RS-11-048, Additional Information Related to Byron Station Unit 1, Inservice Inspection Relief Request I3R-19: Alternative Requirements for the Repair of Reactor Vessel Head Penetrations

From kanterella
(Redirected from ML110870236)
Jump to navigation Jump to search

Additional Information Related to Byron Station Unit 1, Inservice Inspection Relief Request I3R-19: Alternative Requirements for the Repair of Reactor Vessel Head Penetrations
ML110870236
Person / Time
Site: Byron Constellation icon.png
Issue date: 03/25/2011
From: Benyak D
Exelon Generation Co, Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RS-11-048, TAC ME5877
Download: ML110870236 (7)


Text

RS-1 1-048 10 CFR 50.55a March 25, 2011 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Byron Station Unit 1 Facility Operating License No. NPF-37 NRC Docket No. STN 50-454

Subject:

Additional Information Related to Byron Station Unit 1, Inservice Inspection Relief Request 13R- 1 9: Alternative Requirements for the Repair of Reactor Vessel Head Penetrations

References:

(1) Letter from J. Hansen (Exelon) to U. S. NRC, "Byron Station Unit 1 Inservice Inspection Relief Request 13R - 19: Alternative Requirements for the Repair of Reactor Vessel Head Penetrations," dated March 24, 2011 (2) Email from N. DiFrancesco (U. S. NRC) to R. McIntosh (Exelon), "Byron Station, Unit No. 1 - Request for Additional Information re: Relief Request 13R-19 (TAC No. ME5877)," dated March 25, 2011 In Reference 1, in accordance with 10 CFR 50.55a, "Codes and standards," paragraph (a)(3)(i),

Exelon Generation Company, LLC (EGC), submitted the Relief Request 13R-1 9 from the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components," on the basis that the proposed alternatives would provide an acceptable level of quality and safety.

Specifically, Reference 1 proposed to perform an alternative repair technique using an embedding weld overlay methodology on the reactor Vessel Head Penetration (VHP) housings and J-groove welds of Byron Station, Unit 1.

During the current Byron Station, Unit 1 Spring 2011 Refueling Outage B1 R17, EGC performed volumetric examinations of the VHPs in accordance with 10 CFR 50.55a(g)(6)(ii)(D), which specifies the use of Code Case N-729 - 1, with conditions. Examination of the VHPs is on going, however, results for the examination of VHP nozzles 64 and 76 did not meet the applicable acceptance criteria; and therefore, EGC is making preparations for a repair. A teleconference was held between EGC and the NRC on March 25, 2011, to discuss a Request for Additional Information (RAI) from the NRC to complete its review of the proposal.

The EGC request for an expedited verbal authorization from the NRC by March 28, 2011, is revised by this letter to support repair activities specific to the VHP nozzles 64 and 76. contains the information requested by the NRC.

March 25, 2011 U. S. Nuclear Regulatory Commission Page 2 contains one new regulatory commitment in this submittal. If you have any questions about this letter, please contact Mr. Richard W. McIntosh at (630) 657-2816.

Respectfully, Darin M. Benyak Director, Licensing and Regulatory Affairs Attachments: 1. Response to Request for Additional Information on Alternative Requirements for the Repair of Reactor Vessel Head Penetrations

2. Summary of Regulatory Commitments

ATTACHMENT 1 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ON ALTERNATIVE REQUIREMENTS FOR THE REPAIR OF REACTOR VESSEL HEAD PENETRATIONS (Page 1 of 4)

NRC QUESTION RAI-1:

NRC staff notes that the licensee requests expedited verbal relief by 1 PM Central Standard Time on March 28, 2011. Staff notes that expedited review and verbal authorization would be difficult for the generic application of the licenses' submittal within that time frame. Therefore, staff requests licensee reconsider the scope of this relief request under Section 1.0 "ASME Code Component(s) Affected" to the items needed for repair this outage, in order to meet the licensee's requested date of verbal authorization.

RESPONSE TO RAI-1:

The Exelon Generation Company, LLC (EGC) request for an expedited verbal authorization from the NRC by March 28, 2011, is revised by this letter to support repair activities specific to reactor Vessel Head Penetration (VHP) nozzles 64 and 76 only. EGC understands that NRC review of the generic application of the relief request will continue, but not on the expedited schedule.

NRC QUESTION RAI-2:

In Reference 2 of the submittal, the NRC requested the following, "The NRC must be notified of changes in flaw(s) or finding new flaw(s) in the j-groove weld beneath a seal weld repair or in the seal weld repair. " In order to add clarity to this request the NRC staff requests that the licensee commit to the following statement; The licensee will notify NRC staff of the Division of Component Integrity or its successor of changes in indication(s) or findings of new indication(s) in the penetration nozzle or J-groove weld beneath a seal weld repair, or new linear indications in the seal weld repair, prior to commencing repair activities.

NRC staff requests this commitment as a finding of these types of indications may invalidate the embedded flaw repair technique as an effective repair for the penetration nozzle in question. Timely notification of NRC staff of ISI indications will allow clear communications to assist NRC staff in determination of the effectiveness of the repair due to the indication in question.

RESPONSE TO RAI-2:

Exelon Generation Company, LLC (EGC) will notify NRC staff of the Division of Component Integrity or its successor of changes in indication(s) or findings of new indication(s) in the penetration nozzle or J-groove weld beneath a seal weld repair, or new linear indications in the seal weld repair, prior to commencing repair activities.

This Regulatory Commitment is on Attachment 2, committed for Byron Unit 1 refueling outages, beginning with B1 R18.

ATTACHMENT 1 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ON ALTERNATIVE REQUIREMENTS FOR THE REPAIR OF REACTOR VESSEL HEAD PENETRATIONS (Page 2 of 4)

NRC QUESTION RAI-3:

In Section 5.0 of the submittal, Step 1 states that an unacceptable axial or circumferential flaw in a tube below a J-groove attachment weld will be sealed off with an Alloy 52 or 52M weldment, with no additional detail as to the scope of the weldment. WCAP - 15987-P Rev.

2, Reference 1 of the submittal, states in Section 2.2.3, for axial cracks on the penetration tube OD below the j-weld, that the overlay begins %" beyond the Alloy 600/stainless steel interface at the outer periphery of the J -weld and extends down the outer surface of the penetration tube to a point %" beyond the flaw indication. Section 2.2.4, for circumferential cracks in the penetration tube, the scope of the weldment is not specific other than isolation of the flaw. In order to clarify the licensee's implementation of requirements, provide the following; a) State the generic scope of the weldment that will be used to repair an OD flaw in the nozzle below the J-groove weld.

b) State the scope of the weldment being used to repair reactor pressure vessel upper head penetration numbers 64 and 76.

c) In regards to the Table of Item 3 of Section 5.0, "Conditions and Limitations" of Reference 2 of the submittal, answer the following;

1. How will each of the four(4) indications be characterized for, I. "Repair Location, "

ii. "Flaw Orientation, " and iii. "Repair NDE"

2. Will Note 3 be implemented for "ISI NDE of the repair" for penetration numbers 64 and 76?

RESPONSE TO RAI-3:

a) EGC will provide a supplemental response to this letter to discuss generic scope of the proposed weldment.

b) The stainless steel head cladding will have three beads of 309L stainless steel buffer installed 3600 (degrees) around the interface of the clad and the J-Groove weld metal at Penetrations 64 and 76. The J-groove weld will have three layers of Alloy 52/52M deposited 3600 around the nozzle over and out to the stainless steel buffer.

The nozzle tube will have two layers of Alloy 52/52M deposited 360° around the nozzle and tied into the J-groove overlay. On Penetration 76, the nozzle tube will have the overlay extend down to the lowest possible location that will allow reinstallation of the funnel. On Penetration 64, the nozzle tube will be overlayed to the bottom of the nozzle (i.e., no funnel is installed).

ATTACHMENT 1 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ON ALTERNATIVE REQUIREMENTS FOR THE REPAIR OF REACTOR VESSEL HEAD PENETRATIONS (Page 3 of 4) c.1(i) Repair Location The following recordable indications were discovered in the reactor head penetration nozzles 64 and 76; 64-1 approximately 1.3 inches counterclockwise from the 180 degree mark 64-2 approximately 0.9 inches counterclockwise from the 180 degree mark 76-1 approximately 1.0 inches clockwise from the 180 degree mark 76-2 between 0 inches and 1.2 inches counterclockwise from the 180 degree mark NOTE: 0 degrees is located at the downhill side of the penetration where the nozzle extension is shortest.

c.1(ii) Flaw Orientation:

The two indications in Penetration 64 are axial flaws on the uphill side. Indication 1 in Penetration 76 is an axial flaw and indication 2 is a circumferential flaw. Both flaws in Penetration 76 are on the uphill side.

The recorded distances of the flaws to the toe of the weld are:

Ultrasonic Testing Liquid Penetrant (PT)

(UT) measured measured distance from Flaw: distance from Toe of Weld:

Toe of Weld:

(inches) .

(inches) 64-1 0.40 0.40 64-2 NA 0.30 76-1 0.08 0.10 76-2 0.16 0.10 c.1(iii) All repair Non-Destructive Examination (NDE) will be a UT of the nozzle from the Inside Diameter (ID) and a PT Examination of the overlayed surface. In addition, response to Item c.2 below is applicable.

c.2 In accordance with Note 3 of the NRC acceptance for WCAP-1 5987-P-Revision 2, (See Reference 4, TAC No. MB8997) the final NDE performed on Penetrations 64 and 76 will include Performance Demonstration Initiative (PDI) UT of the nozzle and PT of the overlayed area. This will constitute 100% of the required examinations for the final NDE on the repair during B1 R17.

ATTACHMENT 1 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ON ALTERNATIVE REQUIREMENTS FOR THE REPAIR OF REACTOR VESSEL HEAD PENETRATIONS (Page 4 of 4)

For the ISI NDE of the repair for Penetrations 64 and 76 starting with refueling outage B1 R18, Note 3 does not apply since the repair location is in the "VHP Nozzle OD below J-groove weld." Therefore, ISI NDE of the repair for Penetrations 64 and 76 will be performed in accordance with Code Case N-729-1, as amended by 10 CFR 50.55a(g)(6)(ii)(D).

REFERENCES:

(1) Letter from J. Hansen (Exelon) to U. S. NRC, "Byron Station Unit 1 Inservice Inspection Relief Request 13R-1 9: Alternative Requirements for the Repair of Reactor Vessel Head Penetrations," dated March 24, 2011 (2) Email from N. DiFrancesco (U. S. NRC) to R. McIntosh (Exelon), "Byron Station, Unit No. 1 - Request for Additional Information re: Relief Request 13R-19 (TAC No.

ME5877)," dated March 25, 2011 (3) Westinghouse WCAP-15987, Revision 2-A, "Technical Basis for the Embedded Flaw Process for Repair of Reactor Vessel Head Penetrations," December 2003 (4) Letter from H. N. Berkow (U. S. NRC) to H. A. Sepp (Westinghouse Electric Company), "Acceptance for Referencing - Topical Report WCAP-15987-P, Revision 2, 'Technical Basis for the Embedded Flaw Process for Repair of Reactor Vessel Head Penetration,' (TAC NO. MB8997)," dated July 3, 2003 (5) Westinghouse WCAP-1 6401 -P, Revision 0, "Technical Basis for Repair Options for Reactor Vessel Head Penetration Nozzles and Attachment Welds: Byron and Braidwood Units 1 and 2" (6) American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-729-1, "Alternative Examination Requirements for PWR Reactor Vessel Upper Heads With Nozzles Having Pressure-Retaining Partial-Penetration WeldsSection XI, Division 1"

ATTACHMENT 2

SUMMARY

OF REGULATORY COMMITMENTS (Page 1 of 1)

The following table identifies commitments made in this document. Any other actions discussed in the submittal represent intended or planned actions. They are described to the NRC for the NRC's information and are not regulatory commitments.

COMMITTED COMMITMENT TYPE COMMITMENT DATE OR "OUTAGE" ONE-TIME ACTION Programmatic (Yes/No) (Yes/No)

Exelon Generation Company, LLC (EGC) will notify NRC staff of the Division of Component Integrity or its successor of changes in indication(s) or findings of new Byron Unit 1 indication(s) in the penetration refueling outages, nozzle or J-groove weld beneath a No Yes beginning with seal weld repair, or new linear B1 R18.

indications in the seal weld repair, prior to commencing repair activities.