Summary of Telephone Conference Call Held on February 22, 2011, Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc. Regarding Progress on National Fire Protection Association (NFPA) Standard 805 Transition Activities
ML110800417
Person / Time
Site: Palisades Entergy icon.png
Issue date: 03/23/2011
From: Mahesh Chawla
Plant Licensing Branch III
To:
Office of Nuclear Reactor Regulation
chawla M
References
Download: ML110800417 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 23, 2011 LICENSEE: Entergy Operations, Inc. (ENO)

FACILITIES: Palisades Nuclear Plant (PNP)

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 22,2011, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The enclosure provides the status of each task and shows several tasks as complete. Some of the task completion dates were pushed out due to rearrangement of the priorities. However, the licensee still shows the target date for Palisades NFPA 805 project completion as May 27,2011. The licensee will be bringing additional resources as necessary to support this date and will also incorporate comments from independent Probabilistic Risk Assessment peer reviews and any lessons learned from the Oconee Safety Evaluation Report.

Background

On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.

~14U-Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via ListServ

02-22-11 Palisades NFPA 805 Project Milestones Milestone NEI Task No. Title Status Start Oate Date Transition of Nuclear Safety Performance Criteria (NEI 04 ask 1: Complete 02 Table B-2)

Fundamental Fire Protection Program & Design Elements See ask 2: 04/29/11 (NEI 04-02 Table B-1) Comments Radioactive Release Transition ask 3:

(NEI 04-02 Table G-l)

- Complete -

Nuclear Safety Analysis Transition See Task 4:

NEI 04-02 Table B-3) 05/03/11 Comments -

See ST 4.1.1 Off-Site Power Cable Selection and Analysis 02116111 Comments ST 4.1.2 Other Power Cable Selection and Analysis - Complete -

ST 4.1.3 Subsequent Cablellnstrument Identification & Analysis - Complete -

ST 4.1.4 ~e Issues from the FPRA Peer Review 03/29/11 On Track Non-Power Operational Modes Transition See Task 5: 04/29/11 NEI 04-02 Table F-l) Comments Task 6: Internal Events PRA Complete ST 6.2.1 Prepare LERF Model - Complete ST 6.2.2 Update Flooding Analysis Complete -

ST6.3 Thermal Hydraulic Analysis for MSO/H RA Complete ST 6.4 Internal Events PRA Peer Review - Complete See Task 7: Fire PRA 05118/11 Comments ST 7.6.4 R3 Internal Events Model - Complete -

ST7.7 Quantification Risk Screening Complete ST7.8 Scoping for Fire Modeling - Complete -

ST 7.9/10 Circuit Failure Mode Likelihood Analysis Complete -

See ST7.12 Post Fire HRA 04/01/11 Comments ST 7.13 Seismic Fire Interaction Assessment - Complete See ST 7.14 ,Fire Risk Quantification 05/18/11 Comments -

See ST 7.15 Uncertainty and Sensitivity Analysis 05/18/11 Comments ST 7.17.4 In-Process Fire PRA Peer Review - Complete -

See ST 7.17.5 Final Fire PRA Peer Review 04/25/01 Comments See Task 8: NFPA 805 Fire Risk 1 Change Evaluations 04/29/11 Comments - I See ST 8.1 Fire Risk 1 Change Evaluations 04/29111 Comments See ST 8.2 Non-Compliance Risk Evaluations 04/29/11 02/24/11 Comments

  • Task 10: Transition Report 05/09/11 See Comments - I See Task 11: License Amendment Request (LAR) 05/27/11 Comments CR -PLP-2010 App. R Non-Compliance associated with a potential loss of 10/01/11 New 10/01/10 04255 SR 2400 VAC power.

Comments:

Task 2 - Priorities were rearranged resulting in this task complelion pushing out.

Task 4 - Priorities were rearranged resulting in this task completion pushing out.

Task 5 - Rearranged priorities resulling in this lask completion date pushing out.

Task 7 - Subtask 7.12 caused this overall task to push oul.

Task 7.12 - Rearranged priorities resulting in this task completion date pushing out.

Tasks 7.14 & 7.15 - Completion extended due 10 extension of Subtasks 7.12.

Task 7.17.5 - Rnal Fire PRA Peer Review moved based on personnel availability.

Tasks 8, 8.1, & 8.2 - Rearranged priorilies resulted in these tasks pushing out.

Tasks 10 & 11 - Predecessor tasks pUshing out causing these tasks to push out.

E:\Palisades\PlPIEn!orcement ExtensionlNRC Conf callsWilestone Itrs12011INRC Milestones 02-22-11.>Os Enclosure 1

TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.

LIST OF PARTICIPANTS FEBRUARY 22, 2011 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)

Mahesh Chawla Project Manaaer HEADQUARTERS Alex Klein Branch Chief Harrv Barrett Senior Fire Protection Enaineer ENTERGY Jim Miksa Program Engineering Manager Chad Main Project Manager Brian Brogan Fuels and Analysis Engineer Tom Swiecicki Fire Protection Engineer Amy Hazelhoff Contract Licensing Engineer Roger Stobert Contract Project Manager Jim Kuemin Licensing Engineer Enclosure 2

ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.

Mahesh Chawla, Project Manager IRAJ Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via Listserv Distribution:

PUBLIC LPL3-1 rtf RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource RidsNrrLABTully Paul Lain, NRR HBarrett, NRR RidsAcrsAcnw_MailCtr Resource RidsOgcRp Resource JEllegood, Rill DMerzke, EDO R-1I1 CSteger, NRR ADAMS Accession No.: ML110800417 OFFICE LPL3-1/LA DRAlAFPB/BC PL3-1/BC NAME BTully AKlein RPascarelli DATE 03/22/11 03/23/11 03/23/11