Letter Sequence RAI |
---|
|
|
MONTHYEARML1016803802010-06-17017 June 2010 License Amendment Request, Technical Specification Change to Extend the Type a Test Frequency to 15 Years Project stage: Other ML1017601262010-06-25025 June 2010 Acceptance Review Email Technical Specification Change to Extend Type a Test Frequency to 15 Years Project stage: Acceptance Review ML1032103022010-11-17017 November 2010 Request for Additional Information Email, License Amendment Request, Revise Technical Specification 6.5.16, Containment Leakage Rate Testing Program, to Extend Type a Test Frequency to 15 Years Project stage: RAI ML1032202362010-11-18018 November 2010 Request for Additional Information, Email, License Amendment Request, Revise Technical Specification 6.5.16, Containment Leakage Rate Testing Program, to Extend Type a Test Frequency to 15 Years - Revision 1 Project stage: RAI 2CAN011102, Response to the Request for Additional Information Regarding License Amendment Request Technical Specification Change to Extend Type a Test Frequency to 15 Years2011-01-17017 January 2011 Response to the Request for Additional Information Regarding License Amendment Request Technical Specification Change to Extend Type a Test Frequency to 15 Years Project stage: Request 2CAN011104, Response to the Request for Clarification Regarding License Amendment Request Technical Specification Change to Extend the Type a Test Frequency to 15 Years2011-01-20020 January 2011 Response to the Request for Clarification Regarding License Amendment Request Technical Specification Change to Extend the Type a Test Frequency to 15 Years Project stage: Request 2CAN011109, Response to Request for Additional Clarifications Regarding License Amendment Request Technical Specification Change to Extend Type a Test Frequency to 15 Years2011-01-31031 January 2011 Response to Request for Additional Clarifications Regarding License Amendment Request Technical Specification Change to Extend Type a Test Frequency to 15 Years Project stage: Request ML1104606762011-02-15015 February 2011 Request for Additional Information Email, Round 2, License Amendment Request, Revise Technical Specification 6.5.16, Containment Leakage Rate Testing Program, to Extend Type a Test Frequency to 15 Years Project stage: RAI 2CAN031101, Response to the Request for Additional Information Regarding License Amendment Request Technical Specification Change to Extend the Type a Test Frequency to 15 Years2011-03-0707 March 2011 Response to the Request for Additional Information Regarding License Amendment Request Technical Specification Change to Extend the Type a Test Frequency to 15 Years Project stage: Request ML1108000342011-04-0707 April 2011 Issuance of Amendment No. 292 to Revise Technical Specification 6.5.16, Containment Leakage Rate Testing Program, to Extend Type a Test Frequency to 15 Years Project stage: Approval 2011-01-17
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24296A0652024-10-22022 October 2024 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Verbal Authorization of Relief Request for the Proposed Alternative ANO2-RR-24-001 ML24227A0072024-08-13013 August 2024 NRR E-mail Capture - LIC-109 Acceptance - ANO 2 - Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02) - EPID L-2024-LLR-0048 ML24218A0652024-08-0202 August 2024 NRR E-mail Capture - LIC-109 Acceptance Review - Arkansas Nuclear One, Unit 1 - License Amendment Request - Request for Review and Approval Changes to SAR and to a Confirmatory Order - Pzr Htr Emergency Power Supply - EPID L-2024-LLA-0092 ML24180A0022024-06-26026 June 2024 NRR E-mail Capture - LIC-109 Acceptance - ANO 1 and 2 - Proposed Alternatives for Examinations of SG Pressure Retaining Welds and Full Penetrations Nozzles - EPID L-2024-LLR-0038 ML24149A3672024-05-28028 May 2024 August 2024 Emergency Preparedness Exercise Inspection - Request for Information ML24117A0262024-04-26026 April 2024 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Revise Typographical Errors in Technical Specifications ML24088A0082024-03-27027 March 2024 NRR E-mail Capture - ANO-2 -- TSTF-505 Post-Audit Final RAI (L-2023-LLA-0052) ML23269A0232023-09-22022 September 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - TSTF-505 Audit Questions ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23194A1752023-07-13013 July 2023 NRR E-mail Capture - ANO-1 - Acceptance Review of Alternative Request ANO1-ISI-037 ML23187A0432023-07-0303 July 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Agenda ML23166A0132023-06-14014 June 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Questions ML23130A2752023-05-10010 May 2023 NRR E-mail Capture - ANO Unit 2- Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML23118A0692023-04-28028 April 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Modify ANO-1 TS 3.3.1, Reactor Protection System Instrumentation (L-2023-LLA-0048) ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23039A0872023-02-0808 February 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Acceptance Review of Relief Request ANO2-RR-23-001, Half-Nozzle Repair of RVCH Penetration 46 (L-2023-LLR-0000) ML23026A1322023-01-26026 January 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML22354A0122022-12-19019 December 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Acceptance Review of Request for Alternative ANO-CISI-002 Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (L-2022-LLR-0080) ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22341A1202022-12-0707 December 2022 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation (L-2022-LLA-0161) ML22273A0982022-09-30030 September 2022 NRR E-mail Capture - ANO Units 1 and 2 - Acceptance of Requested Licensing Action Emergency Plan Staffing Requirements ML22265A2012022-09-22022 September 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-036 ML22188A1782022-07-0707 July 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-035 ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22081A3902022-03-22022 March 2022 NRR E-mail Capture - ANO-2 - Acceptance Review of Relief Requests ANO2-ISI-023, -024, -025, -026, -027, and -028 (Epids: L-2022-LLR-022, -023, -024, -025, -026, and -027) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML22020A0742022-01-13013 January 2022 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21314A1212021-11-0909 November 2021 Verbal Authorization of Relief Request ANO2-RR-21-002 ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21287A1692021-10-13013 October 2021 Record of 10-13-21 Verbal Authorization of ANO2-R&R-012 (L-2021-LLR-0082) ML21298A1562021-10-11011 October 2021 NRR E-mail Capture - ANO-2 Final RAI Relief Request ANO2-R&R-012 Concerning Rv Closure Head Penetration 46 ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21238A3742021-08-23023 August 2021 RFI Email - Cyber PI&R Inspection (ANO) ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21202A1662021-07-20020 July 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21201A0062021-07-19019 July 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 ML21179A0052021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21179A0042021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping 2024-08-02
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information ML24088A0082024-03-27027 March 2024 NRR E-mail Capture - ANO-2 -- TSTF-505 Post-Audit Final RAI (L-2023-LLA-0052) ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23019A0672023-01-19019 January 2023 Inservice Inspection Request for Information ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22213A1662022-08-0101 August 2022 Information Request, Security IR 2022401 ML22208A0542022-07-26026 July 2022 Request for Information ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22159A3242022-06-0909 June 2022 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000313/2022003 and 05000368/2022003) and Request for Information ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21236A3222021-09-19019 September 2021 Request for Information ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21204A0842021-07-28028 July 2021 ANO Phase 4 2021013 RFI Gap ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 0CAN042105, Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description2021-04-30030 April 2021 Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping ML21105A0122021-04-0909 April 2021 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Adopt a Safety Function Determination Program ML21071A2172021-03-10010 March 2021 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Proposed Change to Quality Assurance Program Manual ML21026A2682021-01-26026 January 2021 Request for Information ML21022A0842021-01-22022 January 2021 Request for Additional Information - Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of Emergency Cooling Pond Supply Piping - Arkansas Nuclear One,Units 1 and 2 -Entergy Operations, Inc. NON-PROPRIETARY Redacted ML21019A5142021-01-14014 January 2021 March 2021 Emergency Preparedness Exercise Inspection - Request for Information ML20324A6412020-11-19019 November 2020 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-034 ML20316A0102020-11-0202 November 2020 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Concerning Relief Request EN-20-RR-01 ML20262H0752020-09-17017 September 2020 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20260H4762020-09-0909 September 2020 NRR E-mail Capture - ANO-1 Final RAI License Amendment Request to Revise Lov Relay Allowable Values ML20154K7622020-06-0101 June 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 ML20065H7992020-03-0606 March 2020 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Revise Loss of Voltage Relay Allowable Values ML20055E9092020-02-24024 February 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Revise Control Element Assembly Drop Time ML20036D3092020-02-0505 February 2020 NRR E-mail Capture - ANO-2 - Final RAI Alternative Request VRR-ANO2-2019-1 ML20013C7472020-01-10010 January 2020 NRR E-mail Capture - ANO-1 and 2 -- Final RAI #2 LAR to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19316A0242019-11-0707 November 2019 NRR E-mail Capture - ANO-1 - - Final RAI Concerning Relief Request ANO1-ISI-033 (L-2019-LLR-0100) ML19280A0402019-10-0707 October 2019 NRR E-mail Capture - ANO-1 and 2 - Final RAI #1 License Amendment Request to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19339F5902019-09-23023 September 2019 Request for Information: Arkansas Nuclear One, IR 05000313/2019-004 Occupational Radiation Safety Inspection ML19281E0032019-08-0505 August 2019 ANO 2019 PIR Request for Information ML19203A0122019-07-16016 July 2019 Request for Information - Inservice Inspection Activities (NRC Inspection Report 05000313/2019004) ML19106A4322019-04-16016 April 2019 NRR E-mail Capture - ANO-2 Final RAI Re LAR to Add TS Actions to Address Inoperability of the Containment Building Sump ML19058A8332019-02-27027 February 2019 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-032 2024-05-22
[Table view] |
Text
Burkhardt, Janet From: Kalyanam, Kaly Sent: Tuesday, February 15, 2011 5:02 PM To: BICE, DAVID B; CLARK, ROBERT W Cc: Lent, Susan; Burkhardt, Janet
Subject:
RAI on the LAR for Revision of TS 6.5.16 (ME4090)
I have changed the high-lighted portion to Arkansas Nuclear One, Unit 2. It was Unit 1 before.
Thanks Kaly The SUNSI information as follows:
Plant: Arkansas Nuclear One, Unit 2 Docket No.: 50/368
Subject:
RAI on the LAR for Revision of TS 6.5.16 TAC Nos.: ME4090 SUNSI Review Done: Yes. Publicly Available, Normal Release, Non-sensitive, From: N. Kalyanam To: D. Bice/ R. Clark Mr. Bice, By letter dated June 17, 2010, Entergy Operations, Inc (Entergy) submitted License Amendment Request on TS Change to extend Type A test frequency to 15 yrs.
The NRC staff has determined that additional information, as detailed below, is needed to complete the review.
We would appreciate a quick response to this RAI in order to meet Entergy need date.
Thanks Kaly N. Kalyanam REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST FOR REVISION OF TS 6.5.16 FOR ADOPTION OF NEI 94-01, REVISION 2-A, 1
AS IMPLEMENTING DOCUMENTFOR 10 CFR 50 APPENDIX J, OPTION B, LEAKAGE TESTING PROGRAM, ARKANSAS NUCLEAR ONE, UNIT 2 DOCKET NO. 50-368 (TAC NO. ME4090)
RAI-1
Condition 2 in the Nuclear Regulatory Commission (NRC) safety evaluation report (SER) for topical report (TR)
NEI 94-01 Revision 2-A states that The licensee submits a schedule of containment inspections to be performed prior to and between Type A tests. (Refer to NRC SER Section 3.1.1.3). In addition, Section 9.2.3.2 of NEI 94-01, Revision 2-A, Industry Guideline for Implementing Performance-Based Option of 10 CFR Part 50, Appendix J, states that in order to provide continuing supplemental means of identifying potential containment degradation, three general visual examinations of accessible containment surfaces (exterior and interior) must be performed between Type A tests and one visual examination prior to a Type A test, if the interval is extended to 15 years.
The purpose of the condition is for the licensee to provide an approximate schedule of inspections of containment surfaces (concrete and steel) covering a typical 15-year interval between and prior to Type A tests that would demonstrate to the NRC staff the licensees understanding and proper implementation of the requirement in Section 9.2.3.2 of NEI 94-01, Revision 2-A. Please note that the NRC staff is not looking for repetition of regulatory requirements and code provisions, as was provided in the LAR, but how they are implemented in order to meet the requirement. Please provide an approximate explicit schedule of containment inspections, in tabular format, covering a typical 15-year ILRT interval at ANO-2that would clearly and explicitly demonstrate how the requirement in Section 9.2.3.2 of NEI 94-01 would be met. Please provide this information for (a) concrete and (b) steel liner components of the containment pressure boundary. Since the last Type A test at ANO-2 was conducted in November 2000, the next one would be scheduled to be performed by November 2015 if the ILRT interval is extended. ANO-2 could provide a schedule covering this period as a typical example. An example of such an inspection schedule for steel (only) containment surfaces based on Subsection IWE can be found in Table 1 of the NRC Safety Evaluation report for Nine Mile Point, Unit 2 (ML100730032).
RAI-2
The licensees response to Condition 3 in the LAR, submitted June 17, 2010, relates only to the accessible areas of the containment structure potentially subject to degradation. Please provide information of instances during implementation of the containment ISI program in accordance with IWE/IWL at ANO-2, where existence of or potential for degraded conditions in inaccessible areas of the concrete containment structure and metallic liner were identified and evaluated based on conditions found in accessible areas, as required by 10 CFR 50.55a(b)(2)(viii)(E) and 10 CFR 50.55a(b)(2)(ix)(A). If there were any instances of such conditions, discuss the findings and actions taken.
RAI-3
Condition 3 in Section 4.1 of the NRC SE for NEI 94-01, Revision 2-A, requires that licensees address the areas of containment structure potentially subject to degradation. Section 3.1.3 of the NRC SE, in part, states that licensees referencing NEI 94-01, Revision 2-A, in support of a request to amend their TS should also explore/consider such inaccessible degradation susceptible areas in plant-specific inspections, using viable, commercially available non-destructive examination (NDE) methods (such as boroscopes, guided wave techniques, etc.- see Report ORNL/NRC/LTR-02/02, "Inspection of Inaccessible Regions of Nuclear Power Plant Containment Metallic Pressure Boundaries," June 2002 (ADAMS Accession No. ML061230425), for recommendations to support plant-specific evaluations). Please refer to NRC SER Section 3.1.3 and 2
Resolution of NEI Comment 6, for a complete discussion of areas potentially subject to degradation and background for Condition 3.
The staff's intent of this statement in the SER is that licensees should explore and consider NDE techniques such as those discussed in the reference or other methods for inspections of inaccessible degradation-susceptible areas of the containment pressure boundary to support plant-specific evaluations of inaccessible areas, as these advanced technologies become commercially available and viable for implementation in practice in the future. While the staff understands that these techniques may not be commercially viable at the present time, the licensee is requested to identify areas in the ANO-2 containment that are inaccessible and degradation-susceptible, and acknowledge that these NDE technologies would be explored and considered in the future for the examination of inaccessible degradation-susceptible areas of the containment, as these technologies become commercially viable.
3