-064, Florida Power & Light Company - 10 CFR 50.46 - Emergency Core Cooling System SBLOCA 30-Day Report2024-04-17017 April 2024 Florida Power & Light Company - 10 CFR 50.46 - Emergency Core Cooling System SBLOCA 30-Day Report L-2024-056, Annual Radiological Environmental Operating Report for Calendar Year 20232024-04-17017 April 2024 Annual Radiological Environmental Operating Report for Calendar Year 2023 L-2024-054, 2023 Annual Environmental Operating Report2024-04-0909 April 2024 2023 Annual Environmental Operating Report 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24192A2302024-07-10010 July 2024 003 Radiation Safety Baseline Inspection Information Request ML24108A0632024-04-18018 April 2024 – Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24177A2512024-02-12012 February 2024 Acceptance Review for RR 7-Proposed Alternative - Extension of Inspection Interval for St. Lucie Unit 1 Reactor Pressure Vessel Welds from 10 to 20 Years ML24177A2532024-02-12012 February 2024 Request for Additional Information Relief Request RR 7, Alternative Examination of Reactor Vessel Welds for Florida Power & Light Company, St. Lucie Nuclear Plant, Unit 1 ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23226A0762023-08-14014 August 2023 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Units 1 and 2 - Adopt 10 CFR 50.69 (L-2022-LLA-0182) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23254A4022023-01-24024 January 2023 RP Inspection_2023-001_Document Request ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22325A0692022-11-18018 November 2022 RAI Set 4 ML22270A1482022-09-26026 September 2022 SLRA Second Round RAI Letter 2 - Class 1 Fatigue (Final) ML22217A0032022-08-0404 August 2022 SLRA Second Round RAI Letter 1) ML22217A0022022-08-0404 August 2022 Email from Brian Harris (NRC) to Robert Coffey (FPL) - St. Lucie SLRA Second Round RAI Letter 1) ML22193A0872022-07-11011 July 2022 Letter RAI Set 3 (Final) ML22133A0032022-05-12012 May 2022 SLRA RAIs Set 1 ML22101A2322022-05-0202 May 2022 Summary of the Environmental Remote Audit Related to the Review of the Subsequent License Renewal Application Enclosure RCIs and RAIs ML22094A1672022-04-0101 April 2022 2022 St. Lucie POV Inspection Information Request ML22075A1212022-03-16016 March 2022 Stl Problem Identification and Resolution (Pi&R) Information Request Final Report ML21350A4262021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Licensing Amendment Request Concerning Technical Specification Conversion to NUREG-1432, Revision 5 ML21119A3142021-04-28028 April 2021 Requests for Additional Information Regarding License Amendment Requests to Apply Risk Informed Completion Times (RICT) for the 120-Volt AC (EPID L-2020-LLA-0283) (Email) ML21063A3192021-03-0404 March 2021 Request for Additional Information Regarding Relief Request RR 15 - Extension of RPV Welds from 10 to 20 Years ML20092G3442020-04-0101 April 2020 RAIs for LAR to Revise Technical Specifications 6.8.4.o, Reactor Coolant Pump Flywheel Inspection Program ML20094G2022020-03-30030 March 2020 Request for Additional Information Regarding License Amendment Request to Adopt EAL Schemes Pursuant to NEI 99-01 (L-2019-LLA-0210) ML19225D3152019-08-13013 August 2019 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Relocate the MOV Thermal Overload Bypass Devices (L-2019-LLA-0106) ML19218A2742019-08-0606 August 2019 Notification of Inspection and Request for Information ML19193A1982019-07-12012 July 2019 Emailed St. Lucie Heat Sink RFI ML19192A1372019-07-11011 July 2019 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Unit No. 2, Fall 2018 Refueling Outage Steam Generator Tube Inspection Report ML19192A1352019-06-25025 June 2019 NRR E-mail Capture - Draft Request for Additional Information - St. Lucie Plant, Unit No. 2, Fall 2018 Refueling Outage Steam Generator Tube Inspection Report ML19151A8312019-05-31031 May 2019 NRR E-mail Capture - St. Lucie Plant, Unit Nos. 1 and 2, Request for Additional Information Regarding Emergency Diesel Generator Surveillance Requirement Amendment Request ML19151A5092019-05-21021 May 2019 NRR E-mail Capture - Draft Request for Additional Information - St. Lucie Plant, Unit Nos. 1 and 2 Emergency Diesel Generator Surveillance Requirement Amendment Request ML19109A1392019-04-18018 April 2019 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding the License Amendment Request Pertaining to the Iodine Removal System ML19053A2242019-02-0101 February 2019 NRR E-mail Capture - St. Lucie Plant Unit No. 1 - Draft Request for Additional Information Related to Relief Request 6 Regarding the Refueling Water Tank Bottom Liner ML18296A2052018-10-22022 October 2018 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181) L-2018-018, St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181)2018-10-22022 October 2018 St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181) ML18197A4112018-08-0101 August 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Reduce the Number of Control Element Assemblies ML18019A0712018-01-18018 January 2018 NRR E-mail Capture - Request for Additional Information - St. Lucie Inop AFW Steam Supply LAR (L-2017-LLA-0296) ML17331B1532017-11-27027 November 2017 NRR E-mail Capture - Request for Additional Information - St. Lucie IST Relief Request #5 - PR-01 (L-2017-LLR-0113) ML17277A3692017-10-0404 October 2017 NRR E-mail Capture - Request for Additional Information - St. Lucie Rict LAR - MF5372/MF5373 ML17152A1842017-06-0101 June 2017 Request for Additional Information - RPS Rate of Change and LCO Change LAR (CACs MF9119 9120) ML16356A1432016-12-20020 December 2016 Notification of Inspection and Request for Information ML16326A0092016-11-18018 November 2016 NRR E-mail Capture - Request for Additional Information Re. Nextera/Fpl LAR to Adopt TSTF-545 - CACs MF8203, MF8204, MF8208, and MF8209 ML16308A3232016-11-0303 November 2016 NRR E-mail Capture - Request for Additional Information - St. Lucie EDG Day Tank LAR - MF8006 ML16292A8212016-10-14014 October 2016 Emergency Preparedness Inspection and Request for Information ML17003A0452016-10-11011 October 2016 NRR E-mail Capture - (External_Sender) FW: St. Lucie Response to RAI on SL2-22 SG Tube Inspection Report (MF7604) ML16244A2602016-08-26026 August 2016 Notification of Inspection and Request for Information ML16155A3502016-06-0303 June 2016 Notification of Inspection and Request for Information ML16089A0052016-03-28028 March 2016 NRR E-mail Capture - Request for Additional Information - St. Lucie Srxb Mtc Surv - MF7269 & MF7270 ML16077A1062016-03-17017 March 2016 NRR E-mail Capture - Request for Additional Information - St Lucie Vacuum Gothic LAR - MF6980/MF6981 ML16068A2612016-03-0808 March 2016 NRR E-mail Capture - Request for Additional Information - St Lucie TSTF-422 - MF6683/MF6684 2024-07-12
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 30, 2011 Mr. Mano Nazar Executive Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420
SUBJECT:
ST. LUCIE PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING RELIEF REQUEST PR-9 (TAC NOS. ME5190 AND ME5191)
Dear Mr. Nazar:
By letter dated September 14, 2010, Florida Power & Light Company submitted Relief Request PR-9 for St. Lucie Unit Nos. 1 and 2. The relief request proposes an alternative to biennial Comprehensive Pump Testing of Group A pumps.
The NRC staff is reviewing your submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). It is requested that your RAI response be provided within 30 days of the date of this letter.
Sincerely, Tracy J. Orf, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-335 and 50-389
Enclosure:
Request for Additional Information cc w/enclosure: Distribution via Listserv
REQUEST FOR ADDITIONAL INFORMATION (RAn REGARDING LICENSE AMENDMENT REQUEST FOR RELIEF REQUEST PR-9 ST. LUCIE PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-335 AND 50-389
Reference:
Letter from Eric S. Katzman of Florida Power & Light Company to NRC, "Fourth Ten-Year Interval Relief Request PR-9," dated September 14.2010.
RAI CPTB-1:
Please confirm that when using the proposed modified Group A test, vibration tests will be performed, and the acceptance criteria for the vibration tests will be the same as for Group A tests shown in Table IST8-5200-1.
ENCLOSURE
March 30, 2011 Mr. Mano Nazar Executive Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420 SUBJECT ST. LUCIE PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING RELIEF REQUEST PR-9 (TAC NOS. ME5190 AND ME5191)
Dear Mr. Nazar:
By letter dated September 14, 2010, Florida Power & Light Company submitted Relief Request PR-9 for St. Lucie Unit Nos. 1 and 2. The relief request proposes an alternative to biennial Comprehensive Pump Testing of Group A pumps.
The NRC staff is reviewing your submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). It is requested that your RAI response be provided within 30 days of the date of this letter.
Sincerely, IRA!
Tracy J. Ort, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-335 and 50-389
Enclosure:
Request for Additional Information cc w/enclosure: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrLABClayton RidsRgn2MailCenter LPL2-2 r/f RidsNrrDciCptb RWolfgang. NRR RidsN rrDorlLpl2-2 RidsAcrsAcnw_MailCTR RidsN rrPMStLucie RidsOgcRp ADAMS A ccesslon. N 0.: ML110871340 *Bsymemo OFFICE LPLlI*2/PM LPLlI-21LA CPTB/BC* LPLII-21BC LPLlI-21PM NAME TOrf BClayton AMcMurtray DBroaddus TOrf DATE 03/29/11 03/28/11 03/15/11 03/29/11 03/30/11 OFFICIAL AGENCY RECORD